Usage of Navigation tool , Timeliner and Clash Detection test using Naviswork
Q1)
AIM:
Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class.
PROCEDURE:
let us suppose the example of project 2.
now we want to export this file to navisworks.
just go to the file option and click NWC.
file will start to export and then save it.
now go to the files and click the saved file.
the file will open in the naviswork as shown in last picture.



Q2)
AIM :
Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file.
PROCEDURE:
open navisworks ,go to save viewpoints option,select record and after that select walk option.
take a walk through the different rooms of the building .
after the walk is finished ,click stop option.
we get a list of different frames of walk.
click on any of it to get the view.
frames are shown in below figures.









Q3)
AIM :
Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file.
PROCEDURE:
open naviswork go to the realism option beside walk.
click third person and take a walk through different rooms of building.
take the screenshots of all the rooms visited and paste here.







Q4)
AIM :
Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks
PROCEDURE:
open the architectural file in revit.
go to append and open the structural file.


we get a combination of both as shown in figure.

now go to the clash detecting option from the tab.
click both the models and rename the test and click on run test.

we get the list of all the clashes ,from here the clashes can be approved or resolved as shown.





Q5)
AIM:
Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file