Usage of Navigation tool , Timeliner and Clash Detection test using Naviswork
1Q:Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class
PROCEDURE:Open revit sofware and select the week 8 challenge file.

Now click on the FILE tab and select the Export option.

In the Export select the NWC and save the File as NWC file.

Now click on export to Export the file in NWC file.
RESULT:Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class is completed.

2Q:Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file.
AIM- TO USE NAVIGATE TOOL TO WALK AROUND THE MODEL AND WALK THRUOGH THE ROOMS CREATED
PROCEDURE:Now open the NEWIS WORK MANAGMENT SOFTWARE.
Now select the File tab selct the file.
Select the NWC file Week 8 challenge open it.
Now click on the viewpoin tab.
Select the saveview point .
Now rename the viewpoint as the living room in save view point.
Now start the recording using the Record option in the Viewpoint option.
Now select the walk option and walk through the model.

After compliting the the walk through model stop the recording watch the animation.


RESULT:Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file is done.

3.Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file
PROCEDURE:
Now select the File tab selct the file.
Select the NWC file Week 8 challenge open it.
Now click on the viewpoint tab.
Select the option Realism option in the viewpoint tab.
In the realism option select the third person.

By adjusting the view selecting the pan, walk through the mode and record the animation.
After compliting the the walk through model stop the recording watch the animation.


RESULT:Use Navigate tool to use Realism feature to walk through the model and record your moving as animation in Navisworks file is done.
4. Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care later)
e. List which of the clashes can be resolved
f. Save the results after color coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks
PROCEDURE:
Now select the File tab selct the file.
Select the NWC file Week 8 challenge open it.
Before Clash detection Insert the structural file by using Append option.
Click on the Home tab and select the CLAS DETECTIVE option.

After selecting the clash detective A table will appear.
Now select the add test option in the table A new column is appear.
Now select the architecture in section A and structural in section B.
Select the surface option and Run the test.

It will show the number of clashes between structural and architectural.
If we need to change the status of clashes in between them, then select the clashes.
Now in status column aelect the status and change it to Approved, Resolved,Active,Reviewed.
Now we can see the status of the clases in the model

RESULT:We have embed the architecture and structural model and run the clash detection test.
5Q:Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file
PROCEDURE:
Now select the File tab selct the file.
Select the NWC file Week 8 challenge open it.
In the Home tab select the selection tree Option.

Now we see that a List will appear accorting to model.

Again select the Time linear option in Home tab.

Alist will be appear then select the Add task in list.
By looking into the Selection tress add the task by Level wise.
Now in the column fill the data using rough estimation of when the plan start and when the plan ends.
Chose the type of task like constrution,demolish,temporary.

For all the task added in the list.
Now simulate usinng the simulate option and play the visuals.
Now we can see that model will construct according to the given data.

RESULT:Using the Timeliner feature in Navisworks prepare a schedule for the project developed in week 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to Navisworks file had been completed.