Preparing Schedule & Cost Estimation for a building using REVIT
1) Use the shortcut keys in Revit discussed in class to complete the following tasks and list them below
a. Using 3D model create a section box
b. To create similar doors and windows in a floor plan layout
c. To reduce the thickness of lines visible in plan views
d. To apply override settings to a floor in the model section view
e. To increase the range of visibility in a plan view
f. To select the previously selected items
g. To add annotations to the model views
h. To bring the model elements in line
i. To rotate the model elements
j. To move an object to another location
k. To copy a model element
l. To mirror an element about an axis
m. To create an array of model elements
a. Using 3D model create a section box-BX
b. To create similar doors and windows in a floor plan layout-CS
c. To reduce the thickness of lines visible in plan views-TL
d. To apply override settings to a floor in the model section view-EOD
e. To increase the range of visibility in a plan view-VR
f. To select the previously selected items-CTRL+C
g. To add annotations to the model views-DL
h. To bring the model elements in line-AI
i. To rotate the model elements-RO
j. To move an object to another location-MV
k. To copy a model element-CO
l. To mirror an element about an axis-MM
m. To create an array of model elements-AR
a. Using 3D model create a section box
b. To create similar doors and windows in a floor plan layout
c. To reduce the thickness of lines visible in plan views
d. To apply override settings to a floor in the model section view
e. To increase the range of visibility in a plan view
f. To select the previously selected items
g. To add annotations to the model views
h. To bring the model elements in line
i. To rotate the model elements
j. To move an object to another location
k. To copy a model element
l. To mirror an element about an axis
m. To create an array of model elements
2) Using Revit and the project used from week 6 to 8 prepare a schedule for the following
a. Walls
b. Doors
c. Windows
d. Material – Concrete/Wood
AIM: Using Revit and the project used from week 6 to 8 prepare a schedule for the following
a. Walls
b. Doors
c. Windows
d. Material – Concrete/Wood
PROCEDURE:
- Open archeitectural tab which is previously created .
- Go to view option click on schedule quantity
- Then you will find options like doors windows, stairs columns,etc select option click ok .
- You will find quantites select cost ,length, area ,etc
- click ok .




3) Using Revit Calculate area and volume of each room in the model with appropriate room tags applied to each room. Prepare a schedule report for area and volume of each room.
Aim: To Use Revit Calculate area and volume of each room in the model with appropriate room tags applied to each room. Prepare a schedule report for area and volume of each room.
Procedure:
- Open archeitectural tab which is previously created .
- Go to view option click on schedule quantity
- Then you will find options like doors windows, stairs columns,etc select option click ok .
- You will find quantites select cost ,length, area ,etc
- click ok .


4) Using the same schedule using the unit cost rate for materials available in the internet, prepare total cost of materials used in the project
a. Total Cost of Materials
b. Individual Material Take off
- Open archeitectural tab which is previously created .
- Go to view option click on schedule quantity
- Then you will find options like doors windows, stairs columns,etc select option click ok .
- You will find quantites select cost ,length, area ,etc
- click ok .


5) Using the concept of Visual Programming discussed in class, list a flowchart for the following scenario
a. How to decide framings for a structure using Dynamo ?
b. If there is no water coming from the pipes
c. If request for money from client has been declined for the project

6) List the parameters associated with each model element
a. Wall
b. Floor
c. Door
d. Window
e. Table
f. Building
A.wall
type
length
width
height
cost
thickness
B.floor
type
length
width
height
cost
thickness
c.Door
type
length
width
height
cost
thickness
d.window
type
length
width
height
cost
thickness
Building
Height
Volume
breadth
length
material used