Reinforcement Detailing of Beams from ETABS output
AIM - i) To design beams from Etabs 2018 in detail.
ii) Provide detailed description of longitudinal and shear reinforcement for two continuous beams.
iii) Calculate the value of the maximum shear force in any of the spans of continuous beams
iv) State the causes of failure of the mean field along grid A.
Introduction -
1) Beams are horizontal structural elements used to support lateral loads.
2) In conventional reinforced concrete structures, the beams usually take the load from the floor slab, but they can also
be exposed to other loads such as wall loads, finishes, service installations, etc.
3) RC beam design and detailing includes selection of proper beam size and number of stringers
and shear reinforcement to meet the limit state requirements for bearing capacity and serviceability.
4) Then it is very important that the beam braces are properly positioned and arranged in place,
so that there is no error in construction.
PROCEDURE-
Step 1)
i) Open the Challenge 7 attachment we received and download it.
ii) After downloading, open the prompt and open it in Etabs software.
Step 2)
i) Now check the load combinations that are already created in the given modeling file.

Step 3)
i) We need to check the model before running the analysis
ii) Click Analyze
iii) Click on Check Model
iv) The structure is verified without any error and the model has been checked.
Step 4)
i) Now we need to start the beam design by selecting 'Start Design/Check'
ii) Once you click on Start/Design Check, the Show Concrete Frame Design Results window will appear.
iii) Where you can choose any design output you want
iv) So click on Longitudinal reinforcement .
Step 5)
i) Once you click on , the longitudinal reinforcement details will appear
Step 6)
1) Reinforcement details along grid A -
i) Max Ast with lower support = 194 mm2
ii) Max Ast with bottom middle = 789mm2
iii) Max Ast with highest support = 2046mm2
iv)Max Ast with top center = 511mm2
Calculation of reinforcement -
1) Up -
i) Total required above is = 2046
So we can provide
4 bars with a diameter of 20 mm and 4 rods with a diameter of 16 mm meet the total Ast
4 x T20 = 1256mm2
4 x T16 = 804mm2
4 x T20 + 4 x T16 = 2060mm2.......................
2) For Bottom -
i) Total required above is = 1945
So we can provide
3 bars with a diameter of 20 mm and 5 rods with a diameter of 16 mm comply with the total Ast
3 x T20 = 942mm2
4 x T16 = 1004mm2
3 x T20 + 5 x T16 = 1946mm2.......................
3) Shear Details -
i) Right click on and click Details
ii) Click on Shear Details


iii) According to Article 6.3.3, we must ensure that the Distance within 2d from the face of the column is 100 .
iv) It should not be more than that
v) Hence provide 10 mm diameter 3 leg stirrups spaced 100 mm along the length of the beam.

Step 7)
1) Details of the reinforcement along the grid 3 -
i) Max Ast at lower support = 1042mm2
ii) Max Ast at bottom middle = 1501mm2
iii) Max Ast at highest support = 1940mm2
iv) Max Ast at top middle = 485mm2
Calculation of reinforcement -
1) for top-
i) Total required above is = 1940mm2
So we can provide
3 bars with a diameter of 20 mm and 5 rods with a diameter of 16 mm comply with the total Ast
3 x T20 = 942mm2
4 x T16 = 1004mm2
4 x T20 + 4 x T16 = 1946mm2......................
2) For lower -
i) Total required above is = 1501mm2
So we can provide
3 bars with a diameter of 20 mm and 3 rods with a diameter of 16 mm meet the total Ast
3 x T20 = 942mm2
3 x T16 = 603mm2
3 x T20 + 5 x T16 = 1545mm2......................
3) shear Details -
i) Right click on and click Details
ii) Click on Shear Details


iii) According to Article 6.3.3, we must ensure that the Distance within 2d from the face of the column is 100 .
iv) It should not be more than that
v) So provide 3-legged stirrups of 8 mm diameter spaced 100 mm along the length of the beam on both sides
vi) And provide 3-legged stirrups of 8 mm diameter with 150 mm spacing at mid span.

Step 8)
i) Check for Sway shear.
A) For the right Sway
formula for the calculation

From the Etabs model results, substitute the value -
i) VD+Lu= 92 Kn
ii) Mas= 176 kn-m
iii) Mbh= 295 kn
iv) Lab = 4.725 m
Paste this value above eqn
we will get ,
Vu,a= 48 Kn
Vu,b = 230 Kn
B) For Left Sway
From the Etabs model results, substitute the value -
Paste this value above eqn
we will get ,
i) VD+Lu= 74 Kn
ii) Mah= 236 kn
iii) Mbs= 150 kn
iv) Lab = 4.725 m
Put this value in above eqn
we get ,
`V_(u,a)`= 190 Kn
Vu,b = 50 Kn
C) Existing shear capacity in beam as per Is 456-2002
i) Known formula -

Insert values -
i) fy = 415 N/mm2
ii) Asv = 151 mm2
iii) Spacing = 100 mm
iv) d = 450 mm
put this value above eqn
we will get
Vus) = 246 kn............................

Result -
i) Beam design is successfully done with detailed bracing.
ii) State the reasons for the failure of the mid-span along grid A. What are the possible solutions to this problem?
1) The main reason for the failure of the mean field along grid A is the shear stress exceeding the limit value
2) It may be due to higher shear force acting on this beam and to provide weak shear
reinforcement on the end supports.
3) This problem can be solved -
i) By providing concrete of higher quality in this particular section
ii) Or by reducing the shear force in this section of the beam
iii) Or by providing higher shear reinforcement that can withstand the shear force in the given section
iii) Calculate the value of the maximum shear force in any of the spans of the two continuous beams,
as per clause 6.3.3 (b) in IS 13920 – 2016.
Since we have already calculated the shear force value as per IS 13920 - 2016 Clause 6.3.3 (b)
We get the shear swing value Right and Left support within the limit
246 kn > 230 kn ...................( Safe )