What does Primavera P6 do that a bar chart in Excel does not?
Primavera P6 is Oracle's scheduling software. You enter activities, link them in logic and give them durations and a calendar, and P6 works out every start and finish date, the critical path and the float for you. A bar chart only draws the dates you typed in. P6 calculates them from the logic.
Four ideas carry the whole course. An activity is one job, such as "foundations". A relationship says which job must wait for which. A calendar says which days are working days. A baseline is, in Oracle's words, "a copy, or snapshot, of project data at a given time", kept as a fixed yardstick so you can later see how far the live plan has drifted. Weeks 3, 4, 5 and 7 of the syllabus cover calendars and the work breakdown structure (WBS: the project cut into smaller and smaller pieces, like a folder tree), activities and relationships, the critical path method, and baselines.
The next three answers work the core of it with numbers you can check: the critical path, relationship types and lag, and calendars. Cost and progress tracking with earned value is not repeated here. Our free project cost budgeting workshop and project monitoring workshop cover that side.
How does P6 find the critical path? A worked example on a small building
It makes two passes through the network. The forward pass finds the earliest each job can start and finish. The backward pass finds the latest each can start and finish without delaying the end. The jobs where the two agree have no spare time, and they form the critical path. Week 5 of the course covers the critical path method and schedule network analysis.
Two kinds of spare time matter. Total float is how long a job can slip before the project finish moves. Oracle defines it as late start minus early start (or late finish minus early finish). Free float is how long a job can slip before it delays the start of any successor. Think of total float as spare time shared along a path, and free float as spare time that belongs to that job alone.
Here is a small example building, with assumed durations in working days. A site clearing and excavation 5, B foundations 10 (after A), C plinth and backfill 4 (after B), D frame and slabs 20 (after C), E brickwork 12, F electrical conduits 8 and G plumbing 6 (all after D), K switch and socket first fix 3 (after F), H plaster 10 (after E, K and G), I flooring and finishes 9 (after H), and J external works 15 (after C, and nothing waits for it). Every link is finish-to-start. This code runs both passes:
acts = { # name: (days, predecessors), listed in logical order
"A": (5, []), "B": (10, ["A"]), "C": (4, ["B"]), "D": (20, ["C"]),
"E": (12, ["D"]), "F": (8, ["D"]), "K": (3, ["F"]), "G": (6, ["D"]),
"H": (10, ["E", "K", "G"]), "I": (9, ["H"]), "J": (15, ["C"]),
}
nxt = {a: [b for b in acts if a in acts[b][1]] for a in acts}
es, ef, ls, lf = {}, {}, {}, {}
for a, (d, p) in acts.items(): # forward pass: earliest start and finish
es[a] = max([ef[x] for x in p], default=0)
ef[a] = es[a] + d
end = max(ef.values())
for a in reversed(list(acts)): # backward pass: latest start and finish
lf[a] = min([ls[b] for b in nxt[a]], default=end)
ls[a] = lf[a] - acts[a][0]
for a in acts: # activity, ES, EF, LS, LF, total float, free float
ff = min([es[b] for b in nxt[a]], default=end) - ef[a]
print(a, es[a], ef[a], ls[a], lf[a], ls[a] - es[a], ff)
print("project =", end, "days")
The columns are the job, early start, early finish, late start, late finish, total float and free float. It prints:
A 0 5 0 5 0 0
B 5 15 5 15 0 0
C 15 19 15 19 0 0
D 19 39 19 39 0 0
E 39 51 39 51 0 0
F 39 47 40 48 1 0
K 47 50 48 51 1 1
G 39 45 45 51 6 6
H 51 61 51 61 0 0
I 61 70 61 70 0 0
J 19 34 55 70 36 36
project = 70 days
The project takes 70 working days. The jobs with total float 0 are A, B, C, D, E, H and I, so the critical path is A→B→C→D→E→H→I, and 5+10+4+20+12+10+9=70. Brickwork E (12 days) beats the conduits-then-sockets route F and K (8 + 3 = 11 days) by one day. So F and K each have 1 day of total float, but F has free float 0: if F slips even a day, K starts a day late. The plumbing G has 6 days of both floats, and the external works J have 36 because nothing follows them. Check G by hand: LS−ES=45−39=6.
The catch is that float is not a gift. If F slips 2 days, it uses its 1 day of float and the finish moves to day 71. Crews sometimes treat float as free time and then discover the path has become critical. A different network, with PERT and crashing, is worked in the operations research book, and a second small example is on the Primavera P6 hub.
What are FS, SS, FF and SF links in P6, and what does lag do? A worked example
A relationship decides how two jobs are tied together. Finish-to-start (FS) means the successor cannot start until the predecessor finishes. Start-to-start (SS) ties the two starts, finish-to-finish (FF) ties the two finishes, and start-to-finish (SF) ties the successor's finish to the predecessor's start. Week 5 of the syllabus lists relationships, lag and lead.
Oracle's help describes all four, and it describes lag as "a permitted modification to these logical relationships". A positive lag is a delay. A negative lag is a lead, which lets the successor begin early. Oracle adds that lag entered in days is converted to hours using the predecessor activity's calendar. Use SS, FF and SF only where the work really overlaps, because each one makes the logic harder to read.
Say brickwork takes 12 days and plaster takes 10, with brickwork starting at day 0. This code shows four ways to link them. The lag values are assumed for the example:
brick, plaster = 12, 10 # days; brickwork starts at day 0
print("FS start", brick, "finish", brick + plaster)
print("FS +3 start", brick + 3, "finish", brick + 3 + plaster)
print("FS -2 start", brick - 2, "finish", brick - 2 + plaster)
print("SS +4 start", 4, "finish", 4 + plaster)
It prints:
FS start 12 finish 22
FS +3 start 15 finish 25
FS -2 start 10 finish 20
SS +4 start 4 finish 14
With plain FS, plaster starts at day 12 and ends at day 22. An FS link with +3 days of lag, say to let the wall dry, starts it at day 15 and ends at day 25. An FS link with -2 days of lead starts it at day 10, while the last two days of brickwork are still going, and ends at day 20. An SS link with +4 days starts plaster at day 4, once a section of wall is up, and it ends at day 14. Starting 8 days earlier than plain FS means ending 8 days earlier, which is the whole point of overlapping jobs, and also its risk: plaster can now be blocked by a wall that is not ready.
How do calendars turn working days into dates? A worked example
A schedule counts working days, but a client wants dates. A P6 calendar says which days are working days and which are holidays, and P6 uses it to convert. The same 70 working days land on very different dates under a 6-day week and a 5-day week. Week 3 of the syllabus covers calendars, their types and uses.
Take the 70-day building above. Assume it starts on Monday 1 February 2027. Assume two days off for festivals, Tuesday 9 March and Monday 29 March 2027. These holidays are made up for the example, so use your project's real list. The work ends at the end of the 70th working day. This code counts it:
from datetime import date, timedelta
start = date(2027, 2, 1) # a Monday
holidays = {date(2027, 3, 9), date(2027, 3, 29)} # assumed days off, not an official list
def finish(days, work_days): # work_days: Monday = 0 ... Sunday = 6
d, n = start, 0
while True:
if d.weekday() in work_days and d not in holidays:
n += 1
if n == days:
return d
d += timedelta(days=1)
for name, week in (("6-day week", range(6)), ("5-day week", range(5))):
f = finish(70, week)
print(name, f.strftime("%a %d %b %Y"), "->", (f - start).days + 1, "calendar days")
It prints:
6-day week Sat 24 Apr 2027 -> 83 calendar days
5-day week Tue 11 May 2027 -> 100 calendar days
On a Monday to Saturday week the building finishes on Saturday 24 April 2027, 83 calendar days after the start. On a Monday to Friday week it finishes on Tuesday 11 May 2027, 100 calendar days after. That is 17 calendar days later for the identical logic and the identical 70 days of work. Check the 6-day case by hand: the 2 holidays use up 2 working days, so 72 days are needed. That is exactly 12 weeks of 6 days, so the finish is the Saturday that ends week 12, which is 11 weeks and 5 days after Monday 1 February: Saturday 24 April.
This is why choosing the right calendar matters before anything else. A wrong calendar shifts every date in the plan, even when the logic is perfect.
What does the course cover, and what do you build?
It is 12 weeks of project planning and Primavera P6, recorded as 72 sessions of about 22 hours in all, with 2 projects. The tool is Primavera P6. It starts with planning fundamentals and ends with reports and exports.
- Weeks 1 and 2: project planning and management, the iron triangle of scope, time and cost, the project lifecycle, contracts, and a project case study.
- Weeks 3 and 4: projects, calendars and the work breakdown structure in P6, then activities, sequencing in construction and demolition, activity codes and user defined fields.
- Weeks 5 and 6: the critical path method, schedule network analysis, relationships, lags and leads, then grouping, filtering, formatting and tracing logic.
- Weeks 7 to 9: baselines and budgeting, resources and costs including resource levelling, then updating progress and tracking.
- Weeks 10 to 12: risks, issues and thresholds, the P6 Visualizer, then reports, batch reports, import and export, and check in and check out.
The 2 projects are "Developing a realistic schedule to construct a main school building (G+2)", with parking, internal roads, architectural, furniture and electrical fittings, and "Developing the project schedule of the 100m WBM road construction project", a resource loaded schedule for a 100 m road. The lesson titles on the learning platform are only "Week 1 Session 1" and so on, so this page describes lessons by the syllabus.
Three sessions are free to watch: Week 1 Session 1, Session 2 Part 1 and Part 2. They cover the scale of the construction sector, what planning means, and the iron triangle of scope, time and cost.
Does learning Primavera P6 lead to jobs?
Our records cannot show it for this course. As of 23 Nov 2026, none of Skill-Lync's 3,905 placement records names this course or the Post Graduate Program in Construction Project Management. A cut by job title finds a small civil group.
- Title or role containing planning/planner, scheduler, quantity survey*, site engineer, estimat*, Primavera or construction: 34 records, from 2021 (1), 2022 (5), 2023 (14), 2024 (13) and 2025 (1). 30 of the 34 came from the Master's in Civil Engineering program. All 34 disclosed pay, with a median of ₹3.1 LPA and a range of ₹1.2 to ₹12 LPA. Employers include Rohan Builders, L&T Construction, Casagrand and Adarsh Developers.
This is a role cut, not an outcome of this course. 34 out of 3,905 is thin. The sample is self-reported by learners, covers 2019 to 2026, and is mostly 2021 to 2023 starting offers. Pay in this group is early-career pay, not a range to expect.
So read the course as a skill. A schedule you can build, explain and update, such as the school building or road from the two projects, is what a site or planning interview tests. For other courses to pair it with, see the Post Graduate Program in Construction Project Management.
Which Skill-Lync construction planning course fits you?
| Course | Length | Projects | Tools | Fee |
|---|
| Construction Planning using Primavera P6 (this page)Planning and scheduling in Primavera P6, 22 h | 12 weeks, 22 h | 2 | Primavera P6 | ₹40,000 |
| Project Management Using PrimaveraPrimavera P6 project management, 20 h | 12 weeks, 20 h | 2 | Primavera P6 | ₹40,000 |
| Construction Project Management FundamentalsConstruction project management basics, 25 h | 12 weeks, 25 h | 2 | - | ₹40,000 |
| Project Cost ControlBudgets and cost control, 18 h | 12 weeks, 18 h | 2 | - | ₹40,000 |
| Project Progress Measurement and ReportingProgress measurement and reporting, 20 h | 12 weeks, 20 h | 2 | - | ₹40,000 |
| PG Program in Construction Project ManagementThe full 24-week PG program, 144 h | 24 weeks, 144 h | 16 | Primavera P6, MS Excel, Power BI | ₹2,75,000 |
Lengths, projects and fees are taken from each course page on 23 Nov 2026; fees are the Premium plan in INR, including all charges.