Week 11 Challenge
Aim:- Design the pile foundation in the abutment bridge. considering the 28-meter span. Vertical capacity-250 tonne horizontal capacity - 40 tonnes.
With abutment having backfill
With abutment having RE wall.
Also List different components of pile foundation and calculate steel quantity in pile. Design of pile cap.
Solution:-
Given Data and Assumption.
| Span and Cross section | Unit | ||||||
| 1 | C/c of exp joint | = | 28.00 | m | |||
| 2 | C/c of bearing | = | 27.20 | m | |||
| 3 | Dist. Of bearing to exp joint | = | 0.40 | m | |||
| 4 | Total Deck width | = | 12.00 | m | |||
| 5 | Carriage width | = | 8.50 | m | |||
| 6 | Footpath width (One Side) | = | 1.50 | m | |||
| 7 | Width of Crashbarrier ( Right Side) | = | 0.50 | m | |||
| 8 | Width of Crashbarrier ( Left Side) | = | 0.50 | m | |||
| Superstructure Details | |||||||
| 1 | No fo girder | = | 4 | ||||
| 2 | Spacing of girder | = | 3 | m | |||
| 3 | Cantilever on both sides | = | 1.5 | m | |||
| 4 | Depth od superstructure | = | 4.2 | m | |||
| 5 | Wearing coat thickness | = | 0.065 | m | |||
| 6 | Dist. of FRL from bearing of least height | = | 10.9 | m | |||
| 7 | Bearing thickness | = | 0.065 | m | |||
| 8 | Pedestal thickness | = | 0.25 | m | |||
| 9 | Bearing + pedestal thckness | = | 0.315 | m | |||
| REFER ATTACHED SHEET FOR DETAILS | |||||||
Que ) Component of pile foundation and Calculate Steel quantity in Kg /cums and detailing in pile foundation.
1. Componenet in Pile foundation
- Pile Shaft (PIles)
- Pile Cap
2. Calculating steel quantity.
Assumption Data,
- Diameter of bar = 25. m
- Lenght of pile = 20 M
- No of Bar = 24 nos
The formula is :
Weight of Steel Bar = [D2 L / 162.28]
=`(25xx25xx20)/162.8`
= 76.79 Kg for single bar.
For 24 nos of bar = 24 x 76.79
= 1842.75 kg. Total
3. Detailing in pile foundation.
REFER ATTACHED SHEET FOR DETAILS