Fireproofing Pipe Racks: Passive and Active Systems

A free lesson from Skill-Lync's Design and Analysis of Piperack Structures using STAAD.Pro course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Fireproofing Methods: Passive vs. Active Systems”

What will you learn in this free Design and Analysis of Piperack Structures using STAAD.Pro lesson?

The instructor compares passive fireproofing (poured concrete, lightweight concrete, cementitious coatings, gypsum boards) with active water spray systems, noting that passive systems are usually rated for 2 to 4 hours. The lesson also lists effects on pipe rack design, such as extra dead load and seismic mass, and a larger surface for wind load.

  • Passive versus active fire protection
  • Poured concrete and gypsum board fireproofing
  • Added dead load and seismic mass
  • Extra wind load from fireproofed profile

What comes after lesson 3?

Later in Skill-Lync's Design and Analysis of Piperack Structures using STAAD.Pro course (paid): lesson 4, Thermal Load Considerations in Pipe Rack Design; lesson 5, Framing of Continuous or Conventional Pipe Rack; lesson 6, Grilled Modeling Technique for Shear Wall Systems. The full course has 49 lessons (21 h 20 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Why fireproofing is used? Fire protection can be provided by passive systems or active systems. There are many commercially available tested and listed passive systems. Systems are usually rated for 2 to 4 hours. So, to protect our structure for fire, like to get them fire protection. So, there are 2 systems. One is passive system and one is active system. And, now, as I already told you, so, the systems are usually rated for 2 to 4 hours. Like, you know, it depends upon the client requirements or there is a design.

Like, you know, what does that mean? That systems are usually rated for 2 to 4 hours. Means, we are buying time when it case of fire for 2 to 4 hours. So, that, you know, in between 2 to 4 hours, there is possibility to come a rescue team and make a control on the fire. Typical passive systems include normal wet concrete, light wet concrete, spray on cementitious coating, coatings. Coatings may be shop or filled applied. Now, what are the passive systems? In this case, there is a possibility that the weight of concrete or the lightweight concrete is applied. Like, if there is a framing of steel structures, then a thin layer of concrete is applied.

So, it depends, like, how much thickness is applied. So, it depends, like, how much thickness is to be applied and how to proceed that. So, that is an another theory. Like, how to design thickness of concrete when it's case of fire proofing and all that. Thus, the coatings may be shop or field applied. Maybe a shop or a field welding depends actually. Active systems such as fire water spray system are less common. So, this is very conservative and you can call it conventional method as well where the water spray systems are adopted or they are placed.

So, when in case of fire, the alarm will burn and the breakage of system is there and that will cause the spraying waters all over the plant. But that is very conservative actually. Nowadays, we are not at all using this system because, you know, you can't buy time in this case. It totally depends upon in that case because putting up just water to avoid fire is not an option. So, this is very conservative method and nowadays we are not using. You can see these active systems in many of the, you know, commercial plants or commercial or residential buildings or you can see in a mall and all that.

So, yeah, for that it's adopted. So, yeah, for that it's adopted but for industrial, it is not at all recommended. The type of system selected depends on client's preferences and economics. It also may be dictated by the industry specific standards provided by the National Fire Protection Association. So, as I told that this is totally depends upon the client's criteria, his preference and how much he want to spend on this particular thing because the fireproofing can affect cost of the project tremendously. So, and it also depends upon the size and we do have National Fire Protection Association codes.

So, as we have IS codes like 456 for concrete but, yeah, in National Fire Protection Association, they have their own standard. They have made the standard and it is kind of code only. So, like we can get some kind of idea after going through that code like, you know, how to calculate this two to four hours. Then how to calculate, you know, how to apply this norms of, you know, applying concrete and then applying the coatings and all that. Then in case of water spray, what will be the intensity of the water or what will be the intensity of the flow, then how much volume of water is required in storage.

So, that is all been given in this code. So, we can go through all this in details by reading this particular code. The traditional method of fireproofing has been poured in place concrete. So, generally nowadays, pouring concrete in place is considered to be traditional method. And this is a form of plain concrete itself. They are using plain cement concrete which we call PCC. So, it can be either M10, M15 grade of concrete because the main purpose of placing concrete is just get them some kind of fireproofing protection.

So, grade is not that important. But as IS code says that, you know, we have to use M10, at least M10 in terms of PCC. So, other fireproofing materials such as light wet cements, prefabricated cementaceous board and intumeset coating are used to a lesser extent, primarily in areas deemed less critical and where weight reduction is a significant benefit. So, other fireproofing materials such as lightweight cements, then some kind of cementaceous board prefabricated, which you call as, you know, gypsum boards and all. So, they are also used.

Then some kind of oily coatings are used to a lesser extent, like, you know, they are not more effective, but yeah, we can use them where there are lesser chances of fire. You can't predict fire, but in a whole project, yeah, there might be some kind of utility areas. There are high risk of fire. So, in that case, the traditional method is used and in other area, where are very less chance of fire, then we can use the other fireproofing techniques. One more thing we have to consider because while designing pipe rack or while applying the loads on it, if you are planning to apply the traditional method of fireproofing, that is in pouring concrete.

So, you have to take consideration of dead load of that concrete as well, because that will be a very huge failure if in case you are not applied concrete weight while placing the loading. So, that we will consider as a self-fed and we will discuss that in details when we actual start STAAD.Pro and applying the loads. So, these are some examples of fireproofing on steel elements. So, as you can see, this is one of the I-member, this is another I-member. Now, in this case, the I-member is filled with the concrete.

So, it is sprayed on cementitious fireproofing. So, it is kind of cementitious material or concrete. So, the I-material is coated with this fireproofing material. So, the epoxy concreting is generally used while doing this. And this is carried out once your frame is placed on the side. Then only it is possible to have this epoxy concreting. Now, what is epoxy concreting? Epoxy concreting is like concreting on the surface of the material by having jack injection. Like, it is an injection kind of equipment. And once you start applying, then it will go like a spraying on the particular surface of this material.

Now, this is gypsum board. Now, as you can see, this is a member, another I-member. And the gypsum board is placed around the materials. So, the gypsum material is very light in a way. So, they have applied throughout the periphery. So, it can be either you can place likewise or you can place it likewise. Now, the main purpose of placing is straight, you know, to avoid the cutting cost and all that. Because when you are applying via periphery, then there is kind of, you know, you have to cut.

Then you have to join, rejoin and all that. To avoid that extra cost, it is applied. In a straight case only. Now these are some of the examples of you know applying gypsum boards or any kind of other materials. So you can see here it is placed at the bottom of the beam then you can see over here like it is continuous then over here see now over here they have placed according to the periphery like with respect to the periphery. And over here also they have placed with the periphery itself. So it's also depends actually. So for this analysis and design a separate team is hired and they shall work on like you know how to work on this.

Now why fireproofing is used. This is very important like we are so much discussed about the fireproofing and all that. So what is important of having fireproofing technique to be used. The design of the pipe rack is required to take into account the following consideration when fire protection system or coatings are used. So the following points to be considered when fire protection systems and coatings are used. Additional dead weight which must be included in the dead load of the structures and included in the seismic mass.

So as I discussed earlier when we are applying some kind of fireproofing material then the dead load of that particular material we need to apply in a STAD or any particular software in form of dead load. And that we also have to include in a seismic mass. Why dead load? Because obviously it is going to be a permanent weight only. When you are applying mass concreting or epoxy concreting or any kind of concreting it will be a permanent structure only. Or it will be a permanent mass only. We can't remove that mass in between.

We have to consider that additional dead load into the dead load which we will define in STAD or in other software. Also we have to consider that in seismic mass because as the dead load increase there are possibility to increase the seismic mass as well. Additional wind load due to increased size of member profile with fireproofing. So as we all know the wind load which we are applying is on surface area. And after putting up the mass concreting or epoxy concreting we are increasing the surface area of that particular frame.

So it is very important to take consideration of that increased profile when we are applying wind load. So we have to consider that as well. Connection types and geometry which may require offset to accommodate members with shop applied for protection. Now when we are giving connections when it comes to you know joining column to beam or you know bracing or any kind of secondary members to the primary members. Over there also we have to apply fire protection by giving shop welding or that kind of provision.

Structural steel coating selection to be compatible with the fire protection system. So sometimes we are giving structural steel coating for the maintenance purpose or for to make the steel durable for the longer and to increase the life of the structure. So that should be compatible with the fire protection system. So that material should not be hazardous or should not contain alcohol because if those materials are willing to catch the fire then it will be very difficult to control that fire system. So that is the very important point.

Fire protection material should not be considered as a coating that will prevent corrosion. Now when we are giving coating to prevent corrosion don't consider or do not consider those as a fire protection material. So yeah the both are individual parts like coating for preventing corrosion and coating for fire protection is totally different. Fire protection material may accelerate corrosion if improperly detailed or applied. Now when you are applying some kind of fire protection material. So you have to apply considering all the norms or all the specification and all the safety parameters.

There is a possibility if untrained team is willing to apply the fire protection material. Then there might be chances that it may get corroded or you know it may accelerate the corrosion. So yeah the proper team is required for that.

Want the rest of Design and Analysis of Piperack Structures using STAAD.Pro?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Design and Analysis of Piperack Structures using STAAD.Pro course

The remaining 46 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Design and Analysis of Piperack Structures using STAAD.Pro course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.