Usage of Navigation tool , Timeliner and Clash Detection test using Naviswork
1. Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class
Aim- to Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings
Commands used-
- Export
- File
- 3d view
Procedure-
- Open the architectural model of previous weeks and view in 3d view
- Click on export optionin a file tab and select NWC
- File is now in NWC format and repeat the same procedure to other file


Result- structural project file is exported successfully
2) Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file
Aim- to Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file
Commands used-
Walls
Viewpoint
Procedure-
- Export the structural and architectural model to naviswork
- Create a viewpoint
- Now select the record option from viewpoint and walk command through room created
- Click on stop after walking through all rooms


Result-walk through a room is successfully created
- Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file
Aim- to Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file
Commands used-
Viewport
Realism
Record
Procedure
- open the exported architectural file in naviswork
- create viewport using clicking on record
- slecting a realism option and clicking on 3rd person option
- start walk by clicking on record option
- click on stop after walking through all rooms


result-created a realism and walk through successfully complted
4) Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks
Aim-to Create a clash detection test between the two models
- Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks
commands used-
clash detective
add test
procedure-
- open the exported structural and architectural file
- select clash detective model on home tab
- a tab in which two new tab appears
- clicking on add test and remaining it as architectural and structural and cclicking run test


result- clash detective is ran successfully
5) Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file
Aim-to Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file
Commands used-
Timeliner
Add task
Procedure-
- open the export structural model to th naviswork
- ckicking on the timeliner option and selecting the slection tree
- sselecting the add task and remaining is appropriate component
- the planned start ,planned end, actual start and end is filled with appropriate date.
- Specify a task type as construction

Result-timeliner iption is used successfully with selection tree with scheduling of coloumn