Project 2_Design & Analysis of a Hostel building at Guwahati, Assam
Aim:
- Etabs model for the two blocks on either side of the expansion gap
- Foundation details illustrating the pile & pile cap reinforcement
- Tie beam details connecting the pile caps
- Column reinforcement
- Framing plan for typical floor
- Beam reinforcements for ground floor
Procedure :
*To model the plan in etabs software
*The first step is to add the grids
*According to the plan the grids are added


*Then the materials are added to the model
*define > materials
*Concrete , steel
*


*Now the beam, column sizes, and slab properties are added
*Section properties >frame sections


*define section properties > slab sections

*edit the storey height


*Now the columns need to be added
*Quick column draw > all stories

*Add the restrain joints
*Assign > joints > fixed support

*Beams are added to the model
*all stories > quick draw beams

*Similar stories >slab

Define load cases > load pattern .
According to the code

dx=67.68m
H=17.3m
Tx=0.18 = 0.2 seconds
Dy= 13.3m
H=17.3m
Ty=0.42

*Now the dead load is added to the model
*Floor finish = 1 Kn/m^2

AAc wall loading = 3.5 Kn/m^2

Live load according to the code is taken as 2KN/m^2

*Now define the mass spectrum :

Response spectrum :

Load cases:

Load combination:

*Diaphram is added

*Now we need to run the analysis :
*Before runing lets check the analysis

After the analysis of the model

*Now we need to check the storey drift



*Now we need to create reinforcement detailing for beams and columns

Column reinforcement :

Beam Reinforcement :


_________________________________________________________________________________
*Design of foundation using safe software :
*Export the etabs files to safe software
*Next step is to import the safe file to the software



*Materials like concrete and steel needs to be defined


*Define column ,pile and pile cap properties



The pile is added

Columns are added :

PIle cap are added

**After the strips are added
*Now the analysis are done

Slab designs are checked
Punching shear :
Everything is less than 1 so safe

Result :
The project is succesfully completed