Usage of Navigation tool , Timeliner and Clash Detection test using Naviswork
1) Use the Architecture/ Structure Project file developed by you in Week 6 to 8. Export the Revit architecture and structure model to Navisworks Cache file following the export settings discussed in class
Aim: To export the Revit architecture and structure model to Navisworks Cache file following the export settings.
Procedure:
Step 1:
Go to the Autodesk website.
Search Naviswork manage and download the 2019 version.

Step 2:
First, we have to open the Revit software and open the architectural model.
Click on the file option and export the model as an NWC file. Save the model as navis works 1.


Result:
The Revit architecture file is successfully exported to the Navisworks cache file.
2)Use Navigate Tool to walk around the model and walk through the rooms created and record your moving as animation in your Navisworks file.
Aim: Using the Navigate Tool, to walk around the model and walk through the rooms created and record moving as animation in your Navisworks file.
Procedure:
Step 1:
Opening the architectural model in the Navisworks.

Click on the walk tool under the view tab.
Use the record option in the viewport toolbar to record the moving animation in each and every room.

Step 2:
Walkthrough the reception area.

Step 3:
Walkthrough the Conference room.

Step 4:
Walkthrough the Cafeteria.

Result:
Used navigation tool to walk around the model and, To walk through the rooms created. To record moving as animation in Navisworks file.
3)Use Navigate tool to use the Realism feature to walk through the model and record your moving as animation in the Navisworks file.
Aim: Use Navigate tool to use the Realism feature to walk through the model and record moving as animation in the Navisworks file.
Procedure:
Step 1:
Select the realism option and select the third person.
Use the record option in the viewport toolbar to record the moving animation in each and every room.

Step 2:
Walkthrough the reception area.

Step 3:
Walkthrough the Conference room.

Step 4:
Walkthrough the Cafeteria.

Result:
Used realism tool to walk around the model and, To walk through the rooms created. To record moving as animation in Navisworks file.
4) Embed both architecture and structure *.nwc file to your Navisworks file. Create a clash detection test between the two models
a. Run the Clash Detection Test
b. Study the clashes between the two models
c. List which of the clashes could be approved
d. List which of the clashes could be neglected ( will be taken care of later)
e. List which of the clashes can be resolved
f. Save the results after color-coding the clashes to the Navisworks file
g. In case of resolution annotate the clash and save the view to defined views in Navisworks.
Aim: To Create a clash detection test between the two models.
Procedure:
Step 1:
Open the Home tab and select the clash detective tool.

Step 2:
Study the clashes between the two models.

Step 3:
List down the clashes which are approved.
List down the clashes which are neglected.
List down the clashes which are resolved.

Step 4:
Save the results after color-coding the clashes to the Navisworks file.

Result:
Created a clash detection test between the two models successfully.
5) Using the Timeliner feature in Navisworks prepare a schedule for the project developed in weeks 6 to 8 by adding reasonable assumptions for task start date and end date and simulate the task completion as a visual simulation. Record it and save the timeline simulation to the Navisworks file.
Aim: To use the Timeliner feature in Navisworks to prepare a schedule for the project developed in weeks 6 to 8.
Procedure:
Step 1:
Open the structural model in Navisworks which was exported from Revit.

Step 2:
Select the Home tab and select the timeliner.

Step 3:
Add the tasks and attach the tasks to them.

Step 4:
Update the actual dates like start and finish date to the task.

Step 5:
Select the elements and attach them to the time liner appropriately.

Next click on the stimulate to play the recorded task and next save the project.

Result:
The time liner feature is used successfully in Navisworks to prepare a schedule for the project developed in weeks 6 to 8.