Clash detection simulator: hard, clearance and duplicate clashes
A hard clash is two solids that intersect by more than the tolerance; a clearance clash is anything closer than the tolerance; a duplicate is the same element modelled twice. In the sample ceiling zone below, a Hard test at 0 mm finds 3 clashes, Hard (Conservative) 4, and Clearance at 100 mm 6. Edit any element, set statuses and re-run, build a clash matrix, and turn a schedule into a CSV for Navisworks TimeLiner.
Rules from Autodesk Navisworks help (Clash Detective glossary, Select and Results tabs, TimeLiner CSV import) · tolerances from the NZ BIM Handbook 2023 · checked against an independent solution (1,337 checks at build) · Updated 24 Nov 2026
Which elements clash, by how much, and how does the answer change with the test type, the tolerance and the selections?
| ID | Element | Discipline | Shape | 1 | 2 | 3 | 4 | 5 | 6 | |
|---|---|---|---|---|---|---|---|---|---|---|
| E1 | ||||||||||
| E2 | ||||||||||
| E3 | ||||||||||
| E4 | ||||||||||
| E5 | ||||||||||
| E6 | ||||||||||
| E7 | ||||||||||
| E8 | ||||||||||
| E9 | ||||||||||
| E10 | ||||||||||
| E11 |
All sizes in mm. Box: 1-6 = x from, x to, y from, y to, z bottom, z top. Pipe: 1-2 = start and end along its run, 3 = its other plan coordinate (y for a pipe along x), 4 = centre height z, 5 = outside diameter. The sample: a 6 × 6 m bay, slab soffit at 3,600, 300 × 450 beams both ways, a 400 × 400 column copied by mistake (E5), a ceiling at 2,700, a 600 × 400 duct, a Ø100 water pipe, a Ø90 sprinkler main, a Ø75 drain modelled 200 mm too high (inside beam B1) and a 300 × 100 cable tray.
Hard: reports pairs that overlap by more than the tolerance; the distance is negative. To find the copied column, choose Duplicates with Structure in both selections.
| Clash | Items | Distance | Point x, y, z |
|---|---|---|---|
| Clash1 | Beam B2 (along y) × Drain P3 Ø75 (wrong offset) | -237.5 mm | 3,000, 3,000, 3,400 |
| Clash2 | Beam B2 (along y) × Duct D1 600 × 400 | -150 mm | 3,000, 4,300, 3,225 |
| Clash3 | Beam B2 (along y) × Sprinkler main P2 Ø90 | -95 mm | 3,000, 1,000, 3,200 |
- One more pair overlaps but its surfaces never cross (the drain inside beam B1): this simulator assumes the Normal Hard method misses it, and Hard (Conservative) reports it.
Set each clash's status, assign it and comment, change the model, and run the same test again: which clashes turn Resolved, stay Active or come up New?
| Clash | Items | Status | Assigned to | Comment |
|---|
The clashes come from tab 1 with its test settings. Every clash starts New.
| Items | Before | After the re-run |
|---|
- Press "Run the test again". The default lowers the duct 200 mm: clear of beam B2, but now into the ceiling.
| Course word | In Navisworks | How |
|---|---|---|
| approved | Approved | Set by hand; Navisworks records who approved it and when, and keeps it Approved when the test runs again. |
| neglected (taken care of later) | Reviewed (or Active) + Assign + comment | Navisworks has no 'neglected' status. Mark it Reviewed, assign it to the trade and write why it waits; it comes back on every run until the model changes. |
| resolved | Resolved | Change the model and run the test again: a clash that is no longer found turns Resolved by itself. Marking it Resolved by hand does not stick: if it is still there, the next run makes it New. |
Which discipline pairs do we test, with which test type and tolerance, and can I hand the table to the team as a CSV?
| Arch | Str | Mech | Plumb | Fire | Elec | |
|---|---|---|---|---|---|---|
| Arch | ||||||
| Str | · | |||||
| Mech | · | · | ||||
| Plumb | · | · | · | |||
| Fire | · | · | · | · | ||
| Elec | · | · | · | · | · |
Type H-25 (Hard, 25 mm), C-50 (Clearance, 50 mm), D-0 (Duplicates) or n/a, the notation of Qatar's Ashghal standard. Defaults: the New Zealand BIM Handbook's coordination tolerance schedule, ~100 / ~50 / ~25 mm at preliminary / developed / detailed design for Arch vs Other, Structural vs Other, Mechanical vs Other and Mechanical vs Mech. It names no test type (Hard is our choice) and has no row for the other 8 cells, so they start n/a. Hover a cell for its source.
Tasks, durations and finish-to-start links: when does each start and end, which tasks are critical, and what CSV does TimeLiner import?
| ID | Task | Days | After (IDs) | Type | Elements (IDs) | |
|---|---|---|---|---|---|---|
Durations in working days; "After" lists finish-to-start predecessors (the task starts the working day after the last of them ends). Elements are the IDs from tab 1. Forward and backward pass only, no lags or other link types: for a full schedule use Primavera P6 or MS Project and import it.
| ID | Task | Start | End | Float |
|---|---|---|---|---|
| 1 | Column C1 | 2026-12-14 | 2026-12-15 | 0 |
| 2 | Props and shuttering | 2026-12-16 | 2026-12-30 | 6 |
| 3 | Beams B1, B2 and slab S1 | 2026-12-16 | 2026-12-19 | 0 |
| 4 | Curing | 2026-12-21 | 2026-12-29 | 0 |
| 5 | Duct D1 | 2026-12-30 | 2027-01-01 | 1 |
| 6 | Pipes P1, P2, P3 | 2026-12-30 | 2027-01-02 | 0 |
| 7 | Cable tray CT | 2026-12-30 | 2026-12-31 | 2 |
| 8 | Ceiling CL | 2027-01-04 | 2027-01-06 | 0 |
building (green) built temporary demolishing not yet / hidden in no task
- In TimeLiner, open the Data Sources tab, click Add and choose CSV Import, then open the CSV from tab 4.
- In the Field Selector, tick Row 1 Contains Headings.
- Choose Use Specific Date/Time Format and type yyyy-MM-dd HH:mm.
- Map Synchronization ID, Task Name, Display ID, Task Type, Planned Start Date and Planned End Date to the columns of the same name.
- Build the tasks from the data source, then attach each task to its selection set and run the simulation.
Type the numbers from your clash report and schedule: do the statuses add up, does the tolerance hide clashes, are the dates possible?
What is clash detection, and how does Navisworks decide what is a clash?
Clash detection takes the architecture, structure and services models together and lists every place where two elements share space or come too close, so the team fixes it in the model instead of on site. In Navisworks Clash Detective you choose two selections (A and B), a test type and a tolerance. Autodesk's glossary defines the three tolerance rules, with d the distance between two items (negative when they overlap) and s the offset between two identical items:
So a hard clash is reported only when the overlap is more than the tolerance: two elements that just touch (d = 0) are not a hard clash at tolerance 0, and a 150 mm overlap disappears from a test run at 200 mm. Clearance reports everything closer than the tolerance, and Autodesk's Select tab adds that "selecting this clash type also detects any hard clashes". A tolerance of zero on Duplicates "would therefore only detect duplicate geometry in exactly the same location".
Hard vs Hard (Conservative) vs Clearance vs Duplicates
- Hard detects "actual intersections between geometry". Navisworks checks the triangles that make up each item, which "may miss clashes between items where none of the triangles intersect", Autodesk's example being two parallel pipes overlapping at their ends.
- Hard (Conservative) "reports all pairs of items, which might clash": more thorough, with possible false positives. In the sample, the drain modelled inside beam B1 never crosses its surfaces, so this simulator assumes the Normal method misses it: Hard finds 3, Hard (Conservative) 4.
- Clearance checks "geometry within a specific distance from other geometry", for example room for pipe insulation. It is not a soft clash: soft clashes involve moving parts, which Navisworks handles by linking a test to an animation.
- Duplicates finds the same part "drawn, or referenced twice". The copied column E5 is found only by this test; in a Hard test it would sit inside its original and be missed.
How is the clash distance calculated?
For two separated elements the distance is the shortest gap between them. For boxes, with g the gap between the two intervals on each axis:
A straight round pipe along x is its length times a circle, so against a box only the y-z outline matters across the pipe:
Two pipes crossing at right angles (each passing over the other's centre line) are apart by the vertical gap between their centres less both radii. Pipes that stop short of each other at a corner have no simple formula; the simulator searches for the closest heights on both (a convex problem, solved to 0.000000001 mm).
Worked numbers from the sample: the duct (top at 3,300) runs under beam B2 (soffit at 3,150), and the Ø90 sprinkler main at 3,200 crosses under the Ø100 water pipe at 3,100:
The sprinkler main also cuts 95 mm into beam B2, the cable tray sits 50 mm below it, and the water pipe touches beam B1 exactly (d = 0). For overlapping elements Navisworks measures "the greatest penetration between a pair of triangles"; this simulator reports the shortest move along x, y or z that separates the two, which shows the same idea without triangles. The clash point is drawn where the two bounding boxes meet.
What tolerance should you use in Navisworks?
The one the project's BIM Execution Plan sets for that pair of disciplines at that stage. Autodesk describes tolerance as the way to "filter out negligible clashes, which can be assumed to be worked around on site". The New Zealand BIM Handbook's coordination model tolerance schedule (Appendix B, 2023) gives about 100 mm at preliminary, 50 mm at developed and 25 mm at detailed design, adding "this table does not infer design tolerances".
The number changes the answer. In the sample, Hard at 0, 100, 200 mm finds 3, 2, 1 clashes; Clearance at 0, 25, 100, 200 mm finds 4, 5, 6, 8. Navisworks converts what you type to the display units ("if the display units are meters and you type 6 inch, this will be automatically converted to 0.15 m"), so 0.01 typed in a model set to metres is 10 mm, and in a model set to feet it is about 3 mm. Write the unit in the report.
What happens to clash statuses when you run the test again?
Autodesk's Results tab lists five statuses and how a re-run updates them:
- New: found for the first time in this run.
- Active: found before and found again.
- Reviewed: marked by someone, often with Assign. The help does not say what a re-run does to it; this simulator assumes it stays Reviewed.
- Approved: set by hand; Navisworks records the user and time, and "if the test is run again, and the same clash is found, its status stays as 'Approved'".
- Resolved: found before but not this time, "assumed to be resolved by changes to the design file". Set by hand while the clash is still there, it comes back New on the next run.
The course asks which clashes could be approved, neglected (taken care of later) or resolved. Navisworks has no "neglected" status; tab 2 maps each word to what Navisworks does, and lets you see the re-run happen on an edited model.
What is a clash matrix?
A clash matrix is the table, agreed in the BEP, of which discipline pairs are tested, by which test and at what tolerance. Qatar's Ashghal standard (S0301, 2022) fills each cell with the distance "preceded by a C or H to indicate the type of clash", for example "H-500 for Hard clash with a tolerance of 500mm", writes "n/a" where no coordination is needed, and names each test column "_v_" row (AR_v_ST). Tab 3 builds one from the NZ tolerances and exports it as CSV. Its severity levels start with "A structural beam clashing with a main HVAC duct".
How do you build a TimeLiner schedule and import it from CSV?
TimeLiner attaches model items to tasks with dates and plays them as a 4D simulation. It has three task types: Construct (items "highlighted in green at the start of the task and are reset to Model Appearance at the end"), Demolish (red, then hidden) and Temporary (yellow, then hidden). Tab 4 works out the dates with a forward and backward pass in working days:
For the sample's 8 tasks, starting 2026-12-14 on a six-day week with 25 December off, the work ends on 2027-01-06, 24 calendar days later, and tasks 1, 3, 4, 6, 8 are critical. To import the CSV, Autodesk says the file must use commas, the Task Name "must also be mapped", and a column of unique data such as an incrementing number must be mapped to Synchronization ID. Task types other than the three must be added in the Configure tab before importing. For full scheduling with lags and resources, see the Primavera P6 course.
What 471 public reports did (as of 24 Nov 2026)
We read the text of the 471 public Skill-Lync reports of the Navisworks project (navigation, TimeLiner and clash detection), as of 24 Nov 2026, n = 471. 19 are image-only, so counts are out of 452; many answers keep their numbers in screenshots, so every count is a floor. 152 reports share four or more long sentences word for word with ten or more others. The links are examples.
- 410 / 452Describe running a clash test. report 1report 2
- 127 / 452Test architecture against structure. report 1report 2
- 42 / 452Describe Selection A and Selection B. report 1report 2
- 6 / 452Mention tolerance at all. report 1report 2
- 6 / 452Name the Hard test type. report 1report 2
- 2 / 452Name Clearance. report 1report 2
- 1 / 452Name Duplicates. report 1
- 34 / 452Type how many clashes the test found. report 1report 2
- 281 / 452Use the status Approved. report 1report 2
- 300 / 452Use Resolved. report 1report 2
- 228 / 452Use Reviewed. report 1report 2
- 21 / 452Give a count for each approved, neglected or resolved group. report 1report 2
- 159 / 452Mention colour coding the clashes. report 1report 2
- 89 / 452Save a viewpoint of a clash. report 1report 2
- 11 / 452Group clashes. report 1report 2
- 385 / 452Describe TimeLiner work. report 1report 2
- 330 / 452Add tasks by hand (Add Task). report 1report 2
- 22 / 452Import a schedule (CSV, MS Project, P6). report 1report 2
- 171 / 452Name the Construct task type. report 1report 2
- 8 / 452Type real start and end dates. report 1report 2
None names Hard (Conservative) and none mentions Self-Intersect; 12 name Demolish and 10 Temporary. Of the reports that type a clash total, 11 repeat the same sentence ("totally 15 clashes ... 4 renewed", and Renewed is not a Navisworks status); without them the median of 23 totals is 691 clashes. In 2 reports the status counts do not add up to the total they state report 1report 2; tab 5 catches that.
These are first-party counts, a starting point rather than a measure of ability.
How we checked the simulator
An independent Python script, scripts/verify/clash_detection.py, recomputes every distance, clash list, status, matrix cell, schedule date and CSV with its own code: overlap depths by bisection on an overlap test (the page uses closed-form formulas), corner distances by a ternary search (the page uses golden-section), and every gap cross-checked by alternating projections between the two solids. This page refuses to build if its code differs in any of 1,337 numbers, lists or texts (436 cases, 1,836 hand checks in the script). The cases cover touching faces, crossing, parallel, coaxial and corner pipes, boxes inside boxes, 40 random pairs, every status on a re-run, five calendars with holidays, loops and missing predecessors. Two deliberate bugs, a hard rule of "at least" instead of "more than" the tolerance and a missing half-width in the pipe overlap, each make the build fail.
What this simulator does not cover
- Real model geometry. Only boxes and straight pipes along x or y; no fittings, sloped pipes, families or triangles. Navisworks clashes the triangles of your model, so its distances differ.
- Clash rules and grouping in full. Only "items in the same file"; no composite objects, search sets or automatic grouping.
- Time-based and soft clashes. Linking a test to TimeLiner or an animation is not simulated.
- Full scheduling. Finish-to-start links only, no lags, resources or calendars per task.
Navisworks clash detection, TimeLiner and walkthroughs are a project in Skill-Lync's BIM in AEC Industry using Revit course.
Frequently asked questions
What is clash detection in BIM?
Clash detection finds places where elements from different models occupy the same space or come too close, before anything is built. In Navisworks you append the architecture, structure and MEP models, pick two selections in Clash Detective, choose a test type and a tolerance, and run it. Each result is a clash you review, assign and track.
What is the difference between a hard clash and a soft (clearance) clash?
A hard clash is two solids that actually intersect, such as a duct through a beam; Navisworks records it as a negative distance. A clearance clash is geometry closer than a set distance, such as a pipe without room for insulation. Autodesk notes that clearance is not a soft clash: soft clashes involve moving components.
What tolerance should I use for clash detection in Navisworks?
There is no single number. The project's BIM Execution Plan should set one per discipline pair and design stage. The New Zealand BIM Handbook suggests about 100 mm at preliminary, 50 mm at developed and 25 mm at detailed design. Hard tests ignore overlaps up to the tolerance, so a large value hides real clashes.
What are the clash statuses in Navisworks?
Navisworks has five: New (found for the first time), Active (found again and not resolved), Reviewed, Approved and Resolved (found before but not in this run). Approved clashes stay Approved when the test runs again. A clash you mark Resolved by hand goes back to New if the next run still finds it.
What is a clash matrix?
A clash matrix is a table of discipline pairs (architecture, structure, HVAC, plumbing, fire, electrical) that says which pairs are tested, with which test type and tolerance. Qatar's Ashghal standard writes each cell as H-500 for Hard with 500 mm or C-1000 for Clearance with 1000 mm, and n/a for pairs not coordinated.
How do I import a schedule into Navisworks TimeLiner?
Save the schedule as a comma-separated CSV with a heading row, a unique incrementing ID, task name, task type and planned start and end dates. In TimeLiner open Data Sources, Add, CSV Import, tick Row 1 Contains Headings, map Task Name and Synchronization ID (both required for CSV) and set the date format.
What is 4D BIM?
4D BIM links the 3D model to time: each element is attached to a schedule task, so you can play the construction sequence day by day. In Navisworks TimeLiner a Construct task shows its items in green while it runs and in their normal look afterwards; Demolish shows red and Temporary yellow, then hides them.
How do I reduce false clashes in Navisworks?
Test only the pairs that matter with selection or search sets, not the whole model against itself. Set the tolerance from the BEP, use rules such as Items in Same File, group related clashes (one pipe through ten beams is one problem), and run a Duplicates test separately to catch elements modelled twice.
Related on Skill-Lync
- Material takeoff calculator (Revit schedules to quantities and cost, the project before this one)
- House plan checker (room sizes and bye-law checks of the plan you model)
- Load combination generator (the structural model's load cases)
- Revit courses compared
- All free engineering tools
Sources
- Autodesk Navisworks help (read 24 Nov 2026): Clash Detective Terminology (glossary: clash status, clearance, duplicate and hard clash, intersection method, severity, tolerance); Select Clash Test Options; Select Tab (Self-Intersect, test types, tolerance and display units); Results Tab (status updates on a re-run, Assign, Group, Compact); Set Clash Rules.
- Autodesk Navisworks help, TimeLiner: Configure Tab (Construct, Demolish, Temporary); To Set or Modify the Task Type; To Import CSV Data; Field Selector Dialog Box (field names and date/time codes); CSV Support; Export TimeLiner Schedules.
- BIM Acceleration Committee, The New Zealand BIM Handbook, Appendix B Model Coordination, V4.1 2023: coordination model tolerance schedule; high-priority issues.
- Public Works Authority (Ashghal), Qatar, ABIMS S0301 Clash Detection Matrix Template Guide, V1, 26 May 2022: clash types, H/C cell notation, test naming, severity levels.