Challenge

Identification of Cracks

Question-1.

(a) What is the mode of failure or damage of the beams in the figure above? Are the damages repairable?Elaborate

Answer

Observation:

  • Concrete crushed and the reinforcement is exposed.
  • Cracks are large and concrete spalled out.
  • Reinforcements are visible through the crack.
  • Cracks are found at support bottom.
  • No cracks found in top of the beam.
  • No cracks fopund in Column.
  • Cracks developing from the bottom of the beam towards top direction.
  • Cracks also trying to form below the adjacent connected beam.


Discussion:

  • As the cracks are formed in the bottom of the beam at support zone which is clearly compression under gravity condition.
  • But the cracks are formed only at the bottom towards top @ support which means due to seismic/lateral forces reversal of moment and stress occurs at the Support bottom.
  • At that moment, the support bottom of the beam becomes ductile and provided reinforcement's moment
    capacity which does not satisfies the requirement moment capacity.
  • In other words, ductile reinforcement not provided or not detailed well for under taking the reversal stresses due to lateral forces.
  • In top of the beam no cracks are formed due to the top flange of the beam (T-action of beam-slab)


Conclusion:

  • It is a form of flexural failure due to the Reversal of stress due to the earthquake.
  • Since the provided reinforcement is not enough and got yielded which leads to concrete spalling which is not repairable by simple manner.
  • It requires modern retrofitting techniques to strengthen beam using external concrete jacketing and steel platting techniques are used.
  • This work result inincreased safety and durability of the structure.

Question-1. (b) What is the mode of failure or damage of the beams in the figure above? Are the damages repairable? Elaborate

Observation:

  • Cracks along Beam-Column edge.
  • Cracks seem to have developed through the structure as it looks much wider.
  • Beam looks seperated from the column at joints.
  • Concrete is not severely crushed.


Discussion:

  • As the cracks are only parallel to the beam direction it is clearly shows that it is the lateral displacement of the beam from the column connection. Which is due to the insufficient anchorage length of the reinforcement bar in the beam.
  • This insufficient anchorage length of reinforcement and poor detailing of the beam in connection location leads to the pull-out mechanism of the beam from the column connection.
  • Provided anchorage of reinforcement does not satisfy the lateral moments occurred.


Conclusion:

  • Its beam pull out failure due to insufficient development length of reinforcement in joints.
  • During earthquake, the horizontal movement of structure makes this condition worse and detached the beam member from column.
  • Providing anchorage length between two existing concrete is very difficult. So it cannot be repairable.
  • So as the beam is pulled out due to insufficient developing length and beam is disconnected from the column it is not repairable.
  • Strengthening should be done by providing brackets in the column to support the beam and to eliminate future crack developing in the beam column edge.

Question-1. (c) What is the mode of failure or damage of the beams in the figure above? Are the damages repairable? Elaborate

Observation:

  • Cracks are formed exactely at the joint of the beam and column
  • Cracks in beam developed through its entire Width.
  • In both intersecting beams cracks formed in the CS direction of the beam.
  • And also, cracks are developed in the slab in the direction similar to beam cracks.
  • Cracks Developed in slab also.


Discussion:

  • Since the observed cracks only in the beam and slab junctions which all cracks are in similar direction and also the cracks extended throughout the beam it is due to the plastic hinge formation at the junction.
  • And also, in both directions no infilled walls are present, therefore this floor shown in picture is more possibly to be ground floor or floors without walls which have high possibility to be soft storey.
  • Combining these all possibilities the occurrence of plastic hinge is possible and the failure caused due the plastic hinge failure.


Conclusion:

  • It is Plastic Hinge failure

Action Taken

  • The join can be strengthened. Since the cracks are minor it is easily repairable by providing special connection steel plates for beam and column.

Question-2. (a)

Observation:

  1. Cracks and concrete Damage shown at the top level of the column.
  2. Concrete Damage all around the Column.
  3. Beamcondition is safe.
  4. Crack occur in the beam column junction location.
  5. By referring the view of the picture, it clear shows no infilled walls present and also have possibility that it is Ground floor or a parking zone.

Discussion:

  • It is soft storey Failure
  • Top of the column spalling of concrete occurred at beam-column junction. As per the observation no reinforcement bucking was happened.
  • No infilled walls and crack occurred at the top therefore more possibility of plastic hinge formation.
  • This plastic hinge formation results in the spalling of concrete.

Conclusion:

  • It is Plastic hinge failure.

Action Taken:

  • No simple method of repair is possible.
  • column bracketing and connection plates are provided for further controlling of crack development and strengthening for stability of structure.

Question- 2.( b)

Observation:

  • Concrete developed complete breakage diagonally.
  • Longitudinal reinforcements are intact.
  • Shear reinforcement spacing looks wider.


Discussion:

  • By observing the pictures, we can assume that the cracks are formed in the mid of column.
  • No buckling of column main reinforcement occurred since we can understand this crack is not due to the axial forces.
  • And the shear links are wider in space which clearly leads to the inadequacy to counteract the shear stress of the column, which cause the cracks and concrete spalling.


Conclusion:

  • Pure Shear failure. Since it is pure shear failure clearly due to the inadequate links provided .
  • it is not repairable by simple means.

Action Taken:

  • Need to retrofit the column section by using composite structures like external column jacketing using steel plates and shear plates are provided or any other composite techniques should be followed.

Question -2. (c)

Observation:

  • As shown in the picture Column completely failed.
  • Failure are at the top of Column.
  • Beams are standing only due the external temporary support provided (Bambu is Given)
  • Another mid-level slab is resting in the column.
  • No infilled walls are there and also seems to be external column.

Discussion:

  • The Mid-level slab resting in the column in between the effective length of the column which provide stiffness at the intersection zone
  • And made the column acts as short column which absorbs more stiffens and axial force all around.
  • For that condition the columns are not designed which results in column failure.
  • The wooden piles might be post failure Supporting after column failed , providing temporary prop to avoid collapse of the entire Structure.

Conclusion:

  • Short column failure. Total column failed due to the short column failure effect. Since it is not repairable.

Action Taken:

  • We have to introduce steel props for temporary supporting of the column to prevent complete failure of the structure.
  • Column jacketing should be suggested for strengthening of the structure.
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.