Challenge

Project 2_Design & Analysis of a Hostel building at Guwahati, Assam

Project 2_Design & Analysis of a Hostel building at Guwahati, Assam

Aim:- To Design and Analysis the of G+3 (RCC) hostel building in ETABS and Foundation in CSI SAFE.

Introduction:- In This Project design process from modelling, analysis, design, and preparation of construction drawings. The architectural drawings of a G+3 RCC building is provided.

The following information on the building is to be used:

  • Location – Guwahati, Assam ( Zone V - for semic zone)
  • Function – Hostel block in an academic institute
  • The walls will be made of AAC blocks. Other loadings are to be calculated as per the architectural drawings.
  • The buildings rests on type 3 soil. Piles of length 10 meters and 500 mm diameter with a load-carrying capacity of 280 KN is to be used.
  • The ground floor level will be at a height of 2 meters above the existing site level to avoid floodwater enter the building.
  • M25 grade of concrete with Fe500 for longitudinal reinforcement and Fe 415 for shear reinforcement is to be used.

Procedure:-

  • First goto open Etabs and select units
  • Create grids as per given architectural drawing
  • Create level as per give in drawing
  • Grids are created
  • Add New Materials M25 concrete, Rebar Fe500 and 415,
  • Add Beam 450X650mm, Coloumn 450X500mm and Slab 150mm thickness
  • Placed Column and beams At grids or where is required
  • Select quick draw column / beam
  • Create slab using Quick draw floor option
  • Define Load Patterns
  • Define Load Values
  • Live load from IS 875 Part-2 = 2kn/m^2
  • Thickness X height X Density => 0.2m X 3.5m X 550 kg/m^3 = 385 kg/m = 385/100 = 3.85kn/m =3.9 kn/m
  • Floor finish = 1.5kn/m^2
  • Define Mass sources/ load cases
  • Add Load combination using Add default design combo
  • Define Diaphragram
  • Check modal after run analyisis
  • Run Analysisi
  • Check Maximum story drift not excceding 0.004 (as per code)
  • EQx is 0.002209 <0.004 (ok)
  • EQy is 0.002599 <0.004
  • Result :- BOTH (EQx or EQy) OF THE STORY DRIFT ARE WITHIN THE CODAL LIMITS WHICH IS 0.004MM OR 4M.
  • Create Concrete Framing Design
  • Check all member is passed or not
  • Now Lets Transfer the Load, Base reaction, grids or etc from Etabs to Safe22
  • Transfer All Load, Load cobination, Points etc
  • Now Open the CSI SAFE22 and goto import > select file > open
  • Successfully File exported
  • Add new material M25 Concrete, Rebar Fe500,
  • Add Slab property
  • First add footing/Pile CAP( in later i will increase the depth upto 1200mm)
  • First add Column ( which is stiff)( in later i will increase the depth upto 1200mm)
  • Also Add Plie (Dia of Pile is 500mm) (which is Footing) ( in later i will increase the depth upto 1200mm)
  • Calculate soil Subgrade / point Spring Constant
  • Piles in the springs are defined as spring so for that the spring constant

    K=EA/L

    E-5000 * (fck)^0.5=> 5000(25)^0.5= 25000 N/mm 2

    Area of pile = (3.414 * d^2)/4 => 3.142 (500)^2/4 => 196350mm^2

    L= 10000mm (10m)

    K= 25000*0.7855/16-306835.9N/mm= 490875N/m => 490.875 KN/m

  • Soil type 3

    Safe baering capacity X factored to ultimate / Maximum settlement

    => 150 X 3 / 0.05 = 9000KN/m^2

  • Check All Loads, Load combo, load pattern are available
  • Firstly Placed Pile Cap of Dim-2500mmX2500mm( Some point it will varrey)
  • Second Placed Coulmn of dim 450X650mm third palced piles dimension is 500mm dia
  • Now make Strips layers of A and B direction
  • Add Beam for dimes 450x500mm of material Is M25 concrete and rebar is fe 500 both bars
  • Assign Spring Constant on pile
  • Assign Soil subgrade on Pile-cap
  • Check Model after analysis
  • Punching Shear result
  • Reaction not much greater than 280kn
  • Increasing Column, Pile And Pile-CAp thickness 1200mm
  • Again Run Analysis
  • Displacement Result
  • Joint Reasction Data
  • Area shells
  • Base reaction
  • Soil Pressure
  • Punching Shear

Reinforcment Detailing:-

Highest Longitudinal Reinforcement Along Gride-3

Provide Top Support Reinforcement

  • 4 Bars @ 20mm dia and 4 Bars @ 16mm dia
  • Total Provide Reinforcement =2060mm^2

Provide Bottom Support Reinforcement

  • 4 Bars @ 12mm dia and 4 Bars @ 16mm dia
  • Total Provided Reinforcement = 1252mm^2

Provide Mid-Span Reinforcement

  • 4 Bars @ 16mm dia
  • Total provided reinforcement = 804mm^2

Provide Mid- Span Reinforcement

  • 3 Bars @ 16mm dia and 3 Bars of 20mm dia
  • Total provided Reinforcement = 1545mm^2

Provide Support Shear reinforcement

  • 4 Leg of 10mm of C/C @ 100mm
  • No. Of Strripus 22
  • Length of end span 2.033m

Provide Top Shear reinforcement

  • 4 Leg of 10mm of C/C @ 100mm
  • No. of Stirripus 28
  • Length of Mid span 2.711m

Provide Longitudinal Reinforcement

  • 10 Bars @ 28mm dia

Provide shear Reinforcement

  • 8mm dia @ 100mm Spacing at column end
  • 8mm dia @ 200mm Spacing at mid Column

Pile Reinforcement 10mm dai @ 100 mm spacing

Floor Pan

Result:-

In result successful Design the model, analysis and Export from Etabs to safe And Also Successfully Design and analysis the foundation in SAFE

Reinforcement detailing are also be created

  • Beam Connecting Piles also same as Upper beams
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.