Challenge

Project 2_Design & Analysis of a Hostel building at Guwahati, Assam

AIM: To Create and Analyse the given building in ETABS and the structural model has to be prepared in accordance with IS 1893 and IS 13920. To design the pile cap and pile reinforcement details, Tie the beam connecting the pile caps, and sketch the column reinforcements, to produce the framing plan and beam detailing for the ground floor.

GIVEN DATA:

  • Location – Guwahati, Assam
  • Function – Hostel block in an academic institute
  • Walls are made of AAC blocks Pile capacity - 280 kN
  • M25 concrete Fe 500 Steel
  • Soil type is 3

INTRODUCTION:

  1. In ETABS, We can create a structural model of the building with the given Data
  2. In this, the first step is to note down the values of grid spacing from the given structural plans.
  3. After that, we have to create the structural model and run the analysis.
  4. Analyse the result and note down the result values from ETABS.
  5. Next is to export the model to SAFE 2016 software in order to design the foundations.

PROCEDURE:

  1. in the first step open the ETABS software go to the file and click on the new model.
  2. Model initialisation window will appear.
  3. Click on the use built-in setting and select the Indian codes and click ok.
  4. Click on the custom grid data and click ok.
  5. Now the values as per the given plans are inserted and our model will be ready.
  6. In the next step, the material has to be defined. Go to define and click on material properties and add the concrete and rebar material specifications.
  7. In the next step, section properties have to be defined. Go to define and click on section properties and add the beam and column specification.
  8. 450 mm x 600 mm beam size is provided for all the beams.
  9. 450 mm x 600 mm beams are provided for the beams at the periphery so as to increase the torsional resistance of the building
  10. The moment of inertia for beams and columns should be reduced by 0.35% and 0.4% respectively.
  11. In the next step define the slab properties by going in to define slab sections. Add the slab property as While defining the slab for Staircase it should be One way.
  12. Define the staircase slab and provide its thickness as 175 mm( varies from 175-225mm)
  13. Draw all the beams using the beam command.
  14. Draw all the columns using the column command
  15. In the next step, slabs are drawn using the slabs command
  16. Now we have to decide the location of the shear walls and how much should be the length of the shear wall.
  17. As per Indian standards, the length of the wall should be 5-2% in each direction.
  18. The thickness of the shear wall is assumed to be 250 mm.
  19. Now go to define and define the loads.
  20. Next, select the beams and floors and add the loads.
  21. AAC load of 3.5 kN/m since the aac blocks are used.
  22. The live load values are got from Is 1875 part 2 for residential buildings.
  23. As per table 1 of IS 875 part 2
  24. For hostel buildings

Living Rooms, Bedrooms and dormitories

2 kN/m^2

Kitchen and Laundries

3 kN/m^2

Billiards and public lounges

3 kN/m^2

Store rooms

5 kN/m^2

Dining rooms, cafeterias and restaurant

4 kN/m^2

Office rooms

2.5 kN/m^2

Bath and toilets

2 kN/m^2

Corridors, passages, staircase

3 kN/m^2

Balconies

4 kN/m^2

  1. As per clause number 875 part 2 reduction factor should be applied to the imposed loads.
  2. The live load at the roof floor needs to be reduced hence 2 kN/m is applied.
  3. Floor finish on all the floors 2 kN/m is applied.
  4. Seismic loads should be defined so as per IS 1893 Table no. 8 importance factor should be 1.2
  5. Since the building.
  6. The time period is calculated as per clause number 7.6.2 of IS 1893

T=0.09h/sqrtd

Tx=(0.09*16.85)/(67.7)^0.5=0.184 Seconds. Or Ty=0.09*16.85/(13.3)^0.5=0.415 sec

  1. Now define the load combinations
  2. In the next step we have to define the mass source, for that go to define and click on the mass source and add on the new, and click on specified load data, in the mass options click on include lateral mass and lump lateral mass at story levels, in the load pattern add multiplier 0.25 for LL and 1 for all the dead and super dead loads.
  3. And select all the floors and apply diaphragm D1
  4. In the next step we have to define the modal cases for that go to define and click on modal cases click add new model cases select eigen and put the number of modes shape required.
  5. now go to define the function and click on response spectrum and add a new function in accordance with IS 1893-2016 check all the values and click ok.
  6. Name the function as IS function, Response spectrum IS function IS 1893-2016 tab will appear to check all the values Seismic zone factor soil type, importance factor click on linear x linear y click ok.
  7. now go to define Load cases and click on Add the new case and Add RSX and Rsy
  8. select the response spectrum to click on Add select the function as IS function and U1 for Rx, and U 2 for Rsy and IS function
  9. Go to define click on load combinations and click on default design combo, click on create frame design and click on convert to design combo click ok.
  10. Now check the model if there are any warnings correct them and run the model.

RESULT:

  1. Go to display then click show tables and then structural data click ok.
  2. Click on show tables, select the Analysis results structure output click ok.
  3. Select the base reaction and check the eqx eqy values, Rx and Ry values see which values are larger if the rX RY values are lesser than the Eqx Eqy unlock the model and then go to define load case and delete the Rx RY cases and again select the load combinations and define that again.
  4. Go to modal mass participation ratio and check the values for U1 U2 U3 values some of these UX Uy UZ for the first 3 modes it should be greater than 65%.
  5. Go to concrete frame design and select the start design or check. and note down the vaLues of reinforcement details.
    1. select modal participating ratios we have got that at mode 7 we have got above 90% so it's okay.
    2. now select the base reactions to check that Eqx Eqy values should be the same and Rsx and Rsy values also should be at least equal to Eqx and Eqy respectively. if not then just take the Rsx values and divide them by Eq values whatever the values will get that value needs to be multiplied in the load cases Rsx tab.
    3. check for the share of shear walls go to base level and click on reaction Ex and ey values will be available take these values and divide it by the Total base shear which should be greater than 90%. If now add the shear walls in the appropriate directions

.

Beam 14 Right end Centre Left End
Bottom Reinforcement 672 605 609
required
Dia of bars 20 20 20
Number of bars 2.140127389 1.926751592 1.939490446
Bottom Reinforcement 675 605 605
Provided at Top 2.149681529 1.926751592 1.926751592
1#24 +2#24 extra is provide 2#20 is provide 2#20 is provide
COLUMN DESIGN
COLUMNS ALONG THE GRID 1B Column dimension 450*600
1 Longitudinal Reinforcement calculation
a) Minimum Reinforcement 0.8% of the Gross cross-sectional Area 2160 mm^2
As per clause no.26.5.3.1 of Is 456 2000
b) Maximum Reinforcement 6% of the Gross cross-sectional Area 15600 mm^2
As per clause no.26.5.3.1 of Is 456 2000
c) Maximum Ast along 3 A 4739 mm^2
As per clause no.26.5.3.1 of Is 456 2000
Dia of the longitudinal Reinforcement should be 12 mm or more
There for using 16 mm dia bars
Dia of bar 24
Area of 1 bar 452.448
number of bars 10.47413183
There fore using 8 28 mm dia bars Ast 4524.48 mm^2
remaining St Ast 214.52 mm^2
2 number #12 extra longitudinal Reinforcements need to be provided Ast 628 mm^2
There fore total longitudinal reinforcement provided
10 no. of 24 mm dia bars 4525
2no. Of 12 mm dia bars 628
Ast provided 5152.48 mm^2
The spacing between the longitudinal bars should not exceed 300mm.
2 Shear Reinforcement calculation
a) Minimum dia for shear Reinforcement for 32 mm dia 8 mm
As per clause no 7.4.2 of IS 13290- 2016
b) Maximum Shear reinforcement from the Etabs output 665 mm^2
c) There for using 8 mm dia bars mm^2
Dia of bar 8
Area of 1 bar 50.272
Special confining reinforcement clause no 8 of IS 13290 2016
The special confining reinforcement shall be provided at lo.
lo should not be less than
the larger lateral dimension of the column 600
1/6 of the clear span of the member 554.1666667
450 mm 450
There fore lo = 600 mm
The spacing of shear reinforcement along lo should not be more than
a 1/4 of the minimum dimension of the beam/column
minimum dimension of the column 150 mm
1/4th of the minimum dimension of the column 112.5 mm
b 6 times the dia of the smallest longitudinal reinforcement bar
Dia of smallest longitudinal reinforcement bar 12 mm
6 times the dia of the smallest longitudinal reinforcement bar 72 mm
c 100 mm 100 mm
Therefore special confining reinforcement #8mm @100 mm c/c is provided in the lo zone.
Transverses Reinforcement calculation for the zone up to h/4.
hc in m Beam depth h
Height of the column of Plinth level column 1 0.6 0.4
Height of the column of column 3.45 0.6 2.85
Height of the column of FF column 3.45 0.6 2.85
Height of the column of SF column 3.45 0.6 2.85
Height of the column of TF column 3.45 0.6 2.85
h h/4 approximate
Plinth level 0.4 0.1 200 mm
GF 2.85 0.7125 800 mm
FF 2.85 0.7125 800 mm
SF 2.85 0.7125 800 mm
TF 2.85 0.7125 800 mm
Transverse reinforcement in the splice Zone as per clause number 7.4.of IS 13290 2016
As per clause no. 7.4.1 of IS 13290 2016 the ends should have 135 hooks with an
extension of 6d of bars.
d 32 mm
6d 192 mm
As per the clause nuo. 7.4.2 of IS 13290 2016
a 8 mm dia bars are used in stirrups if the dia of longitudinal bars is less than or equal to 32 mm
b The maximum c/c spacing of stirrups is 300 mm
c a cross tie should be provided if the dimension of the column exceeds 300 mm.
There fore upto h/4 #8mm @300 mm c/cis provided in the lo zone.
As per clause no. 7.3.2.1 of IS 13290 2016
100 mm space should be provided within this splicing zone
There fore in the splice zone #8mm @100 mm c/cis provided in the lo zone.
For the columns terminating in the footing
as per clause nummber 8.2 of IS 13290 2016.
special confinement reinforcement should be provided up to 300 mm or larger length inside the footing.
COLUMNS ALONG THE GRID 3B Column dimension 450*650
1 Longitudinal Reinforcement calculation
a) Minimum Reinforcement 0.8% of the Gross cross-sectional Area 2340 mm^2
As per clause no.26.5.3.1 of Is 456 2000
b) Maximum Reinforcement 6% of the Gross cross-sectional Area 17550 mm^2
As per clause no.26.5.3.1 of Is 456 2000
c) Maximum Ast along 3 A 5022 mm^2
As per clause no.26.5.3.1 of Is 456 2000
Dia of the longitudinal Reinforcement should be 12 mm or more
There for using 16 mm dia bars
Dia of bar 28
Area of 1 bar 615.832
number of bars 8.154821445
There fore using 8 32 mm dia bars Ast 4926.656
Remaning Ast Ast 95.344
There for using 16 mm dia bars
Dia of bar 16
Area of 1 bar 201.088
number of bars 0.474140675
There fore using 2 20 mm dia bars Ast 402.176
There fore total longitudinal reinforcement provided
8 no. of 28 mm dia bars
2no. Of 16 mm dia bars
Ast provided 5328.832 mm^2
The spacing between the longitudinal bars should not exceed 300mm.
2 Shear Reinforcement calculation
a) Minimum dia for shear Reinforcement for 32 mm dia 8 mm
As per clause no 7.4.2 of IS 13290- 2016
b) Maximum Shear reinforcement from the Etabs output 720.48 mm^2
c) There for using 8 mm dia bars mm^2
Dia of bar 8
Area of 1 bar 50.272
Special confining reinforcement clause no 8 of IS 13290 2016
The special confining reinforcement shall be provided at lo.
lo should not be less than
the larger lateral dimension of the column 650mm
1/6 of the clear span of the member 554.1666667
450 mm 450
There fore lo = 650 mm
The spacing of shear reinforcement along lo should not be more than
a 1/4 of the minimum dimension of the beam/column
minimum dimension of the column 450 mm
1/4th of the minimum dimension of the column 112.5 mm
b 6 times the dia of the smallest longitudinal reinforcement bar
Dia of smallest longitudinal reinforcement bar 20 mm
6 times the dia of the smallest longitudinal reinforcement bar 120 mm
c 100 mm 100 mm
Therefore special confining reinforcement #8mm @100 mm c/c is provided in the lo zone.
Transverses Reinforcement calculation for the zone up to h/4.
hc in m Beam depth h
Height of the column of Plinth level column 1.5 0.5 1
Height of the column of column 4 0.5 3.5
Height of the column of FF column 3.45 0.5 2.95
Height of the column of SF column 3.45 0.5 2.95
Height of the column of TF column 3.45 0.5 2.95
3.45 0.5 2.95
h h/4 approximate
Plinth level 1 0.25 300 mm
GF 3.5 0.875 900 mm
FF 2.95 0.7375 900 mm
SF 2.95 0.7375 900 mm
TF 2.95 0.7375 900 mm
Transverse reinforcement in the splice Zone as per clause number 7.4.of IS 13290 2016
As per the clause nuo. 7.4.1 of IS 13290 2016 the ends should have 135 hooks with an
extension of 6d of bars.
d 32 mm
6d 192 mm
As per the clause nuo. 7.4.2 of IS 13290 2016
a 8 mm dia bars are used in stirrups if the dia of longitudinal bars is less than or equal to 32 mm
b The maximum c/c spacing of stirrups is 300 mm
c a cross tie should be provided if the dimension of the column exceeds 300 mm.
There fore upto h/4 #8mm @300 mm c/cis provided in the lo zone.
As per clause no. 7.3.2.1 of IS 13290 2016
100 mm spacing should be provided within this splicing zone
There fore in the splice zone #8mm @100 mm c/cis provided in the lo zone.
For the columns terminating in the footing
as per clause nummber 8.2 of IS 13290 2016.
special confinement reinforcement should be provided up to 300 mm or larger length inside the footing.

Importing the software Safe 2016

  1. Go to file click on export and select the safe v12.fk.
  2. A tab will appear then click on the story as a base and select the loads and loads from above click on the combination click ok,
  3. Goto SAFE 2016 and fo to file click import and select the file and save the file as FDB.
  4. Go to display click on the show loads select dead above and love above the values will be appeared.

GIVEN DATA:

Column of size:- 450mm *600 mm & 600mm*450m m

the pile has a load-carrying capacity of 280kN

Pile length-16 m and dia of pile -500 mm

SBC-150kN/m^2

SOLUTION:

  1. Number of piles=Total Axial load/pile capacity=(1.5DL+1.5LL)/280= numbers
  2. Piles in the springs are defined as spring so for that the spring constant

K=EA/L

E=5000(fck)^0.5=5000(25)^0.5=25000 N/mm^2

Area of pile =22/7*d^2=3.142*(500)^2/4=196375m^2

L-10000m

K=25000*0.7855/16=306835.9N/mm==419.

  1. Spacing of the piles as per clause number 6.6.2 of IS 2911 the spacing between the piles =2.5dia of the piles =2.5*500=1250mm
  2. Now in the next step, we have to define the material properties for go to define and define the material properties of Concrete and Reinforcement properties Fe500 & Fe 415.
  3. Select the values.
  4. Go to define section properties and define pile caps, pile Dia, and column
  5. Add new, defined pile cap pile 500 as Mat, and Column as Stiff.
  6. Click on the quick draw around the plots a window will open there insert the columns sizes and these columns to their specified positions. Columns should be stated as stiff material.
  7. In the next step pile caps needs to be drawn for that go to the Quickdraw slab command select pile caps and add it. Piles and pile caps should be stated as stiff material.
  8. Select the pile caps and changed the rebar material to Fe 500.
  9. Next, go to draw and draw points and a window will open up there draw the points where piles are to be drawn.
  10. Now again select the quick draw around the pints there select the property circular slab to add piles dia in this case 0.5m and add to the points. Select these piles and again check for the rebar materials.
  11. Now we have to define all the piles as springs for that goes to define
  12. select soil spring properties add new property there click on compression only and add the calculation value of K=EA?L.
  13. Select all the piles and go to assign and select support data and select spring properties and assign it.
  14. Go to define and select the defined beam and define the tie beams whose thickness should be as of pile caps.
  15. Check whether the rebar material is Fe 500 under design preferences
  16. Go to define and define the load combinations sls and uls
  17. Go to design and design preferences
  18. Save the model and run the Analysis
  19. Deformed shapes showed that deformations are negligible
  20. Assign add the design strips
  21. Run the analysis
  22. Deformed shape all the values are less than 25 mm hence ok.
  23. Now go to display and click on the punching shear the values we have to go are less than 1 hence ok.
  24. Now go to display and select slab design.
  25. All the reinforcement details will be available
  26. For X DIRECTION MIDDLE STRIP

maximum Reinforcement was

For Top:- 29834 mm^2/m=29834/3.3=9041 mm^2=28 nos. 20 mm dia are provided

For Bottom-13326mm^2/m=4038 mm^2=13 nos., 20 mm dia are provided

  1. For layer Y direction

maximum Reinforcement was

For Top:- 19926= 3831mm^2/m=12 nos of 20 mm dia are provided

For Bottom-22784mm^2/m=4398 mm^2=14 nos 20 mm dia are provided

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.