Usage of Navigation tool , Timeliner and Clash Detection test using Naviswork
1.
AIM :
Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class.
INTRODUCTION :
naviswork allows user to open and combine 3d model, navigate around them in real time and review the model using set of tools including comments, redlining, viewpoints and measurements.
PROCEDURE :
- open revit and open architectural and structurral drawing of week 7 project
- go to file > select export > select nwc

- save the file to destination folder
- file will export

- do the same procedure for structural drawing
RESULT :
we have Exported the Revit architecture and structure model to Navisworks Cache file.


2.
AIM :
Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file
INTRODUCTION :
naviswork allows user to open and combine 3d model, navigate around them in real time and review the model using set of tools including comments, redlining, viewpoints and measurements.
PROCEDURE :
- open naviswork software
- go to append tab > select append > open the file


- go to viewpoint tab > select walk
- select save view point > rename the view
- select record > start the recording through room by moving mouse cursor

- after completing the animation select stop recording
- recording will be saved

RESULT :
we have Used Navigate Tool to walk around the model and walk through the rooms created and record moving as animation in Navisworks file
3.
AIM :
Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file
INTRODUCTION :
naviswork allows user to open and combine 3d model, navigate around them in real time and review the model using set of tools including comments, redlining, viewpoints and measurements.
PROCEDURE :
- go to viewport tab > select realism
- select third person and walk through the room

-


RESULT :
-we have Used Navigate tool to use Realism feature to walk through the model and recorded your moving as animation in Navisworks file
4.
AIM :
Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks
INTRODUCTION :
naviswork allows user to open and combine 3d model, navigate around them in real time and review the model using set of tools including comments, redlining, viewpoints and measurements.
PROCEDURE :
- open architecturral drawing in navis work
- in home tab > select clash detective

-
- click add test

- at below click on run test

- result comes 198 clashes occur in my drawing


RESULT :
- we have created a clash detection test between the two models.
5.
AIM :
Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file.
INTRODUCTION :
naviswork allows user to open and combine 3d model, navigate around them in real time and review the model using set of tools including comments, redlining, viewpoints and measurements.
PROCEDURE :
- open naviswork and open w7 drawing
- go to home page and select timeliner

- go to homepage ans select selection tree so that we can arrange the task properly
- add task date and attachment

- go to simulate option to animate video

- we can save the file also
RESULT:
we have used the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by added reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation.