Challenge

Project 2_Design & Analysis of a Hostel building at Guwahati, Assam

 Aim:

 To carryout modelling, analysis, design and preparation of construction drawings of a G+3 RCC hostel building situated in Guwahati Assam. 

 Procedure:

  • Open the ETABS software and then provide the required information to create grids and stories as shown below.

              

              

              

  • Next define the material property i.e., concrete as (M25) and rebar as (Fe415 and Fe500).

             

              

              

               

               

  • Now, define section properties. i.e size of beams as (400x500), size of columns as (450x650) and thickness of slabs as (150mm) etc.
  • Go to Define and then choose section properties then select Slab properties.
  • Also, define a slab for staircase as one way slab.

              

              

             

             

              

               

  • After defining the materials, place the components.

                    

  • First place the frame elements and then slab elements.

                     

  • Now define the load cases.
  • Go to Define then select load cases and then Provide DL, LL, Eqx, Eqx+, Eqx-, Eqy, Eqy+, Eqy- as loads.

                        

  • Assign the following loads: 
    • For live load take the value as 2 `(kN)/m^2` with reference to IS 875:part 2.
    • Brickwall load as 3.5kN/m
    • Floor finishes as 1.5`(kN)/(m^2)`

                      

                     

    • Next assign the joints in their respective positions
    • Then define the mass source and response spectrum function for the building modelled till now.

                       

                      

  • Now, define the load combinations.

                        

  • After that assign diaphragm to the shell.

                       

  •  After that, we have to carry out the analysis and design.

                        

  • Also check for story drifts for RSx and RSy.

                     

                    

  • Here, both the story drifts are within the limits provided by codal provisions. 
  • Next, we have to carry out the concrete frame design and then extract the design results for beams and columns ( for both flexural and shear rebar).

                     

  • Beam- longitudinal reinforcement

                              

  • Beam-Shear reinforcement

                              

  • Here, the design result shows that 3 beams are failing in shear.
  • Hence inorder make them safe, we need to increase the size of the beam.
  • So, for 2 beams size have been changed to 450x650mm and for other beams size is remained as it is i.e., 450x750mm.
  • Beam - Longitudinal reinforcement

                                  

  • Beam - shear reinforcement

                                 

  • Column - Longitudinal reinforcement

                                

  • Column - Shear reinforcement

                                

  • Now, the design part is completed.
  • Now, we need to export the Base reactions and load conditions in f2k format for footing design using SAFE software.

                                

  • Now, import the f2k file into the SAFE software.
  • All the reactions and loads have been imported to the software.

                               

  • Define the materials for concrete and rebar as shown below.

                               

                               

                              

  • Define slab properties.

                             

                              

                             

                             

  • Now using draw point option, draw the points for footing for each column.

                           

  • Now, go to draw option and draft points on footing for the piles to be projected.

                        

  • Next, provide pile, using the above process and also mention material property as pile500.

                  

  • Then place the columns along the grid intersections.

                   

  • Define beam for tie beams.

                  

                   

  • Now, assign springs at the locations, where piles are placed.
  • For this, we need to calculate the spring constant: 
    • Spring constant= AE/L=490873 N/mm.
    • Then assign this spring constant.

                   

  • Now, define the load combination for serviceability limit and ultimate limits.

                     

  • Next, check the design results:
    • Displacement values are within the permissible limits, hence  it is safe.

                         

    • Reaction check :

                        

  • Punching shear values are also within the range.

                      

  • Design the strip.

                        

  • Now, carryout the design again:
    • For strip layer A
  •              
    • For strip layer B

                    

  • Hence, the design of required footing is completed.

Result:

Modelling, analysis and design of G+3 hostel building has been carried out successfully using ETABS software and the foundation design(Pile cap and pile) has also been carried out successfully using SAFE software.

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.