What is the difference between RCC and PSC, and what does this course cover?
RCC is reinforced concrete: steel bars carry the tension that concrete cannot. PSC is prestressed concrete: steel tendons are pulled tight so the concrete is already squeezed before any traffic arrives. The course covers both for bridge decks in 12 weekly sessions, from solid slabs in week 2 to PSC I girders in week 5 and box girders in week 6.
Think of a row of books on a shelf. Held flat from the ends, they fall apart. Squeeze the two ends hard and you can lift the whole row, because the squeeze keeps every joint shut. Prestress is that squeeze, applied to a girder.
There are two ways to apply it. In pre-tensioning the steel is stretched first, the concrete is cast around it, and the ends are released once the concrete has bonded to the steel. This suits girders made in a factory casting bed. In post-tensioning the concrete is cast first with empty ducts inside it, and the tendons are pulled through the ducts and locked off at anchorages after the concrete has set (source: Wikipedia, "Prestressed concrete", read 24 Nov 2026). Week 5 of the syllabus covers the differences between the two, bonded and non-bonded tendons, and long-term effects.
The rest of the 12 weeks, from the syllabus: ribbed slabs and grillage models (weeks 3 and 4), strut-and-tie analysis of local regions (weeks 7 and 8), portal and integral bridges (week 9), composite plate girders and trusses (week 10), long-term effects (week 11) and construction stage analysis (week 12). The tool is LUSAS, and there are 2 projects. One analyses a concrete bridge over a river from site details. The other covers a bridge over an industrial site with construction stage, prestress, composite and joint analysis.
How does prestress keep a girder out of tension? A worked example
Prestress puts a compression into the girder that is large enough to cancel the tension the loads cause. Add three stresses at each fibre: the squeeze P/A, the bending from the squeeze acting off-centre, and the bending from the loads. Week 5 of the course starts from why prestressing beats mild reinforcement and uses stress-based checks.
Here is the idea in numbers. Stress is force per area, and 1 MPa is 1 N per mm². The section modulus Z is a number for how well a cross-section resists bending, and for a rectangle Z=bh2/6. The eccentricity e is how far below the centre the tendon force P acts. Compression is positive, and M is the bending moment from the loads:
σt=AP−ZPe+ZM
σb=AP+ZPe−ZM
These are the standard beam flexure formula plus the axial term. The values below are assumed, not from a code. The section is a 300 mm by 600 mm rectangle, the span is 12 m, P=1200 kN, e=150 mm, concrete weighs 25 kN/m³, and the total service load is 10 kN/m:
b, h = 300, 600 # mm, assumed rectangular section
L = 12.0 # m, simple span
P, e = 1200e3, 150.0 # N, mm: prestress force, eccentricity below centroid
A = b * h # mm2
Z = b * h**2 / 6 # mm3, section modulus
wg = 0.18 * 25 # kN/m, self-weight (0.18 m2 x 25 kN/m3 assumed)
w = 10.0 # kN/m, total service load (assumed)
def fibres(P, M): # M in kNm; returns (top, bottom) in MPa, + = compression
m = M * 1e6 / Z
return P / A - P * e / Z + m, P / A + P * e / Z - m
for name, P_, M in [("support, M=0", P, 0), ("transfer, self-weight", P, wg * L**2 / 8), ("service", P, w * L**2 / 8)]:
t, bt = fibres(P_, M)
print(f"{name:22s} M={M:6.1f} kNm top {t:6.3f} bottom {bt:6.3f} MPa")
print("no prestress, service: bottom", round(-(w * L**2 / 8) * 1e6 / Z, 3), "MPa")
It prints:
support, M=0 M= 0.0 kNm top -3.333 bottom 16.667 MPa
transfer, self-weight M= 81.0 kNm top 1.167 bottom 12.167 MPa
service M= 180.0 kNm top 6.667 bottom 6.667 MPa
no prestress, service: bottom -10.0 MPa
So A=180,000 mm² and Z=1.8×107 mm³. The squeeze alone gives P/A=6.667 MPa, and the off-centre part gives Pe/Z=10.0 MPa. Under the full service moment of 180 kNm, the bending term M/Z is also 10.0 MPa. They cancel and the whole section sits at a uniform 6.667 MPa of compression, with no tension at the bottom. Without prestress the same load puts 10.0 MPa of tension on the bottom fibre, and concrete is much weaker in tension than in compression, so it would crack.
Here is the catch. At the support the load moment is zero, so the off-centre squeeze pulls the top fibre into 3.333 MPa of tension while the bottom takes 16.667 MPa of compression. One reason deeper girders use draped or harped tendons, which curve up toward the ends, is to move the force back toward the centre there. A real I-girder also has different top and bottom values of Z, and a real design follows the bridge code. Use this as a feel for the mechanism, not as a design.
How can a curved tendon lift a girder? A worked example
A tendon that curves upward toward its ends pushes up on the concrete along its length, like a bowstring pulled against a bow. For a parabolic tendon with sag e over span L, the push is the same as an upward uniform load of 8Pe/L2. That makes prestress easy to compare with the loads.
Where the number comes from: at midspan the tendon force P acts at distance e from the centre, so it gives a moment Pe. A uniform load w on a simple span gives wL2/8 at midspan. Set them equal:
w=L28Pe
Take the same girder as the last answer. The P is in kN and the e in m, so w comes out in kN/m:
P, e, L = 1200.0, 0.150, 12.0 # kN, m, m (same girder as before)
w_up = 8 * P * e / L**2 # kN/m, upward load from a parabolic tendon
print("equivalent upward load:", round(w_up, 3), "kN/m")
print("moment it cancels at midspan:", round(w_up * L**2 / 8, 1), "kNm = P x e =", round(P * e, 1), "kNm")
print("service load 10 kN/m: net", round(10.0 - w_up, 1), "kN/m")
print("self-weight 4.5 kN/m: net", round(4.5 - w_up, 1), "kN/m (negative = upward)")
It prints:
equivalent upward load: 10.0 kN/m
moment it cancels at midspan: 180.0 kNm = P x e = 180.0 kNm
service load 10 kN/m: net 0.0 kN/m
self-weight 4.5 kN/m: net -5.5 kN/m (negative = upward)
The tendon lifts with 10.0 kN/m, which is exactly the assumed 10 kN/m service load. Engineers call this a balanced load. At that load the girder carries no net bending from the loads, which matches the uniform stress in the last answer. A parabolic tendon also rises to the centre of the section at the supports, so its eccentricity there is zero and the 3.333 MPa of top tension that the straight tendon in the last answer causes at the support disappears. With only the 4.5 kN/m self-weight on the girder, the net is 5.5 kN/m upward, so the girder arches up slightly. The girder also meets its loads in steps as it is built, which is what week 12, construction stage analysis, is about.
In a LUSAS or grillage model you do not apply this by hand. You describe the tendon profile and force, and the software works the effect out stage by stage. The hand number is the check that tells you the model is sensible.
What is loss of prestress, and does the girder survive it? A worked example
Loss of prestress is the drop in tendon force after stressing. The force you put in is not the force you keep. FHWA groups the causes into instantaneous losses (anchorage set, friction and elastic shortening) and time-dependent ones (creep, shrinkage and relaxation) (source: FHWA, fhwa.dot.gov/bridge/Lrfd/pscus054.cfm, read 24 Nov 2026). Weeks 5 and 11 cover creep, shrinkage and prestress losses.
In plain words: elastic shortening is the concrete shortening as it is squeezed, which slackens the tendon. Creep is concrete slowly squashing further under a constant squeeze, like a foam cushion that stays dented. Shrinkage is concrete getting smaller as it dries. Relaxation is steel under constant stretch slowly losing some of its pull. Friction is a post-tensioned tendon rubbing against its duct, so the force falls along the length. A bridge code gives equations for each. This page does not quote the code percentages. Read the current code for those.
To see why the losses matter, reuse the girder and take the bottom fibre at the full service moment. The loss fractions are assumed to show the trend, not code values:
b, h, e, L = 300, 600, 150.0, 12.0
A, Z = b * h, b * h**2 / 6
M = 10.0 * L**2 / 8 # kNm service moment
for loss in (0.0, 0.10, 0.20, 0.30): # assumed losses, not code values
P = 1200e3 * (1 - loss)
bot = P / A + P * e / Z - M * 1e6 / Z
print(f"loss {loss:4.0%} P = {P / 1e3:6.0f} kN bottom {bot:6.3f} MPa")
It prints:
loss 0% P = 1200 kN bottom 6.667 MPa
loss 10% P = 1080 kN bottom 5.000 MPa
loss 20% P = 960 kN bottom 3.333 MPa
loss 30% P = 840 kN bottom 1.667 MPa
Each 10% of lost force takes 1.667 MPa off the bottom fibre, because P/A+Pe/Z=16.667 MPa per full force and the load takes 10.0 MPa away. The bottom reaches zero stress at a 40% loss, since 0.6×16.667=10.0. In this simple case the girder stays in compression at the assumed 20% loss, with 3.333 MPa left. The point is that the margin shrinks quickly if losses are underestimated. Week 11 also covers the parasitic moments that creep and shrinkage cause in continuous prestressed bridges and composite girders.
What is LUSAS, and what is grillage analysis?
LUSAS is finite element analysis software. Finite element means the structure is cut into many small pieces whose behaviour is simple, and the computer solves them all together. LUSAS makes a bridge version used for analysis, design and assessment of bridges. The course uses it for grillage and shell models, and grillage modelling starts in week 3.
On its Bridge page, the maker says it handles simple grid/grillage and slab structures and has options for more advanced bridges, including staged construction, creep, prestress and post-tensioning analysis (source: lusas.com/products/index.html and /products/bridge_tour_overview.html, read 24 Nov 2026).
A grillage replaces the deck with a grid of beams, like the rafters and cross-pieces of a floor frame. Long beams stand for the deck along the span and short ones for across it. Each beam is given the stiffness of the slab strip it replaces, and the computer shares the wheel loads between them. Week 3 introduces grillage modelling for voided slabs and week 4 gives examples with grillage, shell and beam models for ribbed slabs. The syllabus also lists hand calculations and strut-and-tie models next to the computer models. The prestress arithmetic above is the sort of hand check the course expects you to keep, because a model can run without errors and still be wrong.
If the beam theory is new to you, the Strength of Materials book has a chapter on bending and shear stresses in beams. The RCC beam and column design calculator covers the reinforced concrete side.
Can I try the course before enrolling? What do the free lessons teach?
Yes. The first 3 lessons are free on the free course page. The course has 48 lessons in all, about 23 hours of recordings, and the rest are locked.
Lesson 1 covers concrete as a material: cement, water and the hydration reaction, why 28-day strength is used for design, and uncracked against cracked beam behaviour. Lesson 2 is an Excel example for a 500 mm by 300 mm beam, finding a cracking moment, an ultimate capacity and an over-reinforcement check. Lesson 3 explains how site, labour and construction method drive the choice of a concrete bridge form, and compares slabs, ribbed slabs, precast beams, box girders, portal frames and others against typical span ranges. The prestress examples on this page are different from lesson 2: they use a prestressed section where lesson 2 uses a reinforced one.
Lessons after the third are locked, so this page describes them by title only. Some titles from the LMS list: "Pre-stressing in Engineering: Types, Properties, and Calculations", "Design of Pre-Stressed Concrete Box Girders" and "Thermal Loading on Integral Bridges: A Simple Example".
For where this course fits, it is part of the Post Graduate Program in Bridge Design and Analysis. See the bridge design course comparison for fees and options.
What jobs do learners from this course get?
The honest answer is that the data is thin. As of 24 Nov 2026, Skill-Lync has 3,905 placement records, a self-reported learner sample that is mostly 2021 to 2023 starting offers. None names this course. The Post Graduate Program in Bridge Design and Analysis, of which it is a part, has only 4 records.
By program name, those 4 are from 2022 (1) and 2023 (3), and 3 disclosed a salary: median ₹2.4 LPA, range ₹1.4 to ₹8.0 LPA. Employers are RD Civil Solutions (2), WSP and Maps Global CivilTech. That is too few to say anything about pay.
By role, 42 records have "bridge" or "structural" in the role or job title, from 2021 (6), 2022 (3), 2023 (22), 2024 (7) and 2025 (4). 41 disclosed a salary: median ₹3.75 LPA, range ₹1.4 to ₹10 LPA. 31 of the 42 came from the Master's in Civil Engineering program and 3 from the bridge program. Only 4 have "bridge" in the title. Treat these as starting offers, not a promise of any job or salary.
Which Skill-Lync bridge course fits you?
| Course | Length | Projects | Tools | Fee |
|---|
| Design of RCC and PSC Superstructures using LUSAS (this page)Concrete deck design: slabs, PSC girders, LUSAS | 12 weeks, 23 h | 2 | LUSAS | ₹40,000 |
| PG Program in Bridge Design and AnalysisThe full bridge program, loads to foundations | 48 weeks, 89 h | 14 | STAAD.Pro, Autodesk Structural Bridge Design | ₹2,75,000 |
| Design loads considered on bridgesLoads on bridges, the first step | 12 weeks, 10 h | 2 | STAAD.Pro | ₹40,000 |
| Design of Bridge Substructures / Piers using STAAD.ProPiers and substructure in STAAD.Pro | 11 weeks, 21 h | 2 | STAAD.Pro, Autodesk Structural Bridge Design | ₹40,000 |
| Design of Bridge Foundations using STAAD.ProScour, pressure and pile foundations | 12 weeks, 23 h | 2 | STAAD.Pro | ₹40,000 |
| Reinforced Cement Concrete DesignRCC design basics before bridges | 12 weeks, 32 h | 2 | STAAD.Pro | ₹40,000 |
Lengths, projects and fees are taken from each course page on 24 Nov 2026; fees are the Premium plan in INR, including all charges.