To calculate dead and live load for industrial steel structures and to apply them using TSD
- AIM : To calc502ulate dead load in design report based on IS code and apply the dead load on model
- PROCEDURE :
- Dead load = 1.2 Kn/M^2
- Finishes = 500 mm X 24 Kn/m^2 = 1.2 Kn/m^2
- Brick wall load = 0.15 X 20 X 5.2 = 15.6 Kn/m^2
- Brick wall load = 0.15 X 20 X 6.8 = 20.5 Kn/m^2
- Brick wall load = 0.15 X 20 X 14.5 = 14.5 Kn/m^2
- Roof load = 1.5Kn/m
- Ceiling load = 0.3 Kn/m
- Open tekla software design software
- Open week 3 file where we have createed a steel structure

- Go to model tab and select slabs on beams option
- Now odd slabs to each other
- Now go to load tab and select load cases and add required load

- Now select load combination and add what required

- Select the level we want to apply loads on
- Select the loads required from the list

- Now go to select the area to apply load on slab

- Go to load tab and select UDL to apply on brick wall
- Apply loads on the roof as well


- AIM : To calculate live load in design report based on IS code and apply live load on the model
- PROCEDURE:
- Workshop = 5Kn/m^2
- Staircase = 5 Kn/n^2
- Corridor = 5 Kn/m^2
- Meetong room = 5 Kn/m^2
- Store room = 5Kn/M^2
- Toilet = 2 Kn/m^2
- Canteen = 3Kn/m^2
- Office room = 3Kn/m^2
- Conference ROom = 5Kn/m^2
- Equipment room = 10Kn/m^2
- Rest room = 2 Kn/m^2
- Administrative room = 5Kn/m^2
Live loads are applied for all the floors as shown below
- Now select the level where we want to apply the loads
- Now select the loads as required at the bottom, left corner


- RESULT :
Calculation of live load in assign report based on IS code and application of live load on the model is done
- AIM : Generate a calculation for 5 T crane loading based on the following inputs
- PROCEDURE :
- Centre to Centre of wheel =10m
- Weight of crab = 40 Kn
- Number of wheel = 4
- Wheelbase = 2m
- Crane Capacity = 50 Kn
- Weight of trolley =10 Kn
- Hook Approach = 1
Maximum Point load on Crane = Crane capacity + Weight of the trolley
= 50 +10
=60
UDL = Self -Weight of crane distance between grant rails
= 40/14
=2.89 Kn/m
Moment at A :

Ma = 0
Rb = 80 X1 -RbX14 + 2.89X 14 X14/2
Rb = 24.5 Kn
Fy = 0
Ra + Rb - 60 -2.89 X 14 -Rb = 0
Ra = 60 +2.89X14-Rb
Ra = 75.9kN
Assume Self weight of gantry girder = 1.2 Kn/m
Assuming Self weight of gantry girder =0.3 Kn/m
Total self weight = 1.2+0.3
=1.5 Kn/m
Factored Loads =1.5 X1.5
=2.25Kn/m
Now loads on each wheel =37.9 X1.5
= 56.95 KN
= 57 Kn
Moment at c

Mc=0
Rd x 6 = 2.25 x6X6/2 +5.7 X4.5 +57X2.5
Rd = 73.25 Kn
Fy =0
Rc + Rd -57-57-2.25 X6
Rc +Rd =127.5Kn
Rc +Rd =127.5Kn
Rc = -73.25 +127.5
MAX SHEAR FORCE

MF =0
ReX6 - 57-57X4-2.25 X6X6/2=0
Re = 101.75Kn
IMPACT LOAD
= 10% Of wheel load
=0.1 X 101.75
=10.275 KN
V= WI/2
=1.5 X 62
=4.5Kn
Max shear force =4.5 +10.175+101.75
= 116.25 Kn
Lateral load analysis =5% of total weight
=5100 X 60
=3Kn