Identification of Cracks
CHALLENGE 01
1.
a)

Observation:
- Concrete crushed and reinforcement is exposed.
- Concrete spalled beyoned the reinforcement which may be a sign of rupture.
- Beam top portion looks safe because of the flange advantage from the slab.
- The crack develops in bottom to top which means rebar yeilding occurs in support bottom only.
Answer:
- It's form of Flexural failure due to reversal of stress during earthquake.
- During stress reversal, support top experiences compression and bottom experiences tension.
- Top compression is managed by slab advantage. Bottom tension was not satisfied by the provided reinforcement.
- Since the reinforcement got yeilded, it cannot be repaired.
b)

Observation:
- Cracks along beam-column edge.
- Cracks seem to have developed through the structure as it looks much wider.
- Beam looks seperated from the column at joints.
- Concrete is not severly crushed.
Answer:
- It's Beam Pull out failure due to insufficient developement lenght of reinforcement in joints.
- During earthquake, the horizontal movement of structure makes this condition worse and detached the beam member from the column.
- Providing the anchorage length between the two existing concrete is very difficult. So, it is not repairable.
c)

Observation:
- Cracks are excatly at the joint of column-beam.
- Cracks in beam developed through its entire width.
- Slab also developed more cracks along the beam width direction.
Answer:
- It's a Plastic hinge failure.
- The damage occured only in joint zone first of all.
- Cyclic lateral loading and stress reversal at the joints led to the damage.
- Even the slab participated to its best to handle the tension, but unable to control the damage.
- The joint can be strengthened.
2.
a)

Observation:
- Concrete damaged at the top of a column.
- Spalling of concrete occurs all around the column face.
- Beams are safe.
- The location of looks at edge of the building.
- No walls are built along the column means it is probably at the ground floor, for parking car movement access.
Answer:
- It's a Soft storey failure, technically plastic hinge formation.
- Due to the absence of infill walls at the ground floor, the plastic hinge forms at the top of ground storey columns during lateral movement.
- Based on the development of cursh or spall of concrete, it can either repairable or non-repairable.
b)

Observation:
- Concrete developed complete breakage diagonally.
- Longitudinal reinforcements are intact.
- Shear reinforcement spacing looks wider, which means probably lesser shear reinforcement provided.
Answer:
- It's a Pure Shear failure.
- Inadequate shear reinforcement compels concrete takes all the shear stress.
c)

Observation:
- Concrete failed completely.
- Failure at the top of cloumn.
- There are two slabs connected to the column, probably one at mid height of the column.
- The wooden piles might be a post failure support after column failed, providing temporary prop to avoid collapse of the entire structure.
Answer:
- It's a Short column failure.
- An additional slab or a Beam connected to a column in mid-height leads to this effect.
- This leads to failure especially if the connection is unintentional and non accounted in design.
- The failure given in the picture is not at all repairable.