Challenge

Preparing Schedule & Cost Estimation for a building using REVIT

1) 

 

 

Aim - To use the shortcut keys in Revit discussed in class to complete the following tasks and list them below .

Introduction - 1) Shortcut keys are generally used to save the time and increase the speed of the work 

                       2) It also increase the efficiency of the work .

                       3) In Revit if you click on View - User Interface - Keyboard Shortcuts will appear .

                       4) Following are some shortcut keys - 

                           a) Section Box - BX

                            b) Create Similar - CS

                            c)Thin Lines - TL

                            d) Visibility Graphics and override settings - VG

                            e) View Range - VR

                           f)  Reselect - Ctrl+<

                            g) Dimension - DI

                            h) Align - AL

                            i) Rotate - R

                            j) Move - MV

                            k) Copy - CO

Procedure - 

Step 1)  Section Box - BX

i) To use this command , Click on 3D view 

ii) Select the particular view which you want to see

iii) Click on that and Give command Section Box -

Step 2) Create Similar - CS

i) To create a similar element 

ii) Click on particular element and Command CS 

iii) For eg we have select Bed and created similar bed as shown in below

Step 3) Thin Lines - TL

i) This is command is used to see the line thickness of the material 

Step 4)  Visibility Graphics and override settings - VG

i) This command is used to see the visibily of the materials 

ii) You can directly edit the elements such as floor wall doors etc 

iii) Command VG 

iv) Click on Pattern and you can edit directly from here.

Step 5) View Range - VR

i) This command is used to see the view range 

ii) and increase the range of visibility in a plan view 

Step 6) Reselect - Ctrl+<

i) This command is used to Reselect the last view which we have selected

Step 7)  Dimension - DI

i) This command is used to messure the dimension 

Step 8)  Align - AL

i) This command is used to align the element 

ii) First select the line in which we have to align 

iii) Then select the element which you have to align 

iv) For eg we have align the beds which we have created by using CS command 

Step 9) Rotate - R

i) This comman is used to rotate the element 

Step 10)  Move - MV

i) This commad is used to Move the elements 

Step 11) Copy - CO

i) This command is used to Copy the elements 

Step 12) Mirror - MM

i) This commad is used to mirror the elements 

ii) Select the object - Command Mirror and specify the reference line and rotate the object .

Step 12) Array - AR

i) This commad is used to create an array of the elements . 

Results - All the Shortcuts keys are used .

2) 

Aim - To prepare a schedule of week 6 to week 8 project .

Introduction - 

1) A schedule is a tabular display of information, extracted from the properties of the elements in a project. A schedule can list every instance of

    the type of element you are scheduling, or it can collapse multiple instances onto a single row, based on the schedule's grouping criteria.

2) The schedule can be created at any point in the design process. If any changs are made in the model that affects the schedules . It

    automatically updates to reflect those changes. 

3) Using revit softwares cost estimates can also be developed. By providing the unit cost of materials, total cost can be derived.

 

Procedure 

Step 1)

i) Open the Architectural file of Project 2 which we have create in week 6 to 8

ii) Click on view tab 

iii) Click on Schedue tab 

iv) Again click on Schedule and Quantities 

Step 2) 

i) Once you click Schedule / Quantities a following dialog box will open

ii) Click on Wall 

Step 3) 

i) Once you click okay a following dialog box will open

ii) Now select the parameters whic you want 

iii) For eg Area , Count , Length etc as shown below 

Step 4 ) 

i) Click on Okay 

Step 5) 

i) Similarly we have to create a Schedule of Doors also

ii) Follow the same procdure 

Step 6) Window take off 

i) Follow the same procedure to create a Schedule of windows also 

Step 7) Material Take off - Wall 

i) Now we have to calculate the material take off for Concrete and wood  

ii) So click on Schedule - Material Take off 

iii) Select - Wall 

iv) Select the parameters as shown in fig

Step 7) Material Take off - Door 

Step 8) Material take off - Window -

Results - A Schedule is prepared for given elements 

1) Wall 

2) Door Schedule 

3) Window - 

4) Material - 

3) 

Aim - To Calculate area and volume of each room in the model and to prepare Schedule reoport .

Introduction - 

1) A schedule is a tabular display of information, extracted from the properties of the elements in a project. A schedule can list every instance of

    the type of element you are scheduling, or it can collapse multiple instances onto a single row, based on the schedule's grouping criteria.

2) The schedule can be created at any point in the design process. If any changs are made in the model that affects the schedules . It

    automatically updates to reflect those changes. 

3) Using revit softwares cost estimates can also be developed. By providing the unit cost of materials, total cost can be derived.

 

Peocedure 

Step 1) 

i) Click on view tab 

ii) Click on Schedue tab 

iii) Again click on Schedule and Quantities 

Step 2) 

i) Once you click Schedule / Quantities a following dialog box will open

ii) Click on Room

Step 3) 

i) Click on Okay 

ii) Select following parameters as shown in fig .

iii) click on okay 

Step 4) 

i) Click on Okay 

First Floor  , Second and Third floor 

Results - A Schedule Report is created .

4) 

Aim - To prepare the schedule of total cost of materials 

Introduction - 

1) A schedule is a tabular display of information, extracted from the properties of the elements in a project. A schedule can list every instance of

    the type of element you are scheduling, or it can collapse multiple instances onto a single row, based on the schedule's grouping criteria.

2) The schedule can be created at any point in the design process. If any changs are made in the model that affects the schedules . It

    automatically updates to reflect those changes. 

3) Using revit softwares cost estimates can also be developed. By providing the unit cost of materials, total cost can be derived.

 

Procedure - 

Step 1) 

i) To prepare the schedule of total cost

ii) Click on View - Schedule - Material take off 

iii) First will create Total cost of wall 

A) For wall 

i) Open the Material take off 

ii) Select the parameters as shown in below 

 iii) Click on okay 

iv) Here we can see that Cost is zero , So go to the floor plan and select the wall 

v) Click on edit and there is an option of Cost 

vi) Enter the cost 

vii) To calculate Total Cost - Add dummy parameter 

viii) Right Click and Insert the Column - Comment 

ix) Click on Dummy parameter - In Ribbon bar there is an option called Calculated 

x) Click on that - Enter the Formula as shown in below 

xi) Once you Click Okay - Tota Cost is calculated 

B) For Floor - 

i) Follow the same procedure to calulate the Total Cost of floor

ii) Following parameters are considered 

C) For Doors - 

i) Follow the same procedure to calculate total Cost of Doors 

ii) Following parameters are considered 

D) For Furnitures 

i) Follow the same procedure to calculate total Cost of Furnitures

ii) Following parameters are considered 

E) Curtain Panel 

i) Follow the same procedure to calculate total Cost of Curtain Walls 

ii) Following parameters are considered 

Results - A Material take off and Total cost of material is calculated and Schedule report is created as follows 

1) For Wall 

2) For Floors - 

3) For Doors - 

4) For Furnitures 

5) For Curtain walls -

5) Flowchart 

a) How to decide framings for a structure using Dynamo

B) If there is no water coming from the pipes

C) If request for money from client has been declined for the project

6) List the Parameters 

a) Wall - 

i) Wall type

ii) Wall description

iii) Wall length

iv) Wall thickness

v) Wall height

vi) Wall materials

vii) Wall location

viii) Material cost

ix) Structural Material 

x) Wrap 

xi) Function and Coarse pattern 

b) Floor 

i) Floor type

ii) Function and Coarse pattern 

iii) Floor area

iv) Floor Offset

v) Floor Dimensions

vi) Floor Material

vii) Floor thickness 

viii) Floor Roughness 

viii) Cost 

c) Door 

i) Door Family

ii) Door Type 

iii) Door Width 

iv) Door Height 

v) Door Thickness

vi) Functions

vii) Cost 

d) Window

i) Window Family

ii) Window Type 

iii )Window Width 

iv) Window Height 

v) Window Thickness

vi) Functions

vii) Cost 

e) Table 

i) Table Family

ii) Table length

iii) Table width

iv) Table weight

v) Table Thickness

vi) Table material

vii) Cost

f) Building 

i) Building type

ii) Building FSI ( Floor Space Index / Floor Area Ratio ) 

iii) Building perimeter

iv) Building location

v) Building Storey 

vi) Plot area

vii) Material

viii) Cost of the building 

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.