Week 10 Challenge
1. AIM:
Purlin & Girts number determination problem
Calculate total number of purlins and girts required for the building with following inputs



Create nodes as shown

Add beams to complete the structure

Insert nodes for purlins


To include the brick wall height of 2m , insert a node at 2m in the columns

Add nodes for the girts




2. AIM:
Taper the beam according to BMD envelope
For the STAAD file attached. For given loading taper the beam for the BMD envelope and check utility ratio within limit. (Design Parameter is already applied)
Procedure:
Download and open the attached file in StaadPro

Check the loadings and parameters applied

Now run the analysis

Check the utilization ratio

Now check the BMD for envelope load. Enable beam numbers in Label settings


|
Member Name |
Tag |
Utility Ratio |
Remarks |
|
End Column |
1 |
0.634 |
The column is utilized for 63.4% only. |
|
Middle Column |
5 |
0.863 |
The column is utilized for 86.3% only. In this column no moment is to be transferred as moment is released. |
|
End Column |
2 |
0.598 |
The column is utilized for 59.8% only. |
|
Rafter 1 |
3 |
0.866 |
The Rafter is utilized for 86.6% only. |
|
Rafter 2 |
4 |
0.866 |
The Rafter is utilized for 86.6% only. |
Now go to Analytical modeling and check the properties table

Check the node to node distance under Utilities - Node tools

Now modify the tapered section for the end columns to match with the BMD


Run the analysis to check the utilization ratio
We can see that the utilization ratio is very small. So we can decrease the tapered member size



So decrease it further more


Hence end columns are OK
Now add nodes to the beams

Assumption from gravity analysis standpoint is that the point of contraflexure in beams is at 0.2L from the column = 0.2 * 25.028 = 5m from either end of the nodes

The following are the tapered sections assumed for the members











Now check for the utilization ratio



3. AIM:
Determining Wind load for certain category and condition as per IS 875 Part 3 :2015
An Industrial building of plan dimension 10m x 5m to be constructed (as in Figure below). Building is situated in Chennai. Find the wind pressure on the wall of the building. Assume wall opening as 15 %. Bay spacing = 2.5m.


Procedure:
Step 1: Design Wind speed Vz
Basic wind speed Vb = 50 m/s ( For Chennai as per IS 475 part-3 Fig. 1)
Design wind speed Vz = Vb x K1 x K2 x K3 x K4
Where K1 is Probability factor (risk coefficient) taken from Table 1
Considering general building and structure and Vb =50 m/s
K1 = 1.0 for design life of structure 50 years & and for given Basic wind speed of 50 m/s
K2 is Terrain roughness & height factor taken from Table 2
For the height of 6m and Terrain category 3,
K2 = 0.91
K3 = Topography factor for Upwind slope < 3° from Clause 6.3.3
K3 = 1.0
K4 = Importance factor for cyclonic region for Industrial Structure from Clause 6.3.4
K4 = 1.15
Therefore Vz = 50 x 1.0 x 0.91 x 1.0 x 1.15 = 52.325 m/s
Step 2:-
Wind pressure Pz = 0.6 (Vz)2
Where,
Pz = wind pressure at height z in N/m2
Vz = design wind pressure at height z in m/s
Therefore
Pz = 0.6 x (52.325)2 = 1.643 kN/m2
Step 3:-
Design wind pressure Pd = Kd x Ka x Kc x Pz
Where,
Kd = wind directionality factor 1.0 for cyclone affected region
Ka = Area averaging factor 0.9 for tributary area < 25 m2
(Tributary area = 6 x 2.5 = 15 m2)
Kc = combination factor 0.9
for framed structure
Therefore
Pd = 1.0 x 0.9 x 0.9 x 1.643 = 1.331 kN/m2
Step 4:-
Wind load acting in a direction normal to the individual structural element or cladding unit
F = (Cpe – Cpi) x A x Pd
Where,
Cpi = internal pressure coefficient
Cpi = +0.5 and -0.5 for opening of 15% of wall area i.e. medium permeability (Clause 7.3.2.2 of IS :475, part 3)
External pressure coefficient:
L = 10 m; w = 5 m; h = 6 m
h/w = 6 / 5 = 1.2
l/w = 10 / 5 = 2
Thus as per table 5 of clause 7.3.3.1 of IS:475, Part 3
For 1/2 < h/w < 3/2 and 3/2 ≤ l/w < 4


On roof:


- AIM:
Find support reaction for given load. Static check problem
Mono sloped structure (20 degree) of width 10 m & length 30 m with bay spacing of 6 m having no wall sheeting (fully open all around) has following loads. Model the structure in STAAD. Apply Dead load, Live Load & Wind load on the structure and find the support reaction. Also perform static check if the total load applied on the structure is captured in support reaction for each load case.
Self Weight factor – 1.1
Roof Sheet loading = 0.5 kN/m2
Purlin load = 6 kN/m2
Live Load on Roof = 1.5 kN/m2
Wind Load on rafter (Pressure) = 2 kN/m2
Procedure:
Assume Frame height as 5m
Support as Fixed.
Total Dead Load = 0.5 + 6 = 6.5 kN/m2
Dead Load on Main frame = 6.5 x 6 = 39 kN/m
Dead Load on Gable frame = 6.5 x 6 / 2 = 19.5 kN/m
Live Load on Main frame = 1.5 x 6 = 9 kN/m
Live Load on Gable frame = 1.5 x 6 / 2 = 4.5 kN/m
Wind Load on Main frame = 2 x 6 = 12 kN/m
Wind Load on Gable frame = 2 x 6 / 2 = 6 kN/m
- Open STAAD Software and create a New File.

Add beams to connect the nodes



Use translational repeat to create a length of 30m


Under loading, add DL, LL and WL cases



Under DL,

Dead Load on Main frame = 6.5 x 6 = 39 kN/m
Dead Load on Gable frame = 6.5 x 6 / 2 = 19.5 kN/m


Now add LL
Live Load on Main frame = 1.5 x 6 = 9 kN/m
Live Load on Gable frame = 1.5 x 6 / 2 = 4.5 kN/m


Wind Load on Main frame = 2 x 6 = 12 kN/m
Wind Load on Gable frame = 2 x 6 / 2 = 6 kN/m


Now start assigning each load to the rafters

DL:

LL:

WL:


Add parameters and perform Static Check




From this we could understand that the applied load is equal to the total reaction load
Hence static check is done