Material takeoff calculator: Revit schedules to quantities and cost
One cubic metre of brickwork takes 500 modular bricks (190 × 90 × 90 mm, 10 mm joints) and about 0.23 m³ of wet mortar; one cubic metre of 1:1.5:3 concrete takes 8.1 bags of cement. Type the walls, openings, slabs and rooms from your Revit schedules to get every quantity, a cost with CPWD 2023 rates and the schedule formula for cost.
IS 1077, IS 2212, IS 456 Table 9 · rates: CPWD Delhi Schedule of Rates 2023 and Plinth Area Rates 2023 · Revit behaviour from Autodesk help and support articles · checked against an independent solution (2,043 checks at build) · Updated 24 Nov 2026
Wall schedule plus door and window schedule: what is the net wall area and volume, and how many bricks, bags of cement and m³ of sand?
| # | Wall | Length (m) | Height (m) | Thick (m) | Outer | |
|---|---|---|---|---|---|---|
| 1 | ||||||
| 2 | ||||||
| 3 | ||||||
| 4 | ||||||
| 5 |
| Door / window | No. | Width (m) | Height (m) | In wall # | |
|---|---|---|---|---|---|
The sample is a G+1 house we made up: 10 × 8 m on wall centre lines, 230 mm outer walls, 115 mm partitions, 3.0 m floor to floor and 150 mm slabs, so walls are 2.85 m between slabs. Every opening is taken off its wall in full. Dry factor 1.25: see "How many bricks" below. Autodesk's help only calls the wall Area and Volume "read-only", and its support site says opening areas cannot be pulled out of a wall's area, so compare these sums with Revit's own Area column.
| # | Wall | Gross | Openings | Net (m²) | Volume (m³) |
|---|---|---|---|---|---|
| 1 | Outer wall, ground floor | 102.6 | 11.64 | 90.96 | 20.921 |
| 2 | Outer wall, first floor | 102.6 | 13.23 | 89.37 | 20.555 |
| 3 | Partitions, ground floor | 39.9 | 7.25 | 32.66 | 3.755 |
| 4 | Partitions, first floor | 39.9 | 8.82 | 31.08 | 3.574 |
| 5 | Parapet | 32.4 | 0 | 32.4 | 3.726 |
- 434 bricks a m³; the bricks fill 76.9 % of the wall, wet mortar 12.15 m³, dry 15.19 m³.
- Outer walls (ticked) net 212.73 m², the rest 63.74 m²: one face each for outside and inside finishes.
Floor, beam, column and foundation schedules: how many m³ of concrete, and how much cement, sand and aggregate for a nominal mix?
| Element | No. | L (m) | B (m) | D or H (m) | Mix | |
|---|---|---|---|---|---|---|
Nominal mixes by volume, the way the course and most sites write them. For a design mix use the concrete mix design calculator (IS 10262); for the steel, the bar bending schedule calculator. This page gives no steel per m³ figure.
| Element | Mix | m³ | Bags | Sand m³ | Agg. m³ |
|---|---|---|---|---|---|
| PCC under footings | M7.5 | 2.352 | 8 | 1.11 | 2.23 |
| Footings | M20 | 5.184 | 41.8 | 2.18 | 4.35 |
| Columns 230 × 300 | M20 | 4.968 | 40.1 | 2.09 | 4.17 |
| Beams 230 × 300 below slab | M20 | 6.9 | 55.6 | 2.9 | 5.8 |
| Slabs 150 mm | M20 | 25.258 | 203.7 | 10.61 | 21.22 |
| Lintels 230 × 150 | M20 | 1.38 | 11.1 | 0.58 | 1.16 |
Finish schedules: plaster on the net wall area of tab 1, paint on the same area, floor tiles on the room areas of tab 4.
Extra area: ceilings or anything not in the wall schedule. Coverage: the Asian Paints Tractor Emulsion sheet gives 130 to 150 sq ft a litre for two coats on masonry; the lower end is 24.15 m² a litre a coat. The 2 mm joint is NITCO's spacer for wall tiles; the 5 % tile wastage is our allowance (NITCO says to buy extra tiles but gives no figure).
- Plaster: wet 6.635 m³ × 1.5 = dry 9.953 m³, split 1 : 6.
Room schedule: area, Unbound Height and the calculated volume Area × Unbound Height.
| Room | L (m) | W (m) | or area (m²) | Unbound height (m) | |
|---|---|---|---|---|---|
Revit measures room area at the wall finish by default (one project-wide setting) and always computes room volume to the wall finish; volume is off until you turn on Areas and Volumes. Unbound Height is the largest height the room's limits allow, so Area × Unbound Height can exceed Revit's Volume where a floor or roof cuts the room.
| Room | Area (m²) | Volume (m³) |
|---|---|---|
| Living | 17.55 | 50.02 |
| Dining | 9 | 25.65 |
| Kitchen | 8.1 | 23.09 |
| Bedroom 1 | 11.88 | 33.86 |
| Bath 1 | 3.15 | 8.98 |
| Stair (GF) | 7.2 | 20.52 |
| Family room | 17.55 | 50.02 |
| Bedroom 2 | 14.04 | 40.01 |
| Bedroom 3 | 11.88 | 33.86 |
| Bath 2 | 3.15 | 8.98 |
| Bath 3 | 3.15 | 8.98 |
| Stair (FF) | 7.2 | 20.52 |
Material takeoff with a cost column: every quantity from tabs 1 to 4 times a unit rate you can change.
| Item | Qty | Unit | Rate (₹) | Amount (₹) |
|---|---|---|---|---|
| Brickwork | 52.53 | m³ | 4,78,349 | |
| Concrete M20 | 43.69 | m³ | 5,02,674 | |
| Concrete M7.5 | 2.35 | m³ | 16,022 | |
| Plaster 12 mm | 552.93 | m² | 1,84,319 | |
| Paint | 552.93 | m² | 76,000 | |
| Floor tiles | 113.85 | m² | 1,76,860 |
Item rates are Delhi rates of April 2023 with material, labour, 18 % GST, profit and overheads; concrete excludes reinforcement, formwork and finishing. Basic material rates exclude GST, carriage and overheads. Rates change by city and month: type your own. Plinth area: both floors of the sample, 10.23 × 8.23 m outside, 168.39 m².
- CPWD's Plinth Area Rate 2023 for a residential RCC framed building with 3.0 m floors is ₹23,530 a m² (Delhi, 1 Apr 2023): the whole building cost. Your measured items cover 36.2 % of it; steel, formwork, doors, windows, waterproofing, plumbing and wiring make up much of the rest.
What do I type in the schedule's Calculated Value so the cost column works?
Area and Volume belong to a wall, floor or room schedule; Material: Area and Material: Volume to a material takeoff. Pick the cost field your schedule lists; "Cost" is the name in Autodesk's own example.
(Material: Area / 1 m2) * CostType: Currency, Discipline: Common- Material: Area / 1 m2 is a plain number of m², so the product is a cost.
- Type the rate into Cost: Edit Type for a wall, door or window type, or the material's Identity tab for a material takeoff.
- Open the schedule (View, Schedules, Schedule/Quantities or Material Takeoff) and add the quantity field and Cost.
- Click Calculated (Modify Schedule/Quantities, Parameters panel), name it Total cost, choose Formula, Discipline Common, Type Currency.
- Type the formula from the builder above, dividing the quantity by 1 m2 or 1 m3 so the result has no unit.
- In Formatting, select Total cost and choose Calculate totals; in Sorting/Grouping tick Grand totals.
- To get one row per type, clear Itemize every instance; each row then shows the group's total.
Type the numbers from your report: does the cost follow from the quantity and the rate, in the same units?
- 100 m² = 1076.391 sq ft; × ₹150.00 = ₹1,61,458.66.
How do you do a material takeoff from a Revit schedule?
Take each quantity the schedule gives you, in its own unit, and multiply it by a rate in the same unit. Walls give area and volume; doors and windows give counts and sizes that come off the wall; floors, beams and columns give concrete volume; rooms give area and volume. For a wall the arithmetic is:
For the ground-floor outer wall of the sample house (36 m of 230 mm wall, one door, five windows, two ventilators):
Every opening comes off in full here. Autodesk's help does not say how a wall's Area treats openings (it calls Area and Volume "read-only"), and an Autodesk support article says the opening areas cannot be extracted from a wall's calculated area, so check these sums against Revit's own Area column. If your measurement rule leaves small openings in, leave them out of the table.
How many bricks are there in 1 m³, and how much mortar?
Add the joint to each side of the brick, find how many such blocks fit in a cubic metre, and the space the bricks leave is mortar:
For the IS 1077 modular brick, 190 × 90 × 90 mm with a 10 mm joint, in 1:6 mortar:
IS 1077 lists the modular 190 × 90 × 90 mm brick and, as an allowed non-modular size, 230 × 110 × 70 mm; IS 2212 counts modular bricks with "allowance of 1 cm for mortar joint", so 20 × 10 × 10 cm each. The non-modular brick gives 434 a cubic metre and 0.231 m³ of wet mortar. For comparison, Arunachal PWD's 2023 Analysis of Rates allows 487 local bricks and 0.22 m³ of mortar for a cubic metre of 1:6 brickwork, brick size not stated.
The dry factor turns wet mortar into the loose cement and sand you buy. The default 1.25 comes from the same analysis of rates, which puts 0.25 t of cement and 1.07 m³ of sand in 1 m³ of 1:6 mortar (1.25 × 6/7 = 1.071 m³ of sand). Websites use 1.27 or 1.33; type yours. A bag is 50 kg, and IS 875 (Part 1) gives ordinary cement 1440 kg/m³:
How do you calculate concrete for a slab, and why 1.54?
The wet volume is length × width × depth. The loose cement, sand and aggregate it takes are more than that, because the voids between loose particles fill when the mix is wetted and compacted. Sites and textbooks multiply by 1.54 for that; it is a convention, not a clause of IS 456, and the reasons websites give for it vary. For 1:1.5:3 (taken as M20 in the course) per cubic metre:
As a check, Arunachal PWD's 2023 Analysis of Rates puts 0.40 t of cement (8.0 bags), 0.43 m³ of sand and 0.85 m³ of aggregate in 1 m³ of 1:1.5:3, about 1.56 times the wet volume; 1.54 gives 8.06, 0.42 and 0.84. IS 456 itself sets nominal mixes by mass, not volume: "Nominal mix concrete may be used for concrete of M 20 or lower" (9.3), and Table 9 allows at most 250 kg of dry aggregate and 30 litres of water per 50 kg of cement for M20, fine to coarse generally 1:2 by mass. The 1:1.5:3 to 1:5:10 ratios are how CPWD items and the course write mixes; the grade beside each is the course's label. For M25 and above, or to batch by mass, use the concrete mix design calculator.
How much cement and sand for plaster and paint?
Plaster works like mortar, with extra for joints and an uneven wall. Arunachal PWD's analysis of rates allows 0.144 m³ of mortar for 10 m² of 12 mm plaster, 1.20 times the finished 0.12 m³; times the mortar's 1.25 that is the default 1.5. For 100 m² of 12 mm plaster in 1:6:
The analysis of rates itself gives 7.2 bags and 1.54 m³ of sand for this, so the cement is within 3 % and the sand matches. Paint is area × coats ÷ coverage. Coverage comes from the paint's data sheet; for one interior emulsion it is 130 to 150 sq ft a litre for two coats:
Plaster on both faces of every wall in the sample is 552.93 m², about 46 litres of paint for two coats.
How do you get room volume in a Revit schedule?
Turn on volume computation (Area and Volume Computations, Areas and Volumes), or add a Calculated Value of type Volume:
The sample's 12 rooms add up to 113.85 m² and 324.47 m³. Room areas measured at the wall finish are clear floor areas. The RERA Act 2016, section 2(k), defines carpet area as "the net usable floor area of an apartment, excluding the area covered by the external walls, areas under services shafts, exclusive balcony or verandah area and exclusive open terrace area, but includes the area covered by the internal partition walls of the apartment". So carpet area is the room areas plus the partitions' footprint.
How do you add cost to a Revit schedule without "Inconsistent units"?
Autodesk's support article on the error gives the cause: the formula's units do not match the Type of the Calculated Value. Cost has no unit, so Cost × Material: Area is an area, not a currency; the fix it gives is to divide by 1 m². With the Type set to Currency:
(Material: Area / 1 m2) * Costfor a rate per m² of a material's area,(Material: Volume / 1 m3) * Costfor a rate per m³,(Area / 1 m2) * 10.7639 * Costfor a rate per sq ft on a wall schedule, since 1 m² is 10.7639 sq ft.
A schedule lists elements: one row per wall, door or room with its Area, Volume and the type's Cost ("cost of the materials for constructing the wall"). A material takeoff lists the materials inside each element, so each layer of a compound wall gets its own Material: Area and Material: Volume. Autodesk notes that layer volumes are approximated where sweeps, reveals and some joins occur. Calculate totals sums a column, but only shows with Grand totals ticked.
What 205 public reports did (as of 24 Nov 2026)
We read the text of the 205 public Skill-Lync reports of the Revit schedule and cost estimation project, as of 24 Nov 2026, n = 205. 4 are image-only, and the rest are mostly screenshots, so every count is a floor: totals, rates and formulas shown only in pictures are not counted. The links are examples.
- 180 / 201Describe a wall schedule.
- 178 / 201Describe a door schedule.
- 172 / 201Describe a window schedule.
- 179 / 201Describe a material takeoff schedule.
- 178 / 201Describe a room schedule with area and volume.
- 152 / 201Describe all five. report 1report 2
- 52 / 201Name a Calculated Value for the total cost.
- 22 / 201Type the cost formula as text (the rest show it only in a screenshot). report 1report 2
- 12 / 201Divide the quantity by 1 m³, 1 m² or 1 CF in that formula. report 1report 2
- 2 / 201Type the room volume formula (Area × Unbound Height). report 1report 2
- 12 / 201Type a unit rate. report 1report 2
- 0 / 201Name where the rate came from (a website or a schedule of rates).
- 0 / 201Type the total cost as a number.
- 0 / 201Mention the Inconsistent units error.
Of the 12 reports that type a rate, 4 quote it per sq ft and 6 give no unit at all, and none names a schedule of rates. The one slip we could count from text alone: 2 reports convert a per sq ft rate to per m² by multiplying by 0.092, which makes the cost about 117 times too small (10.764 ÷ 0.092; ×10.764 is right). report 1report 2. Tab 7 catches it. 100 reports refer to a Dynamo flowchart for the last question.
These are first-party counts, a starting point rather than a measure of ability.
How we checked the calculator
An independent Python script, scripts/verify/material_takeoff.py, rebuilds every quantity, cost, formula string and verdict with its own code. This page refuses to build if the browser code differs from it in any of 2,043 numbers or verdicts (341 cases, 27 hand checks in the script). The cases include the sample house, an opening larger than its wall, a wall of zero thickness, a door placed in a wall that does not exist, both brick sizes in 1:4 and 1:6, every nominal mix, three dry factors, every tile size with and without wastage, sq ft and cu ft rates on m² and m³ quantities, and every Calculated Value combination. Two deliberate bugs, a 1.52 dry factor and a brick height without its joint, each make the build fail.
What this calculator does not cover
- Steel and formwork. Reinforcement comes from the bar bending schedule calculator; formwork, centring and shuttering are left out, as in the CPWD concrete items.
- Doors, windows, services. Joinery, plumbing, wiring and waterproofing are not measured. The Plinth Area Rate includes them, which is why the measured items are only part of it.
- Your city's rates. The defaults are Delhi rates of April 2023. Use your state's schedule of rates or a current quotation.
- Revit's exact geometry. The calculator multiplies the sizes you type. Revit measures joins, layers and finishes in the model, so expect small differences.
Schedules, material takeoffs and cost estimation of a building are a project in Skill-Lync's BIM in AEC Industry using Revit course.
Frequently asked questions
How do I do a material takeoff in Revit?
Open View, Schedules, Material Takeoff, pick a category such as Walls, and add Material: Name, Material: Area and Material: Volume. Each layer of a compound wall gets its own row. Add Calculate totals and Grand totals to sum a column, then multiply the quantity by a rate with a Calculated Value to get cost.
How do I add cost to a Revit schedule?
Type the rate into the Cost parameter of each type or material, then add a Calculated Value of type Currency. Cost has no unit, so divide the quantity by one unit first: (Material: Area / 1 m2) * Cost. Without the division Revit reports Inconsistent units, as Autodesk's own support article explains.
How many bricks are there in 1 m³ of brickwork?
500 IS 1077 modular bricks (190 × 90 × 90 mm): with 10 mm joints each takes 200 × 100 × 100 mm. Non-modular 230 × 110 × 70 mm bricks give 434. Add wastage as your specification allows. The bricks fill about 77 % of the volume and mortar the rest.
How much cement and sand do I need for plaster?
For 100 m² of 12 mm plaster in 1:6, the finished volume is 1.2 m³. Allow 1.2 times for joints and an uneven wall and 1.25 for dry volume: 1.8 m³. One part in seven is cement, 7.4 bags of 50 kg; six parts are sand, 1.54 m³.
How do I calculate concrete for a slab?
Multiply length, width and thickness: a 5 × 4 m slab 125 mm thick holds 2.5 m³. For a 1:1.5:3 mix (M20 in the course) multiply by 1.54 for dry materials and split 1 : 1.5 : 3: about 8.06 bags of cement a cubic metre, so 20.2 bags for this slab.
Why is 1.54 used for dry volume of concrete?
Loose cement, sand and aggregate have voids between particles that the paste and fines fill when mixed with water, so 1 m³ of wet concrete needs more than 1 m³ of loose dry material. 1.54 is a site and textbook convention, not an IS 456 clause; one state analysis of rates works out to about 1.56.
What is the difference between a schedule and a material takeoff in Revit?
A schedule lists elements, one row per wall, door or room, with their parameters such as Area, Volume and the type's Cost. A material takeoff lists the materials inside each element, so a wall with brick, plaster and paint layers gives a row and an area or volume for each layer.
How accurate is a Revit cost estimate?
Only as good as the model and the rates. Revit counts what is modelled: no steel unless detailed, no formwork, labour or services. Autodesk notes layer volumes are approximated at sweeps and joins. For the sample house, the measured items come to 36 % of CPWD's plinth area rate.
Related on Skill-Lync
- Bar bending schedule calculator (the steel quantities this takeoff leaves out)
- Concrete mix design calculator (IS 10262 design mixes by mass)
- Building load calculator (dead loads of the same walls and slabs, IS 875)
- House plan checker (room sizes, FAR and ground coverage of the plan, MBBL 2016)
- Clash detection simulator (Navisworks clash tests, statuses and a TimeLiner schedule for the same Revit model)
- Stadium seating sightline calculator (riser, C-value and rake of every row, and the Dynamo parametric stadium of the same course)
- Revit courses compared
- All free engineering tools
Sources
- CPWD, Delhi Schedule of Rates 2023, Vols 1 and 2 (w.e.f. 16 Oct 2023; read 24 Nov 2026): items 4.1.3 to 4.1.10 (p. 96), 5.1.3, 5.3 (p. 105), 6.4.2 (p. 118), 11.41.2 (p. 180), 13.1.2, 13.2.2, 13.3.2 (p. 200), 13.82.2; basic rates 0367, 0982, 0295, 2602, 2757.
- CPWD, Plinth Area Rates 2023 (as on 1 Apr 2023): item 1.1.2, residential, RCC framed, 3.00 m floor height, ₹23,530 per m².
- Autodesk Revit help: Wall Instance and Type Properties, Material Takeoff Schedules, Calculated Values, schedule Formatting (Calculate totals), About Room Height, How Room Volume is Computed, Change the Room Area Boundary Location; Autodesk Support, "Inconsistent units when creating a formula for a schedule in Revit" (Apr 2026) and "How to create parameter that extract the area of openings in the walls in Revit".
- BIS: IS 1077:1992, clauses 6.1.1 and 6.1.2 (brick sizes); IS 2212:1991, clause 3.1 (1 cm joint allowance); IS 875 (Part 1):1987, Table 1 item 19 (cement 1440 kg/m³); IS 456:2000, clause 9.3 and Table 9.
- PWD Arunachal Pradesh, 2023 Analysis of Rates for Building Works: brickwork 1:6 (487 bricks, 0.22 m³ mortar a m³), mortar 1:6 (0.25 t cement, 1.07 m³ sand a m³), concrete 1:1.5:3 and 1:2:4, 12 mm plaster (0.144 m³ mortar for 10 m²).
- The Real Estate (Regulation and Development) Act, 2016, section 2(k), Gazette of India, 26 Mar 2016.
- Asian Paints, Tractor Emulsion product sheet (coverage, 2 coats 130 to 150 sq ft per litre). NITCO Tile Guide (2 mm spacer, buy extra tiles).