Dead Load on Structure

1) Pier Dead Load = 0.785 x 2 x 2 x 12 x 16 x 2500 /1000 = 1507.2 MT

2) Longitudinal Girder Dead Load = 12 x 8 x 1.7 x 0.5 x 2500/1000 = 204 MT

3) Cross Girder Dead Load = 4 x 5.9 x 1.5 x 0.3 x 2500/1000 = 26.55 MT

4) Deck Slab Dead Load = 7.9 x 0.2 x 24 x 2500 /1000 = 94.8 MT

5) ACB Dead load = 24x0.35x0.35x2500/1000 = 7.35 MT

6) Wearing coat Dead Load = 24 x 6.3 x 0.05 x 2300/1000 = 17.388 MT

Total Dead Load = Sum 1 to 6 = 1857.288 MT