Challenge

Project 2

Aim:

To Create the project as per the given question using Primavera P6

Procedure:

Step 1:

1) Open Primavera P6 and click report option

2) Click + button on top of the right screen

3) Choose the EPS as Skill lync education which created on project 1

Step 2:

1) Rename the project as Education Centre Road

2) Click next

Step 3:

1) Edit the project start date as 22nd febrauary 21

2) Click next

Step 4:

1) Choose the responsible manager

2) Click next

Step 5:

Adding Resource:

1) Click Enterprise and choose resource option

2) Click + button on top of the right screen

3) Edit the resource name as A

4) click next

Step 6:

1) Choose the type as labour for resource A

Step 7:

1) Edit the units/time for each resource

2) Click next

Step 8:

1) Assign the role as Engineer

2) Click next

Step 9:

1) Choose the existing calender as 5 days workweek

2) Click next

Step 10:

1) Therefore A resource has been added successfully

Similarly need to repeat this process for B and C resource

Adding Activities:

1. Develop the project schedule as per the given question:

Step 11:

1) Click activity tab

2) Click + button on top right of the screen

3) Edit activity name and code

4) Click next

Step 12:

1) Choose WBS as Education centre road

2) Click next

Step 13:

1) Choose task type as task dependent

2) Click next

Step 14:

1) Assign the resoruce of A,B and C

2) Click next

Step 15:

1) Choose duration type as fixed duration and units

2) click next

Step 16:

There fore 1st activity has been added successfully

Similarly repeat this process for all other activities

Step 17:

1) Provide the predecessors for each activity

Step 18:

1) All the activities has been updated successfully

2. Use 3-Tier timescale with Year / Month / Weeks

Step 19:

1) Right click the gantt chart and choose timescale

2) Select 3 line option

3) Choose month/week option

4) Click apply

Step 20:

1) Therefore timescale has been updated year/month/week wise

4. Add a budget to your project - INR 6 cr.

Step 21:

1) Open report page and click the education centre road report

2) Go to budget log on bottom tool

3) Edit the original budget as 6 Cr.

5. Assign a baseline to the project:

Creating Baseline:

Step 22:

1) Click project tab and choose maintain baseline option

Step 23:

1) Provide the baseline name

2) On the bottom, choose the baseline type and clik ok

Step 24:

1) Click update option

2) Choose all activity option

3) Click update and close

Step 25:

1) Click project tab and choose assign baseline option

Step 26:

1) Choose the primary, secondary and tertiary baseline as Education centre road

2) Click Ok

Therefore baseline has been assigned successfully

6. Add following expense:
Task - 1 - Rs 20,000/- (Item - Fuel)
Task - 2 - Rs 30,000 /- (Item - Maintenance)

Step 27:

1) Go to Project tab and choose expense option

Step 28:

1) Click + button on top right of the screen

2) choose the activities

Step 29:

1) Edit the expense name, cost and its vendor name

2) Input the expense cost at the bottom of the screen

7. Generate material resource costs curve

Step 30:

1) Click the activity which are belongs to material resource

2) Select the resource tab on below of the control bar

Step 31:

1) Click the resource tab and select customize option

2) Choose curve from general option

Step 32:

1) choose the curve option from the curve

2) Click ok

Step 33:

1) Click activity resource usage option from top of the screen

Step 34:

1) Right click the curve and choose activity usage profile option

Step 35:

1) Click material option under the filter

2) click ok

Step 36:

Therefore the material resource cost curve has been generated.

8. Generate an activity wise cost report

Step 37:

1) Click report on leftside of the screen

2) Click + button on top of the right screen

3) Click next

Step 38:

1) Choose subject area as activities

2) Click next

Step 39:

1) click group and sort option

2) Choose the costs and activity related options

3) Click ok

Step 40:

1) Rename the report title as Activity cost

2) Click ok

Step 41:

1) Therefore activity wise cost report has been generated

9. Create a reflection

Step 42:

1) Click project on leftside of the screen

2) Select the project of education centre road

3) Right click and choose create reflection option

Step 43:

Therefore reflection of the project has been created successfully

10. In the reflection, auto update the project at 15 days from start

Step 44:

1) Right click the reflected project

2) Choose open project option

Step 45:

1) Change the date of 15 days prior to the current project

Step 46:

1) Click tools tab and select update progress option

2) click ok

Step 47:

1) Therefore the schedule has been auto updated successfully

11. Open a TSLD view of the project in Visualizer

Step 48:

1) Go to tools tab and select visualizeer option

Step 49:

1) Click + button on top of the screen

2) Choose TSLD option

Step 50:

1) Choose the education centre road project

2) Click ok

Step 51:

1) Rename the tsld

2) Choose TSLD type

3) Click draw

Step 52:

Therefore project has been created in P6 Visualization

12. Add curtains up-to first 15 days of the project.

Step 53:

1) Go to View tab and choose attachment option

2) Select curtain and choose add curtain

Step 54:

1) Edit the start and finish date of the project

2) click ok

Step 55:

Therefore the curtain has been added successfully

13. Find out the actual cost for labour, non-labour and material cost of the updated schedule

Step 56:

1) Go to project page and click calculation tab

2) Select add actual option

Step 57:

1) Click anyone of the project and choose resource option on bottom of the project

2) There we can find the actual and budgeted costs for each resource

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.