Challenge

Reinforcement Detailing of Beams from ETABS output

Aim

To design the beams in detail, form the Etabs 2017

To provide the detailing of longitudinal and shear reinforcement for two continuous beams.

To provide the reasons of failure at middle span along grid A.

Introduction

Beams are horizontal structural elements used for the supporting lateral loads.

In conventional reinforced concrete structures, beams usually receive load from the floor slab, but may also be subjected to other loads such as wall loads, finishes, services installation, etc.

The design and detailing of RC beams involve the selection of the proper beam size and the quantity of longitudinal and shear reinforcement that will satisfy ultimate and serviceability limit state requirements.

Afterwards, it is very important that the beam reinforcements are placed and arranged properly on site, to avoid construction error.

Procedure

Step 1:

Open the challenge 7 attachment which are provided to us and download it.

After downloading open the Challenge import e2k file in the Etabs software 2017.

Step 2:

Now check the load combinations which are already created in given modelling file.

Step 3:

Before Run Analysis we have to check the model

Click on Analyze

Click on Check Model

A structure is verified without any error and Model has been checked.

Step 4:

Now we have to start the beam design by selecting the 'Start Design/Check' option

Once you click on Start / Design check you will see Display concrete frame Design results box.

Where you can select whatever design output you want

So, Click on Longitudinal Reinforcement.

Step 5:

Once you click on, Longitudinal reinforcement details will appear

Step 6

Reinforcement details along Grid A

Max Ast at bottom support =1927mm²

Max Ast at Top support = 2027 mm²

Reinforcement Calculation

For Top & Bottom Max Ast is 2027 and 1927 mm2

So we can provide 2 bars of diameter 32 mm and

Additional bar of 25 mm diameter to satisfies the overall Ast

2 x T32 = 1608 mm²

1 x T25 = 490 mm² ................... Hence Satisfy.

For Shear details

Right Click on Beam and Click on Details

Click on Shear Details

As per Clause 6.3.3 we have to provide Spacing till 2d from the face of the column is 100.

It should not be more than that

So provide 3 legged stirrups of 10mm diameter with 100mm spacing throught the beam length.

Step 7

Reinforcement details along Grid 3

Max A, at bottom support = 1501 mm²

Max At at Top support = 1940 mm²

Reinforcement Calculation

For Top & Bottom Max Ast is 1940 and 1501 mm2

So we can provide 2 bars of diameter 32 mm and

Additional 1 bars of 25 mm at top to satisfies the overall Ast

2 x T32 = 1608 mm²

1 x T25 = 490 mm² ...............Hence Satisfy.

For Shear details

Right Click on and Click on Details

Click on Shear Details

As per Clause 6.3.3 we have to provide Spacing till 2d from the face of the column is 100.

It should not be more than that

so provide 3 legged stirrups of 8mm diameter with 100mm spacing throughout the beam length.

Step 8:

Now we have to do Check for Sway shear.

A] For Right Sway

We know that the formula to calcuate

From Etabs Model results substitute the value -

VuD+L =92 Kn

Mas = 176 kn.m

Mbh = 295 kn

Lab = 4.725 m

Put this value in above eqn

we get,

Vu,a = 48 Kn

Vu,b = 230 Kn

B] For Left Sway

Follow the same process

We know the formula

From Etabs Model results substitute the value

VuD+L = 74 Kn

Mah = 236 kn

Mbh = 150 kn

Lab = 4.725 m

Put this value in above eqn we get,

Vu,a = 190 Kn

Vu,b = 50 Kn

C] Existing Shear capacity in beam as per Is 456-2002

We know the formula

put the values

Fy = 415 N/mm2

Asv =151 mm2

Spacing = 100 mm

d = 450 mm

put this value in above eqn

we get

Vus) = 246 … > 230 kn (Shear sway) .............(Hence Safe)

Results

Beam Design is done successfully with detailed reinforcement.

Provide reasons for failure of the middle span along grid A. What are the possible ways this issue can be resolved?

The main reason of failure of middle span along grid A is shear stress is exceeded the limiting value

This may be because of the higher Shear force acting on that beam and due to provision of weak shear reinforcement at the end supports.

This Issue can be solved by

By providing Higher grade of concrete in that particular section

Or by reducing the Shear force in that beam section

or by providing higher shear reinforcement which can resist the shear force in that section

Calculate value of the maximum shear force in any one of the spans in both the continuous beams, as per clause 6.3.3 (b) in IS 13920 2016.

As we have already calculated the value of shear force as per IS 13920 - 2016 Clause 6.3.3 (b)

We get the Shear sway value Right and Left support within limit

246 kn > 230 kn................... Safe).

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.