Preliminary and Detailed Site Investigation Stages Explained

A free lesson from Skill-Lync's Sub Surface Exploration and Geotechnical Investigation course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 2 Part 2”

What will you learn in this free Sub Surface Exploration and Geotechnical Investigation lesson?

The instructor covers the preliminary exploration with trial pits, geophysical methods and light cone penetration, including cone refusal at bedrock. The lesson then outlines the detailed stage: technical specification, bill of quantities, test locations and depths, factual report and interpretative report.

  • Trial pits, geophysics and light cone tests
  • Cone resistance refusal indicating bedrock
  • Engineered fill criteria such as fines under 5%
  • Specification, factual report and interpretative report

What comes after lesson 3?

Later in Skill-Lync's Sub Surface Exploration and Geotechnical Investigation course (paid): lesson 4, Part 3; lesson 5, Part 4; lesson 6, Week 1 Session 3. The full course has 51 lessons (24 h 6 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Then, once you finish your DISC study and the field recognizance, you should go for a preliminary site exploration. That is, you have to give a minimum number of tests to foresee the strength of your soil. So, what you do is, you give some trial pits, some geophysical methods you conduct, so-called penetration test. So, I will be discussing about trial pits and geophysical methods, penetration test in the later stage. Now, if you see the trial pits, trial pits is nothing but cut open of, like, a large bulk volume of your samples.

So, I will be discussing a few things in later slides. So, for the preliminary investigation, this is only for giving you the rough idea of your strength of your soil. So, if you cut open your large volume of your sample, maybe you can determine some kind of engineering properties. You can visually identify what is the soil present. And some geophysical methods you would have learned about, seismic refraction, a few more geophysical methods in your semesters. So, these are the few kind of simple methods which you can do prior to your detailed stage of your project.

And then cone penetration test. So, you have a light cone penetration test. You can insert your cone penetration for a few meters, like, to, for, like, until 5 meters. You can insert and you can see whether the cone is very hard to insert or cone is just going very easily. So, these are the few things which you can do during your preliminary site investigation program. Okay. Now, I will show you one figure. So, basically, this is your geological hammer. So, this geological hammer, a geologist will be carrying to find out the strength of the soil.

Maybe he will hit on the ground to find out the strength of the soil. Maybe, suppose you have done a trial pit. That is, I cut open the large volume of the soil sample and below ground surface, below 3 meter ground surface, you are just hitting with this hammer. And then, if it is easily going, then, if you are hitting the hammer and it is having a huge amount of settlement there itself, then you conclude if there will be a loose sand or it will be a soft clay, something like that.

So, if you hit your hammer and you have very hard strength, then you evaluate that as a, the soil may be very dense sand or it can be a very stiff clay. So, using this, this is a portable equipment you can carry, like, as I showed you earlier, GPS equipments and this geological hammers, where you can easily carry it your, when you are doing your site visits. Okay. Now, let's get back to the slide. So, you should know why we do this preliminary site exploration. So, it gives some amount of information on the soil strata, like, means of a geological hammer or doing a cone penetration test.

You will give, you will have a feel of what is a type of the soil present, whether it is a very loose or it is having a medium strength of the soil. So, if you have a cone penetration, even in very dense sand, it is very hard to penetrate the cone. If there is any loose fill on the top of the bedrock, in the loose sand, your cone might penetrate very easily. But, when, once, when it reaches a bedrock, it may not penetrate. So, in that case, you might conclude that a bedrock has been reached.

Suppose there is a loose fill for 5 meter and from the 5th meter below a ground surface or below your ground level, bedrock starts and the cone is not penetrating. So, it is giving you a cone resistance of greater than 50 MPa or you can even say cone resistance of 35 MPa. Then, you can term that as a refusal. Actually, when you term this cone resistance greater than 25 MPa or 35 MPa, you term it as a refusal. And, thereby, you can conclude your bedrock has been started.

Okay. So, next, as I showed you the previous slides about the ground water conditions, you have to foresee if there are any local water bodies present. Or, if in the marine conditions, like marine structures, your high water tide will be very high. So, all this kind of hydrological data, you have to be very sure. And, the location of the extent of the natural cavities. Same thing as I have shown you in my previous slides. The natural cavities. What is the size of your natural cavity? If it is very big or very small, how to treat it with the ground improvement methods?

That's the occurrence of the soft material in between the soil layers. Suppose, from 0 m below ground level to 5 m, you have medium dense sand of medium strength. Again, from 5 m to 10 m, you have soft clay. And, then, from again 10 m to 15 m, you have dense sand. So, in between this medium dense and dense sand, you have existing soft clay. So, you should even see how to treat this. So, all this will be foreseen in your preliminary site in investigation itself.

And, then, suitability of the soil for its use as an engineered fill material. As I shown in the previous slide. So, in this, even fill this gap. You should see whether this material is suitable. So, or else you have to bring the material from somewhere else. So, suppose this elevation is plus 20 and this is plus 19. Suppose, a client is giving you plus 21 as a final ground elevation. Then, you have to bring the material from elsewhere and to see whether that material is suitable.

Or else you have to foresee even this material is suitable to fill from plus 20 to plus 21. From plus 19 to plus 21. That is what. If you have this medium strength of this material, you have a criteria for any material to be filled as a backfill material. You should pass certain criterias. So, these criterias are always in the method statement. So, when you take the earthwork topic. So, you will have certain criterias. A plastic limit should be like it should be non-plastic. And your sieve size, the material passing through this point that is a fine material.

So, it should be 5% less. So, all this kind of criterias should be satisfied to use this material itself as a backfill material. That is backfill material in the sense you have to fill your ground from plus 20 to 21 and plus 90 to 21. So, this is called as engineered material. The material which is passing all the criterias like a plastic limit, non-plastic and the fine should be less than 5%. So, all these criterias, if a material is fulfilling, this is called engineered material. So, that is why you have to see the suitability of the soil for its use as an engineering fill material.

Next. Now, using your geophysical methods or it is called as a geophysical survey, one can determine what is the depth of the bedrock. Suppose you have a top or some soft clay or medium dense using some electrophysical methods or some geophysical methods. So, you can find what is the level of your bedrock. This brown indicates that your level is from minus 1 to minus 8. And then this blue indicates your level is from 1 to 10. If you put this in a contour, then it will be like this.

So, if you can ask me why the level is minus 1, minus 2, minus 3. Because this is a seabed level. So, let's go to the whiteboard. In offshore structures, if you see, this is your, not the ground surface, this is your water level. Maybe your seabed may be present here. This is your top of your soil bed. Okay. This is your water. Okay. In this full area, maybe it is full of water. This is where your soil starts. Okay. From this level. So, this normally you refer as water level.

So, water level will be always referred as MSL. Mean sea level. Okay. And then the symbol you call it as, in form of triangular shape like this. This is your water shape. And this from here, it will be your ground surface. So, this level, for offshore structures or marine structures, you call it as, sea bed level. So, this might be minus, okay. So, it will be minus 1 M SVL. Okay. And then same way, this would be minus 2, minus 3. So, this would be minus 2.

This will be minus 3. Okay. So, in this case, if you see for the rock bed, let's go back to the slide. So, this is maybe from the land it is starting. So, 0, 1, minus 1, minus 2, minus 3, minus 4. So, if you take a cross section like this in the diagonal way. So, it will be like a heap. So, I will show you in the whiteboard. On the left. So, if you take a cross section like this. So, if you take a cross section like this you can take a cross section like this.

From brown, if you start from the brown, and then you go to the blue. Let's see how this is going to look like. Let's go to the whiteboard now. Elevation would be like this. Your rock profile would be like this. So you are starting from minus 8, then minus 7, minus 6, minus 4, minus 3, minus 2, minus 1, 1, 0. So then you will have a hike 1, 2, 3, 4, 5, 6, 7, 8, 9, 10. So this is your elevation of the rock profile.

So this level you call it as here. This you call it as minus 8, minus 8, M, seabed level. So your water will be here, 0. So this would be 0, M, okay. And then this would be plus 10, plus 10, M, seabed level. Once you reach this level, then you are on the land, okay. With a little amount of water might be present. But once you reach the land, then you call it as a datum, okay. So your rock profile will be like this, from minus 8 to plus 10. So this is what it is shown in the 3D figure here.

Actually it is in the 2D figure. So what I have drawn is a 3D figure for you. So if you take a section here, whatever I have drawn here would be representing, okay. It represented my bedrock profile. So maybe here you have a big lump of soil depots. It's like it can be a medium dense sand or very loose sand from this. But here it may be a few meters of the soil and then your bedrock will stack. So it is like that. These are findings you can do using your geophysical surveys.

And then next, if you want to have your groundwater mapping. So even you have a geophysical methods to do that. So if you see here, this is your kind of very light brown and then you have a very dark blue here actually. So if you see this red marking, so the contour lines. So if you see this is a minus 4. So this is into the sea. So if you go here, this is on the land plus 5. So your water profile is varying from minus 4m seabed level to plus 5m chart datum.

So these are all things which you can find out initially during your preliminary site investigation, okay. Next, once you finish your preliminary site investigation, you will be going into a detailed stage. This is where you will have to find out, I mean you have to recommend a few more additional tests. So a stage will come where only the preliminary investigation is not enough. Then we have to proceed into a detailed stage. If it is a small budgeted project, whatever test I have shown you until now would be enough.

But if it is a multi-story building, if it is a bridges, tunnels, then you will have a detailed site investigation. You have to recommend a few more tests. So all the few more tests, what all to recommend, it is shown in the future slides. So you have to, as a geotechnical engineer, in the detailed stage, you have to perform few more stages so that you can complete your geotechnical investigation program. Why is this a detailed investigation is needed? So as I said, it is for complex loaded structure.

If it is a tunneling, if it is for bridges, or if it is for a multi-story building, if it is a plus G plus a 22, G plus 40 building, then it is a complex load. For that, you have to go for a detailed geotechnical investigation. Then, as I said, if the preliminary investigation is not sufficient, you have to extend your geotechnical investigation. So, what is the stages in the detailed geotechnical investigation? First, you have to prepare your specification. That is nothing but the geotechnical investigation specification.

So, in that, you have to recommend a few more tests. So, where all the boreholes has to be located. Like, you have to give your standard penetration test, cone penetration test, plate load test. I will show you in the future slides. So, all these tests which you are going to recommend, you have to put it in a specification format. So, where to do your borehole test. So, what is the spacing of the boreholes? What is the depth of their boreholes? How the borehole test has to be conducted?

And then, for example, then cone penetration test. How the cone penetration test has to be conducted? Which cone has to be used? And then, what is the spacing of the cone penetration test? What is the spacing between the boreholes and the cone penetration test? Where the plate root test has to be specified? How the laboratory test? What all the laboratory test has to be conducted for your project? Suppose you have to have your cohesion and angle of internal friction. You need your direct shear test or tri-axel shear test.

So, that test has to be specified. So, all this kind of a detailed specification based upon your project need. You have to prepare your technical specification. Next comes the bill of quantities. So, you have to prepare your bill of quantities of your soil investigation. This I have shown in the future slides. I will show you how to prepare the bill of quantities. And then, you have to decide the location and depth of the investigation point. So, where all you have to give your borehole points? Where all you have to give your cone penetration?

Where you have to give your plate load test? So, all this kind of layout you have to prepare. And then, depth. So, borehole has to go for how many depth? Like your first 10 meters or 20 meters or 30 meters, 40 meters. So, you have to recommend the depth of the investigation point. And then, after preparing all this technical specification, bill of quantities, deciding on the location and depth, you have to expedite. Expedite is like doing your soil investigation program. How do you carry out? So, you will hire your soil investigation contractor for this.

So, he will do a soil investigation program for you. And then, finally, you have to get the report from the soil investigation contractor. And then, from him, you have to review all the factual data. Factual data is nothing but whatever the field test you are conducting. That is, the soil investigation subcontractor is conducting the field test. And then, laboratory testing he is conducting. So, all these are called factual data. So, that will be put in the report format, which is called as a factual report. So, as a geotechnical engineer, you have to get the report from the soil investigation subcontractor.

And you have to review all the datas. And from the factual report, then you have to prepare a interpretative report, geotechnical interpretative report, from the factual data. That is, from the field test, laboratory test, you have to sum up everything. And you have to determine your shear stem parameters, unit weight, what is the moisture content, what is the liquid limit, plastic limit, everything. You have to sum up everything. And then, you have to use those parameters for your design. So, this is the whole process sequence in the detailed investigation program.

So, we will see, look into in the future slides. We will be seeing how these stages have been given in the detailed format. Okay. Now, let's get into preparation of the technical specification. So, what are all the things you have to specify in your method statement? And method statement is also called as a technical specification. So, you have to refer to your IS codes or if you are inside your Indian country, then you have to refer IS codes. Same if you are in Indian country and looking for the outside projects, like if you are dealing with the UK projects or US projects or Middle East projects, then you have to refer to British standards, ASTM, Hashtag standards.

So, it is just a reproduction of some kind of codes and standards. So, you should not exactly copy-paste, but you have to specify what is your need based upon your project. The standard document that describes the field and laboratory test procedures. So, that is what I said. In the standard, suppose there is a SPT, a standard penetration test described in the code. You have to take a few points from that. You have to decide what is your need. Suppose you have to do a standard penetration test every one meter.

So, one meter below your ground surface, two meter below your ground surface, three meter and so on. So, these kind of project needs, you have to specify in your technical specification as well as a laboratory test. So, how many laboratory tests you are in need of or what are the tests like you have to specify moisture content test, UCS, that is an unconfined compression test. Direct shear test, dry axis test, and Atterberg limit test. So, you have to specify all those things in your technical specification.

So, as I said, it is required to mention the specific requirements from the standard procedure. So, some examples I have given. So, you would have learned many drilling techniques. So, I have covered in the next slide also. For the next big course, I have covered what are the drilling techniques. So, you have auger boring, wash boring, rotary drilling, and percussion drilling. So, if you want the contractor to use only rotary drilling, so you have to mention use a rotary drilling method to collect good quality soil and rock samples.

And conduct the standard penetration test every 1.5 meter and the starting depth. Suppose your borehole depth is like 0 meter from ground surface. So, below 1 meter, you have to start your standard penetration test. So, 1, 1.5, then every 1.5. So, 1.5, 3 meter, 4.5 meter, and then 6 meter, 7.5. So, it goes on like that. You have to specify that very clearly in your technical specification. And collecting undisturbed samples every 3 meter interval. So you have a sampler for your undisturbed, for collecting your undisturbed samples. So that should be done at every 3 meter. So you have to stand 3 meter below your ground surface. 3 meter, 6 meter, 9 meter, 12 meter, 15 meter and go on. And conducting your plate load test. Suppose your building load is 150 kPa. So you always give your design load for testing.

your plate load 1.5 times or till the failure of your plate. So if you, if it is 150 m, 150 kPa. That is 150 kN per meter square. You can specify it as you have to go till 600 kN per meter square. Okay. And then plate diameter. So it can vary from 30 centimeter to 70 centimeter also. So you have to specify your plate diameter level of the test. So this is very important. So you have to specify where the plate test has to be conducted.

So it shall be 0.5 meter below your ground surface or 1 meter or specifically like 1.2 meter, 1.5 meter below ground surface or 3 meter below ground surface. So all this kind of in detail project requirements you have to specify in your technical specification. And then the specification also covers deliverables like you should ask your soil investigation subcontractor. The subcontractor might use their drillers and supervisors to do this investigation program. So when you go for a site visit as a geotechnical engineer, you have to ask them the field record. Suppose they have, they would have done the standard penetration test today and you have to go and ask them about the field records.

So they would have done the standard penetration test. So they would have done the standard penetration test. So you have to ask them logging of that. So once they finish the SPT test at 1 meter, they will log it. 2 meter, they will log it. Same way, cone penetration test also. Once they finish, they will log it. So you have to collect all that factual data day to day. Okay. And then field report. Field report same way. Like when they are coming, when they are going, how long they are present at the site. So all this kind of field report you have to get from them.

And then preliminary laboratory test results. So once you have given the specification to them and then after finishing day to day field test, these field test soil samples has to be taken to the laboratory. So as a geotechnical engineer, you have to ensure that whatever soil samples they have collected in day work, they have to safely transport to the laboratory also. So on those soil samples or rock samples only, they are going to conduct the laboratory test. So once they have finished, so they have done the laboratory test. So they have to send the laboratory test results day by day. So those things also you have to ensure not only the field test, even the laboratory test.

Even you can go to the laboratory test. I mean, they are testing laboratory itself for the ensure whether they are doing their laboratory test correctly or not. And then finally the factual report. So this factual report is nothing but the collection of the field data and the laboratory data. So this totally they will be putting in a report which is called the factual report. So ok, for instance, we are using that graph. So this is good. You

Want the rest of Sub Surface Exploration and Geotechnical Investigation?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Sub Surface Exploration and Geotechnical Investigation course

The remaining 48 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Sub Surface Exploration and Geotechnical Investigation course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.