Challenge

Project 1

Q.1. Design a battery pack for a car roughly 150 Kw with 120 V. Use 3500 mAh 3.6V nominal NMC chemistry cell.

a. Design the battery pack configuration.

b. Draw the BMS topology for this battery pack.

Solution:

Rated Power (P rated) = 150kW

Rated Voltage (V rated) = 120V

Nominal Cell Capacity = 3500mAh

Nominal Cell Voltage = 3.6V

Rated Current (I rated) = Prated/V rated

= 150*103/120

Rated Current (I rated) = 1250A

Number of Cells in series = V rated/Nominal Cell Voltage (assuming maximum voltage = rated voltage)

= 120/3.6

Number of Cells in series = 33.33

Case 1: Considering Number of Cells in series as 33

Total Battery Voltage = Nominal Cell Voltage*Number of Cells in series = 3.6*33

Total Battery Voltage = 118.8V

Case 2: Considering Number of Cells in series as 34

Total Battery Voltage = Nominal Cell Voltage*Number of Cells in series = 3.6*34

Total Battery Voltage = 122.4V

As the Total battery voltage in case 2 is higher than the rated voltage, number of cells in series is taken as 34

Number of Cells in series = 34 cells

Number of cells in parallel = Rated capacity/Nominal cell capacity

= 1250/3.5

Number of cells in parallel = 357.14

Case 1: Considering Number of Cells in parallel as 357

Total Battery Capacity = Nominal cell capacity*number of cells in parallel = 3.5*357

Total Battery Capacity = 1249.5Ah

Case 2: Considering Number of Cells in parallel as 358

Total Battery Capacity = Nominal cell capacity*number of cells in parallel = 3.5*358

Total Battery Capacity = 1253Ah

Number of Cells in parallel = 357 cells

Therefore, the battery pack configuration is 34S357P

Master Slave BMS topology is used for this battery pack. In this architecture, there is typically one "master" module that oversees and controls the overall operation of the BMS, and multiple "slave" modules that monitor and control specific subsets of the battery pack. The master module communicates with the slave modules to gather information, make decisions, and ensure the proper functioning of the entire system.

The master-slave architecture allows for the scalability and modularization of the BMS, making it suitable for large battery packs with numerous cells. It also facilitates communication and coordination among different parts of the battery pack, ensuring safe and efficient operation.

Master Slave BMS Topology

Q.2. Build a 3S2P battery pack configuration with generic battery block using Matlab/Simulink.

Solution:

Aim: To build a 3S2P battery pack configuration with generic battery block using Matlab/Simulink.

Theoretical Calculation:

Nominal voltage of cell = 3.6V

Capacity of cell =3.5Ah

Maximum voltage of cell =4.2V

Number of cells in series = 3

Number of cells in parallel = 2

Nominal Voltage of battery pack = no. of cells in series * nominal voltage of a cell = 3*3.6

Nominal Voltage of battery pack = 10.8V

Capacity of battery pack = no. of cells in parallel * Capacity of a cell = 2*3.5

Capacity of battery pack = 7Ah

Maximum Voltage of battery pack = no. of cells in series * Maximum voltage of a cell = 3*4.2

Maximum Voltage of battery pack = 12.6V

Blocks used:

  • Li ion battery (6)
  • Bus Selector
  • Powergui block
  • Controlled current source
  • Constant block
  • Voltage measurement
  • Scope block
  • Display block

Simulink Model:

Cells are connected in 3S2P configuration (3 cells in series and 2 cells in parallel) as shown in the above figure. A Constant current source with the capacity of 3.5Ah (constant block) is connected to the battery pack acts as the load. The voltage measurement block is connected to measure the battery pack voltage. Scope is connected through the bus selector, which provides the voltage, current and SOC of the cell.

Result Screenshot:

The simulation is run for 1000sec.

Conclusion:

Simulink model for 3S2P battery pack configuration is built with generic battery block. The simulation is run for 1000sec. The SOC of the battery has reduced to 86.1% from 100% and the maximum voltage of the battery pack has dropped to 11.6V.

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.