Challenge

Project 2

1) we downloaded door & the required data from TE.com & Hellarman tyton website.

Assumption-

1)We used 2 pole connectors 2 nos for name plate ligting

2)Used 4 pole conectors for tail LH & RH both lamps

3)1 nos 8 pole connector for inteconnection from roof harness

also after downloading, we defined as electrically & stored in a catlouge,snapshots as follows-

2) After defining electrically we arranged the connectors,clamps & clips at a proper location in assembly workbench by using smart move & manipulation command as follows-

3) After placing components, we start routing by considering actual practices & considering interferences as

4) We checked for bundle continuty & that found ok-

5)Snapshots for geometrical bundle-

6)After we go for harness flattening in flattening workbench by confirming parameters & maintained the orientations of branches as-

7) We create drawing view for flattened tail gate harness as-

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.