The instructor defines dead load (25 kN/m3 for reinforced concrete, 78.5 kN/m3 for steel), fixed and variable superimposed dead load, live load, braking, centrifugal, temperature, wind, erection, collision and earth pressure loads. It ends with the IRC 6 ultimate limit state table, where dead load is 1.35, surfacing 1.75 and a leading live load 1.5.

  • Dead and superimposed dead load, fixed versus variable
  • Longitudinal, centrifugal, wind and temperature loads
  • Differential settlement limits of 12 mm and 6 mm
  • Leading and accompanying load factors

What comes after lesson 3?

Later in Skill-Lync's Design of Bridge Substructures / Piers using STAAD.Pro course (paid): lesson 4, Introduction to Bearings in Bridge Engineering; lesson 5, Articulation of Bearings in Bridge Modeling; lesson 6, Introduction to Bridge Abutments and Types. The full course has 45 lessons (20 h 54 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Dead load, while for calculating dead load, generally for reinforced concrete, we considered the density of concrete as 25 kilonewton per meter cube. With that, we multiply the quantity and that we will get a weight and that weight will be applied in the or on the structure as a self-weight. Moving on to steel, the density for steel, we consider it as 78.5 kilonewton per meter cube. A similar procedure will be done for calculating the weight of steel also. But in softwares such as STAD, MIDAS, LUSAS, we have an option wherein the self-weight, by using a self-weight command, we can generate the actual weight that would act on a structure because of its self-weight.

So that options we have in softwares. Alternatively, we can also calculate the loads ourselves and apply manually as an external load on the structure. So basically, it rests with the designer whether how he or she would like to apply the self-weight. Moving on to superimposed dead load, that is SIDL. So these basically are the loads which are permanent in nature other than the dead load. Let's say take for example, I can call the weight of a girder and the slab as a dead load. But the weight of a crash barrier, parapet, and surface cores, these all could be considered as a superimposed dead load.

So that is the difference between dead load and superimposed dead load. This superimposed dead load, it can be divided into two types. One is a fixed one. Then the fixed, generally the parapet, crash barrier, handrails, and these electric poles, since these are almost permanent in nature, they are fixed. Their weight is almost same throughout the design period, throughout the life period. So they are called fixed superimposed dead load. Whereas a variable superimposed dead load necessarily refers to the cores, the overlay, the concrete cores, or the bituminous cores, which acts as a carriageway.

So that would be considered as a variable because as that particular highway or superstructure as it ages, this layer keeps eroded and eroded now and then it will be removed and replaced. So that's why it is called variable. So what is the necessary to divide the superimposed dead load into fixed end variable? So where it was, what is the significance of it? Because load factor for variable and fixed, it is based on because we have a different load factors for both. For fixed, it is a different load factor and for variable, it is a different load factor.

These play an important role when we combine different loads. That's the reason we divided into that two. Moving next, live load. Are we going to use or run a same live load on all our bridges, whether if a bridge is of a, whether if it's a metro bridge or if it's just a flyover or if it's just a highway bridge or railway bridge, are we going to run a same live load? No. So based on the type of the structure, based on the type of for the purpose, we would test run a different type of live load on our structure.

Take for example, in a highway bridges, where flyovers also come under this, we refer to IRC6 or what are the different types of live load we need to run on our bridges. A more detail on this different types of live loads will be discussed while we model and analyze in StatPro. Till that, let's have just a rough idea that we have different types of live loads for different types of bridges. So, when this live load was run on the structure, for every point, for every movement, there will be a different bending movement.

So, if we could recall our basics, there will be influence line diagram for the moving loads. So, in softwares, are we going to draw an IFL for each position of the live load? Luckily, softwares for such as Stat also, we would get a combined onerous effect. That is, envelope will be automatically obtained in the StatPro. So, that would drastically reduce our work in getting the critical bending movement for a structure, for a superstructure. Next, longitudinal loads. Generally, if we take live load, the longitudinal loads to live load are primarily braking and if there is a vehicle which has run such as IRC7TR class AA tracked vehicle, we need to consider traction force also.

So, these are the generally longitudinal loads that we consider and based on the span and other criteria as mentioned in IRC6, they vary approximately around 18% to 20% again subjected to the span and other span conditions. These loads act on the superstructure which will then be transferred to the substructure and foundation. But, specifically, they can get additional longitudinal loads such as water force, water current forces, then the seismic forces, they can be additionally subject to a substructure. And, when we do a continuous bridge, a bridge which is continuous in nature, during that time, we make sure that one of the pier will act as a fixed.

So, the longitudinal loads will be addressed or will be taken care by that particular fixed pier. More on it, we will discuss when we reach bearings there. So, there we have a separate topic for this. We will discuss more on it there. Next, centrifugal loads. When does this centrifugal loads come into picture? If our bridge is not straight in alignment and due to some requirements, it is curvature, if it is curved, then we need to consider the centrifugal loads coming to picture. So, this centrifugal load, it again depends on the speed of the vehicle and the radius of the curve.

Based on that, it will induce an extra loads in the structure. These centrifugal focuses cannot be ignored because they create a very huge impact on the design of superstructure particularly. Few years back, there was some mistake in considering centrifugal loads calculation or the centrifugal load has been ignored in a Mumbai bridge floor. I think the radius of the curvature was around 200 meters. With such a curved superstructure, the centrifugal loads were ignored. And the result was during the construction time, the entire tech, that particular span, it just fell down.

So, the point here is, centrifugal loads cannot be ignored. Next, temperature or overall effective bridge temperature. For calculation of loads due to temperature, we refer to clause 215.2 of IRC6 and also we would refer to figure 15 and 16 showing the isotherms of shared air temperature. So, we have a map or isotherms generated for Indian map and through that we can deduce which particular region is subjected to what kind of temperature. So, we would refer to those isotherms and accordingly, we will calculate the load on the temperature, load on the bridge due to temperature.

Next, wind load. All these loads, at least for highway bridges, we refer to IRC6. So, if we have a particular clause for each of these loads. Next, wind load. Wind load needs to be considered one in the absence of live load, one case. Another case is with live load, the most onerous effect will be considered. This wind load can act in any direction, so our bridge needs to be designed for a wind in any direction. Basically, we consider wind in transverse direction, longitudinal direction, and vertical direction, that is upwards and downwards.

That's why I mean we can't give a space for wind that we cannot consider wind in vertical direction or wind in transverse direction. We need to check for all the directions. Next, erection or temporary load. These loads come into the picture while construction phase. So, what are these loads generally comprises of? The loads for launching a girder. Launching a girder means once the bridge is constructed up to substructure, we have a choice or the constructor has a choice to employ the type of construction for superstructure in consultation with the design.

So, there are different types in which a superstructure can be constructed. Let's take for example of girders. They can be just a temporary formwork can be laid and then the concrete can be cast and below a temporary formwork all can be provided. And on that, these girders can be placed. The other method is the entire setup, the deck, including girders, slab, everything would be constructed at a precast AR. And while placing it on the bridge side, we use something like a launching instrument machinery wherein it will just the entire deck will be moved and placed a particular span will be placed on its position.

So, that is something like launching girders, the crane loads, there will be temporary cranes which are used to lift the structures, machinery, equipments, all those things. And even the shuttering, there will be sometimes we use permanent shutters also. These all come under erection or temporary load. So, there is a good probability that these erection loads can be a most onerous one for a particular structure. So, we need to consider these as well. The next one is vehicle collision load. This generally happens when a vehicle collides with a bridge structure.

The collision can occur in the top parapet also or if a substructure such as pier is placed in the existing roadway or highway, then there is a good probability that a vehicle traveling in that highway could hit the up here. So, this particular vehicle collision was found to be governing during a foundation design. This needs to be considered. So, we are referring IRC6 for that, plus 222 for vehicle collision load. So, next, earth pressure, I won't be going much detail as we said earlier because these all are covered in a separate course.

You could refer to that course. Earth pressure basically in our bridges, it acts at the abutments. So, there are so many clauses corresponding to earth pressure, like how the load needs to be considered and at what height the net force would be acting and what is the minimum, which terrain we need to follow to arrive at our coefficients. So, all these things were given in earth pressure clauses. We also, in addition, we might also refer to IRC78 for more details on earth pressure. But the thing here is, our piers generally, they are not subjected to the earth pressure, but our abutments would be designed to withhold these extra loads because of earth pressure.

And because of this very reason, that the abutments would be checked for stability also. Generally, we don't check the stability of piers, but it is necessary that we need to check the stability of abutments. The main reason is being the earth pressure without backfill, which is behind abutments. In addition, we have a separate load here. It's a differential settlement load. So, let's say that our bridge has number of piers in it and because of some reason, one pier, the reason may be either because of soil characteristics or because of scour, in case of if it's a river bridge, there is a good probability that one of the pier may sink or may settle more compared to its adjacent pier.

During that time, because of there is a difference in the settlement between adjacent pier and this might result in the extra loads. And for all the design purposes, we are putting a cap that we would consider the maximum differential settlement as 12 mm while designing. And the same thing will be conveyed to the constructor saying that a structure cannot undergo more than 12 mm differential settlement. It is, the constructor needs to be sure that while constructing, the structure doesn't undergo more than 12 mm differential settlement.

This 12 mm, which I said, it is for long-term settlement. When we go for the short-term settlement, we reduce it for 6 mm. This short-term settlement, generally, it might occur during bearing replacement. As I said, if we have simply supported, then there won't be any much difference because of differential settlement. But if it is a continuous structure, then it has more implications. It induces a secondary forces in our structure. Differential settlement just occurs not only in longitudinal direction, but also in transverse direction also. While, let's take example of spill-through abortments, which we see in our next week, there is a good probability that there will be a differential settlement in transverse direction also.

So there also we are going to put a cap of this 12 mm or 6 mm. So that's the importance of differential settlement load. So, as I mentioned earlier, the water current force, which primarily act generally on a substructure, this also needs to be considered. So, while design, I mean, this generally doesn't affect our superstructure, but substructure and foundation needs to be considered, needs to consider the effect of water current force. So, there is an extra effect, which is called hydrodynamic effect of water. We need to consider that also as per IRS seismic code.

Yeah, moving on to load combinations. Here, I would just take you through a standard label, which is given in IRC6, because these loads and load combinants are already covered in a separate course. So, as I mentioned earlier, if you look into this table, table B.2 in IRC6, we have for verification of structural strength. So, what are these are the, I mean, for ultimate limit state, it is divided into three combinations. One is basic combination, other is accidental, and the third one is seismic. So, our structure needs to be designed to withstand these load combinations.

One important thing you can see here is, let's say we generally, the ULS state, we generally do this basic combination. You can see for dead load, the general effect is 1.35, and again, we have difference if it is adding to the effect or if it is subtracting to the net effect. If it's adding, it is called unfavorable, then it would be 1.35. If it is reducing our effect or if it is called favorable, then it would be taken as a 1. One thing which would, I like to highlight here is, as I mentioned earlier, the surfacing, which is called variable superimposed dead load, which comes under variable superimposed dead load.

If you look into that, it has 1.75 as a factor, but whereas, you can see here, the saddle except surfacing, which like crash barrier parapets, they will come under this dead load here. So, they have 1.35, whereas the surfacing has 1.75. That's what I would like to say here, that we have a higher combination factor for surfacing. Again, we also take into account the risk-rescent secondary effects. Then the backfill, you can see it's 1.5, earth pressure, again, if it's adding with 1.5, else it's 1. Then the variable loads, generally the loads, which vary, generate the live load, wind load, and other construction loads, so thermal loads, snow load.

So, these are the loads which vary. So, one thing is, when one load governs, or when one live... ... ... ... When the live load is leading, the others we consider as an accompanying load. So that's why you have two factors here. As a leading load, when a live load is leading, we need to take the factor as 1.5. But if it is accompanying, then we need to take 1.15. For construction live load, we just restrict to 1.35. Let's take an example. Let's say that the live load is leading.

So the factor for live load will be 1.5. Since live load is leading, we will take wind load as an accompanying load. So wind will take it as 0.9 and live loads are charged with 1.2 only. Then the thermal loads, we need to take it as an accompanying load with the factor 0.9. That is what it means when one load is leading, the other loads need to be accompanying loads. So as I said earlier, we also have a combination for accidental effects. You can see in the basic combination, we don't have anything here.

But this is a collision combination. Here we have the factors for accident. Again, hydraulic loads, buoyancy, these all have some factors in our basic combination. That's all a small introduction or there's a small data on loads and load combinations. Thank you. Thank you. You

Want the rest of Design of Bridge Substructures / Piers using STAAD.Pro?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Design of Bridge Substructures / Piers using STAAD.Pro course

The remaining 42 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Design of Bridge Substructures / Piers using STAAD.Pro course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.