Challenge

REVIT_Naviswork_Project- 4

1) Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class.

aim: Useing the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class.

procedure:

Open the new architectural file and open 3D view

and open the file command and then select export and then select nwc

we can see The architectural file will be exported to the naviswork in nwc format

and Open the Structural file

open the file command and then select the export and then select nwc

Then we can see the structural file will be exported to the naviswork in nwc format.

Results:

2) Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file

aim:Useing Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file

procedure:

now Open the architectural file in naviswork which is exported .

select the viewpoint and select the view as views whole project was exported.

select the record option in viewpoint and select walk

next walk through the rooms, halls, bathroom etc select the stop button after walking

on right side animation will find in which amination we can record for the rooms and halls

Results:

3) Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file

aim: Useing Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file

Procedure.

now Open the architectural file in naviswork .

open the viewpoint and select the view as views are exported from revit as whole project was exported

open the realism and click on the third person and then select the record and select walk

and Start walking through the rooms and select the stop button on the top right

we can see animation will be created in project

Results:

4) Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks

ans:

aim: Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks

procedure:

Now Open the architectural file in the naviswork and select the append in the home button

next select the new test and rename the test if you want

select the architecture and structural file and select the surface of both the file

now select the run test

we can see that Clash detection test is completed

we can view clased items if present.

if present then List the clash which can be approved with the drop down menu in the status and select as approved

now List the clash as reviewed which can be taken care later and List the clash as resolved which clash has been resolved .

after making correction then save it with appropiate name

Results:

5) Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file

aim:Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file

procedure:

Now open the structural file in naviswork

open the home tab and select timelinear

and add the tasks and attach the tasks in it

then update the actual dates like start , finish date of project

select stimulate to play the recorded task

and save it.

Results:

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.