Project 1
PROJECT-01: Prepare a Plan to contruct a Bridge which will 6 days working calendar and WBS like Identify the Problem, Determine Constriants, Analysis of Design, Design Refinement, Implement Plan, Construction, Pre-streseed concrete, Final Step and Testing & inception.
- KEY HIGHLIGHTS
A- Create a Calendar:
We have created 2 calendar for this project.
1. Normal Calendar:
- 6 days workweek
- 9:00 AM to 7:00 PM (10 hours work timing)
- 1:00 PM to 2:00 PM (1 hour break)
- Total working hours = 9 hours

2. Task Calendar:
- 7 days workweek
- 8:00 AM to 5:00 PM (9 hours work timing)
- 1:00 PM to 2:00 PM (1 hour break)
- Total working hours = 8 hours

B- Create a Project:
We have created a project
- Project ID :- P-01
- Project Name :- Construction of Bridge
- Total Activity :- 55
- Calendar :- Normal Calendar

C- Create a work package for a project:
We have created 7 work package for the project "Construction of Bridge".
| WBS CODE | WBS NAME | TOTAL ACTIVITY |
| P-01.A | Civil Work | 10 |
| P-01.B | Electrical work | 10 |
| P-01.C | Commission | 3 |
| P-01.D | Installation | 15 |
| P-01.E | Termination | 4 |
| P-01.F | Tests | 3 |
| P-01.G | Backbone | 9 |

D- Create an Activity:
We have created the activity as per given in the question. We have assigned the calendar, predecessors and the resources. After assigning, we have evaluated original duration and budget total cost.

E- Practice Activity Code:
Add activity code to activity, for filtering out the activity which comes under the specific activity code.

F- Practice Resource Management:
After assigning the resopurces to activity > check the overallocation > if there is any overallocation > fix it with fast tracking or crashing method.

- FINDINGS
1- Find the total duration of project.
Answer: 257 days
2- Find total cost of project.
Answer: 2352377.78 rs

3- Find critical path of the project.
Answer: Red block and red lines represent the critical path of the project.


4- Draw the network diagram of the project.
Answer: Yellow block represents the network diagram of the project.
