GATE Production and Industrial Engineering (PI): Industrial Engineering (time study, standard time, work sampling, therbligs, operation charts, line balancing, CRAFT layout, product design and standardisation), previous-year questions solved

Every industrial engineering question from the GATE Production and Industrial Engineering papers of 2024, 2025 and 2026, solved: time study with rating and allowances, standard time, work sampling and its standard error, therbligs and motion economy, two-handed operation charts, assembly line balancing and line efficiency, CRAFT layout exchanges, the design process and concept selection, and product standardisation. Each answer matches the official key and was recomputed by code with the numbers printed in the paper, by a second method where one exists.

Questions from official GATE PI papers (IISc Bengaluru 2024, IIT Roorkee 2025, IIT Guwahati 2026); solutions by Skill-Lync. · Updated 19 Nov 2026 · 14 questions

GATE 2024 · PI · Q.22MCQ · 1 markWork study: method study, time study and work sampling

Work sampling with many observations: which distribution is used to estimate the required sample size?

If work sampling is carried out using a large number of observations, then the required sample size is estimated using
  1. (A)Poisson distribution
  2. (B)Uniform distribution
  3. (C)Normal distribution
  4. (D)Exponential distribution

Answer: (C) Official key: C

  1. Work sampling takes many random snapshots of a worker or machine and records whether it is busy or idle. If a fraction of all moments is busy, each snapshot is a yes-or-no trial, so the number of busy observations in snapshots follows a binomial distribution with mean and variance .
  2. When is large (and is comfortably more than about 10), the binomial is very close to a normal distribution (central limit theorem). The sample proportion is then normal with standard error , and a confidence interval of standard errors, with for 95 % confidence, gives the required size for an absolute error .
  3. Poisson fits rare events with very small , uniform has no bell shape, and exponential describes waiting times. None of them describes a yes-or-no count. Hence (C).

Check: for and the largest gap between the exact binomial distribution function and a matched normal was 0.003, against 0.044 for Poisson, 0.058 for uniform and 0.552 for exponential. For the normal gap fell steadily: 0.012, 0.006, 0.003, 0.001. In 20 000 simulated studies of 400 snapshots, the estimate fell within 1.96 standard errors of the true in 94.9 % of runs. Trap: choosing Poisson because the data are counts.

Where this shows up in industry

A work-sampling study on a maintenance crew or a packing line fixes the confidence and the accuracy wanted, estimates the busy fraction from a short pilot, and then uses the normal-approximation formula to decide how many random observations to take over the coming weeks.

GATE 2024 · PI · Q.61NAT · 2 marksWork study: method study, time study and work sampling

Time study: 9 min observed, 120% rating, allowance 10% of standard time. Standard time in minutes?

In a time study, the average time taken for packaging a product in a warehouse by a worker with 120% performance rating is observed as 9 minutes. Assuming an allowance of 10% of the standard time, the standard time (in minutes) for packaging is __________ . (Answer in integer)

Answer: 12 minutes Official key: 12 to 12

  1. In a time study, the observed time is adjusted for how fast the worker was working compared with a normal pace. Normal time = observed time × rating. With a 120 % rating, a pace of 1.2 times normal: normal time = min.
  2. The standard time is the normal time plus allowances for personal needs, fatigue and unavoidable delay. Here the allowance is 10 % of the standard time, so the normal time is the other 90 %: .
  3. 12 min, equal to the key 12 to 12.

Check: 12 min minus 10 % of 12 min (1.2 min) gives back 10.8 min. Trap: taking the allowance as 10 % of the normal time gives min, which is not the key. The wording "of the standard time" is what makes the divide-by- form the right one.

Where this shows up in industry

Time-study boards set standard times for packing, picking and assembly jobs from stopwatch readings, a rating and an allowance, and the result feeds labour planning and incentive schemes. Allowances are often stated as a share of the standard shift, which is why the base of the percentage must be checked.

GATE 2025 · PI · Q.19MCQ · 1 markWork study: method study, time study and work sampling

Standard deviation of the mean proportion of idle time in a work sampling study

In a work sampling, out of observations, a worker was sitting idle in observations. The standard deviation of the mean proportion of idle time is given by
  1. (A)
  2. (B)
  3. (C)
  4. (D)

Answer: (B) Official key: B

  1. Work sampling treats each random observation as idle or not idle. With a true idle proportion , the number of idle observations in looks is binomial, so the observed proportion has variance . The standard deviation of the proportion is its square root, called the standard error.
  2. Estimate by the observed proportion , so .
  3. , which is option (B).
  4. Numerical feel: idle in gives and , that is percentage points. A simulation of 20,000 studies of 400 observations with true gave a spread of 0.0229, matching .

Trap: option (C) has the right top line but divides by , which is the standard deviation of a single yes/no observation, not of the mean of of them. Option (D) is the mean itself, not its spread.

Where this shows up in industry

Work sampling studies of idle time on shop floors and in maintenance crews quote the result as a proportion with a confidence band built from this standard error. Planners use it to decide how many random observation rounds are needed before a stated idle percentage is trusted.

GATE 2025 · PI · Q.48NAT · 2 marksWork study: method study, time study and work sampling

Standard time in seconds with 30 minutes personal time in an 8-hour shift and normal time 5 minutes

A worker is allowed half an hour personal time in a normal 8-hour shift. If the normal time for manufacturing a product is 5 minutes, the standard time (in second) is________. (Answer in integer)

Answer: 320 s Official key: 315 to 325

  1. Standard time is normal time plus allowances. Here the only allowance is personal time, which the worker gets out of the paid shift, so it is a share of the 480 minute shift.
  2. Personal allowance as a fraction of the shift: , that is 6.25 percent.
  3. Of every 480 minutes of paid time, only minutes are working time at normal pace. That is pieces per shift.
  4. Standard time per piece minutes seconds. Written as a formula, .
  5. The other common reading, adding the allowance fraction to the normal time, gives , which also lies in the key range 315 to 325 s. Either way the answer is about 320 s.

Trap: adding the whole 30 minutes to the 5 minute normal time gives 35 minutes or 2100 s. The 30 minutes belong to the whole shift, not to each piece.

Where this shows up in industry

Time-study engineers add personal, fatigue and delay allowances as a percentage of the shift when they turn observed and rated times into standard times for a labour standard. The same standard time then feeds piece-rate, capacity and line-balancing calculations.

GATE 2026 · PI · Q.50MSQ · 2 marksWork study: method study, time study and work sampling

Operation chart for assembling nuts and bolts, left-handed operator: which statements are correct

The operation chart of a method of assembling nuts and bolts for a left-handed operator has been illustrated in the figure.

Which ONE or MORE among the following options is/are CORRECT?

Operation chart for assembling a nut on a bolt, left hand on the left and right hand on the right, read top to bottom (redrawn: the paper prints the right-hand symbols at the right edge of their column). Symbols: circle is an operation, block arrow is a transport, inverted triangle is a hold, D-shape is a delay (idle). Left hand: idle, grasp the bolt, hold the bolt for a long stretch, release the assembly to the right hand, idle. Right hand: go to bin 1, pick the bolt, bring near left hand, release to left hand, go to bin 2, pick the nut, bring near left hand, screw the nut onto the bolt, grasp the assembly, move the assembly to bin 3, release the assembly.Left handRight handGo to bin 1Pick the boltBring near Left handRelease to Left handGo to bin 2Pick the nutBring near Left handScrew the nut onto theboltGrasp the assemblyMove the assembly tobin 3Release the assemblyIdleGrasp the boltHold the boltRelease the assembly toRight handIdle
  1. (A)The work distribution between the two hands is not balanced.
  2. (B)The two hands do not follow opposite motions.
  3. (C)The work is well distributed between the two hands.
  4. (D)The dominant hand of the operator performs majority of the tasks.

Answer: (A) and (B) Official key: A;B

  1. Rule (motion economy): in a two-hand operation chart both hands should start and finish together, never be idle together except for rest, move in opposite and symmetrical directions, and share the work evenly. The chart uses a circle for an operation, an arrow for a transport, an inverted triangle for a hold and a D-shape for a delay (idle).
  2. Count the symbols. Left hand: 2 operations (grasp the bolt, release the assembly), 1 hold, 2 delays, no transports, so 5 symbols. Right hand: 6 operations and 5 transports, so 11 symbols, no hold and no delay.
  3. Effective work (operations and transports): left hand 2 elements, right hand 11 elements. The left hand does only 15% of the work, far from an even 50%. The distribution is not balanced: (A) is true and (C) is false.
  4. Opposite motions: the left hand holds the bolt, and idles, while the right hand fetches, screws and moves. Both hands are doing effective work together in only 2 of 11 rows (the two hand-overs of the bolt and of the assembly), and even then the two hands do different things, not mirror-image ones. So the hands do not move in opposite, symmetrical motions: (B) is true.
  5. The operator is left-handed, so the dominant hand is the left. The left hand does the minority of the tasks. The right hand, the non-dominant one, does the majority, so (D) is false. The answer is (A) and (B).

Trap: (D) is true for most operators, who are right-handed. The question says left-handed on purpose. The chart also shows a poor method: the dominant hand is used as a vice, which a fixture could do. We read every symbol off the figure, counted them per hand and tested each option against the counts.

Where this shows up in industry

Two-hand operation charts are drawn when a bench assembly job is slow or tiring. A hand that only holds the part is the usual finding, and a jig or fixture that holds the bolt frees that hand to do useful work and can shorten the cycle.

GATE 2026 · PI · Q.62NAT · 2 marksWork study: method study, time study and work sampling

Standard output per hour from a two-element time study with ratings and a further 20% allowance

A time study was carried out for a job broken into two elements. For each element, three iterations of task were observed, and observed time was recorded. The observed times (in seconds) and the rating factor for each element are given in the table.
Work elementObserved time (seconds)Rating factor
A20; 25; 21105%
B19; 17; 1890%

If a further 20% needs to be added for allowances, then the standard output of the worker is ______ units per hour (in integer).

Answer: 76 units per hour Official key: 75 to 78

  1. Rule: normal time = average observed time rating factor. Standard time = normal time plus allowances. Output per hour = 3600 s divided by the standard time in seconds.
  2. Element A: average s. Normal time s.
  3. Element B: average s. Normal time s.
  4. Normal time of the job s. 'A further 20% to be added' means the allowance is 20% of the normal time: standard time s.
  5. Standard output , which is 76 units per hour (in integer).

Trap: if the 20% is read as a share of the standard time, the standard time is s and the output is 73.3 units per hour, outside the key. The wording 'a further 20% needs to be added' points to the first reading. Skipping the ratings gives 75.0 and skipping the allowance gives 91.6 units per hour. We recomputed the averages from the table and both allowance readings; only the added-on reading lands in the key range.

Where this shows up in industry

A time-study engineer rates each element against a benchmark pace, adds personal, fatigue and delay allowances, and publishes the standard time in seconds per piece, which then sets the line target, the labour estimate in a quotation and the base for any incentive pay.

GATE 2024 · PI · Q.19MCQ · 1 markFacility design: layout and assembly line balancing

CRAFT on a four-department layout: which department pair cannot be considered for exchange?

The following layout of four departments P, Q, R and S is provided as input to CRAFT (Computerized Relative Allocation of Facilities Technique). Which one of the following department pairs cannot be considered for exchange in CRAFT?
Layout of four departments: P and R each 20 m by 20 m on the left, Q and S each 40 m by 20 m on the right, Q above S and P above RPQRS20 m20 m20 m40 m
  1. (A)P and Q
  2. (B)R and S
  3. (C)P and R
  4. (D)Q and R

Answer: (D) Official key: D

  1. CRAFT is an improvement routine. It starts from an existing layout and tries swapping the positions of two departments, keeping the swap that cuts total material-handling cost (flow times distance) the most. A swap is only allowed for a pair that can trade places without breaking the building outline: the two departments must be adjacent (share a border) or have equal area.
  2. Areas from the drawing: P = 20 m × 20 m = 400 m², R = 400 m², Q = 40 m × 20 m = 800 m², S = 800 m².
  3. (A) P and Q share the 20 m vertical wall: adjacent, allowed. (B) R and S share the same wall in the lower row: adjacent, allowed. (C) P and R share the 20 m horizontal wall: adjacent, allowed (they are also of equal area).
  4. (D) Q is top right and R is bottom left. They touch only at the single corner point where the two walls cross, so the shared border is 0 m, and their areas are 800 m² and 400 m², not equal. Neither test is met, so Q and R cannot be exchanged: (D).

Check: the layout was rebuilt from 10 m cells and the shared border and areas computed for all four pairs; only Q and R have zero border and unequal area. Trap: treating a corner touch as adjacency. A touch at a point does not give a border along which the departments can slide into each other's place.

Where this shows up in industry

Plant layout projects use CRAFT-type exchange routines, or the same idea in commercial layout software, to test whether swapping two departments cuts forklift and conveyor travel. Planners also check each swap against walls, columns and utilities, which is why only adjacent or equal-area pairs are tried.

GATE 2024 · PI · Q.62NAT · 2 marksFacility design: layout and assembly line balancing

Three-station line with 6, 4 and T minutes at 75% efficiency: maximum T in minutes?

An assembly line consists of three work stations (S1, S2 and S3) in series to assemble a toy. The times required to perform tasks at these stations are 6, 4 and T minutes, respectively. If the efficiency of the assembly line in the steady state is 75%, then the maximum value of T (in minutes) is ____________. (Answer in integer)

Answer: 8 minutes Official key: 8 to 8

  1. On a serial line every station must wait for the slowest one, so the cycle time is the largest station time. Line efficiency = total work content / (number of stations × cycle time).
  2. The work content is min, with 3 stations.
  3. Case 1: , so the cycle time is 6 min. gives , so min.
  4. Case 2: , so station S3 is the bottleneck and the cycle time is . gives , so 8 min.
  5. Both values give 75 %, and the question asks for the maximum, so min.

Check: we scanned from 1 to 20 min in steps of 0.001 min and the efficiency crossed 75 % at 3.5 and 8.0 only. At : . For the efficiency is 66.7 % and for it is 81.0 %. Trap: using only the case where is not the bottleneck, which gives 3.5 min.

Where this shows up in industry

Line-balancing studies on assembly lines compare each station time with the cycle time and report balance efficiency and balance delay. A slower station sets the pace for the whole line, so the first step is to move tasks off it or add a second worker there.

GATE 2025 · PI · Q.49NAT · 2 marksFacility design: layout and assembly line balancing

Number of stations for minimum cycle time with six sequential tasks of 37, 8, 19, 34, 36 and 17 minutes

A product has to be manufactured in a single-line layout by carrying out the six tasks in a sequence. The time (in minute) of the six sequential tasks are 37, 8, 19, 34, 36 and 17. These tasks cannot be further sub-divided. For minimizing the cycle time, the number of stations to be used is________. (Answer in integer)

Answer: 5 Official key: 5 to 5

  1. On a line the cycle time equals the time of the slowest station. Tasks cannot be split and must stay in sequence, so each station takes a run of neighbouring tasks.
  2. Lower bound: a station must hold the longest task, so the cycle time cannot be below 37 min. Adding any neighbour to 37 gives at least 45 min, so 37 must stand alone.
  3. Try to hold the cycle time at 37 min. Start a new station whenever the next task would push the load above 37: [37], then (adding 34 would give 61), then [34] (adding 36 would give 70), then [36] (adding 17 would give 53), then [17].
  4. That is 5 stations with loads 37, 27, 34, 36 and 17 min and cycle time 37 min. No cut into fewer stations reaches 37: with 3 stations the best cycle time is 53 min (loads [45, 53, 53]). Checking all 32 ways to cut the sequence confirms that the minimum cycle time is 37 min and that 5 stations is the fewest that reach it.

Trap: stopping at 3 stations because the total of 151 min divided by 3 is about 50 min. Fewer stations raise the cycle time, which the question asks to minimise.

Where this shows up in industry

Assembly-line balancing assigns tasks to stations in precedence order so that no station exceeds the target cycle time. The slowest, indivisible task sets the best cycle time a line can reach, whatever the number of stations.

GATE 2026 · PI · Q.64NAT · 2 marksFacility design: layout and assembly line balancing

Items out of a cutting, welding and polishing line with three workers in six hours, steady state

Consider an assembly line producing an item through a process involving three activities in the following order: cutting, welding, and polishing. There are three workers available: one is assigned only for cutting, one is assigned only for welding, and one is assigned only for polishing.

The activity time per item is given in the table.

Activity nameCuttingWeldingPolishing
Activity time/item (in minutes)304025

Assuming that the process is running in steady state, the total number of items coming out of the assembly line in six hours is ______ (in integer).

Note: Assume that workers, items, and machines/tools are available as and when needed.

Answer: 9 items Official key: 9 to 9

  1. Rule: in a serial line with one worker per activity, the slowest station, the bottleneck, sets the cycle time. In steady state one item leaves every cycle time, however fast the other stations are.
  2. Station times are 30, 40 and 25 minutes, so the bottleneck is welding and the cycle time is 40 minutes.
  3. Six hours minutes. Output items, so the answer is 9 items.

Check and trap: cutting is idle 10 minutes and polishing 15 minutes per cycle, so the line efficiency is . Dividing 360 by the sum of the times (95 minutes) gives 3.8, which is the wrong idea: the stations work in parallel on different items. Counting from an empty line, the first item only emerges at 95 minutes and only 7 items are out by 360 minutes, but the question says steady state, which ignores that start-up. A simulation of the line (unlimited buffers, items always available) shows one item every 40 minutes, and exactly 9 items in every 6-hour window after start-up.

Where this shows up in industry

This is the basic line-balancing check on a fabrication and finishing line: the slowest station sets the daily output, so adding a second welder or splitting the welding task raises output, while speeding up cutting or polishing alone does nothing.

GATE 2025 · PI · Q.18MCQ · 1 markProduct design and development

Proper sequence of the design phases of a product

The proper sequence of design of a product is
  1. (A)Conceptual design, Embodiment design, Detailed design
  2. (B)Conceptual design, Detailed design, Embodiment design
  3. (C)Embodiment design, Conceptual design, Detailed design
  4. (D)Embodiment design, Detailed design, Conceptual design

Answer: (A) Official key: A

  1. The standard design process (Pahl and Beitz) moves from the vague to the exact in three phases, and each phase needs the output of the one before.
  2. Conceptual design: clarify the task, find the working principles and choose a concept. Output: a principle solution.
  3. Embodiment design: give the chosen concept its shape, materials, dimensions and layout, and check it against cost and manufacture. Output: a definitive layout.
  4. Detailed design: fix every tolerance, finalise every drawing and prepare the production documents. Output: a full drawing and parts-list set.
  5. So the order is conceptual, embodiment, detailed, which is option (A). Options (B) and (D) put detailing before the layout exists, and (C) and (D) lay out a product before any concept has been chosen.

Check: the three names run from principle, to form, to documents, which is the order in which the amount of fixed detail grows.

Where this shows up in industry

New-product design reviews are organised around exactly these gates: a concept review, a layout or embodiment review and a final drawing release. Freezing tolerances before the layout is agreed is a common cause of late engineering changes.

GATE 2025 · PI · Q.42MSQ · 2 marksProduct design and development

Benefits of product standardisation

The benefit(s) of product standardization is/are
  1. (A)Need of less number of drawings
  2. (B)Reduction in unit cost
  3. (C)Reduction in inventory cost
  4. (D)Greater product variety

Answer: (A) and (B) and (C) Official key: A;B;C

  1. Standardisation means agreeing on fixed sizes, grades, shapes and parts so that the same item serves many uses. Its effect is to cut the number of different items a company designs, makes and stocks.
  2. (A) True. Fewer different parts means fewer drawings to prepare, issue and keep current.
  3. (B) True. Fewer variants mean larger batches of each, longer production runs, less changeover and cheaper bought-in parts, so unit cost falls.
  4. (C) True. Fewer item types and interchangeable parts mean fewer spares and less safety stock, so inventory cost falls.
  5. (D) False. Standardisation reduces variety. Offering greater variety is the opposite aim, and is the usual price paid for the savings above.
  6. The correct set is (A), (B) and (C).

Trap: do not confuse standardisation with diversification, which adds products to widen the range.

Where this shows up in industry

Fastener, bearing and motor catalogues limited to preferred sizes are standardisation at work, and purchasing teams use them to cut the parts list for a new product. Design reviews often include a check that a new part does not duplicate one already in the stores.

GATE 2026 · PI · Q.11MCQ · 1 markProduct design and development

Which step is NOT part of product concept selection: matrix, ranking, combining or cost model

Which ONE of the following steps is NOT a part of product concept selection?
  1. (A)Preparation of the selection matrix
  2. (B)Ranking of the concepts
  3. (C)Combination and improvisation of the concept
  4. (D)Development of a cost model of the product

Answer: (D) Official key: D

  1. Rule: concept selection is a structured screening of the concepts that concept generation produced. In the widely taught method of Ulrich and Eppinger it has six steps: (1) prepare the selection matrix, (2) rate the concepts against the criteria, (3) rank the concepts, (4) combine and improve the concepts, (5) select one or more concepts, (6) reflect on the results and the process.
  2. Match the options: (A) is step 1, (B) is step 3, (C) is step 4. All three are part of selection.
  3. (D) is not a selection step. A cost model is built for the concept that has been chosen, in the economic analysis and design-for-manufacture work that follows. Selection itself compares concepts with coarse ratings against criteria (cost is only one criterion in the matrix), not with a detailed cost model.
  4. So the step that is NOT part of concept selection is (D).

Trap: step 4 sounds like creative work, so it can look out of place, but selection deliberately includes combining and improving the best concepts before the final choice. We encoded the six steps and tested each option for membership: only (D) fails.

Where this shows up in industry

In a new-product design review, the team scores three or four concepts in a selection matrix against criteria such as cost, ease of assembly and durability, keeps the best two, borrows good features from the others, and only then asks finance for a cost model of the winner.

From GATE prep to a production, industrial engineering or manufacturing career

Talk to a counsellor.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.