Challenge

Project 1_Analyze and design a steel building to 10T CRANE as per IS standard code using TEKLA STRUCTURAL DESIGNER.

Aim :-

To analyse and design a steel building to 10T CRANE as per IS standard code in TEKLA STRUCTURAL DESIGNER.

Procedure:

  • Open the TEKLA software and select structure window.
  • Now enter the levels as base, ground floor, first floor and roof as per the question
  • Now select the grid lines and draw them according to the ground floor plan
  • Now from the Manage property sets, define a new concrete column as 400*800 with grade of M45 and place the columns on the grid intersections
  • Now define a steel column of section ISMB 500, and place it at the grid intersections of first floor.
  • Now define the primary beams as ISMB 500 and place it on the ground floor
  • Similarily draw the same beams on the first floor and roof.
  • Now define the frames for the model and select any one frame and draw a central vertical line. Slope of the roof is 18 degree, so the height at which the rafter has to be placed should be determined. tan 18 = ht./19 => ht. = 6m
  • Now we have to go to the slab sections and define a slab of thickness of 300mm and grade M50. Since the first layer is a square shape, it has to be a two way slab and the other two rows are one way.
  • The same process is repeated for all the three floors
  • Now we have to assign the roof panels and wall panels

Calculation of Dead load:

  • Finish of 50 mm = 0.5*25 = 1.2KN/m
  • Brickwall load for ground floor = 0.15*20*5 =15.5KN/m
  • Brickwall load for first floor, second floor and roof = 0.15*20*7 = 21.2KN/m
  • Now apply all these loads to the entire model

Calculation of Live Load:

  • Meeting room = 2KN/m
  • Toilet = 2KN/m
  • Office Room = 2.5 KN/m
  • Maintenance room = 2.5KN/m
  • Pantry =5KN/m
  • Staircase = 5KN/m
  • Now we have to apply all these loadsto each floor of the model

Calculation of Wind Loads:

  • Vz= Vb*k1*k2*k3*k4

Vb = 39 m/s

From Table 1, IS 875-3 , k1 = 1

From Table 2, IS 875-3, k2 = 1.03

k3 = 1 ; k4 =1

Vz = 39&1*1.03*1*1 = 40.17 m/s

  • Pz = 0.6*Vz^2

Pz = 0.6*40.17^2 = 0.968 KN/m^2

  • Along face A

Interior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =0.7
  • Cpi =0.5
  • Cp= 0.2
  • Pz = 0.968KN/m^2
  • Load = 0.1936 KN/m

Exterior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =0.7
  • Cpi =-0.5
  • Cp= 1.2
  • Pz = 0.968KN/m^2
  • Load = 1.16 KN/m
  • Along face B

Interior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =-0.25
  • Cpi =0.5
  • Cp= -0.75
  • Pz = 0.968KN/m^2
  • Load = -0.726 KN/m

Exterior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =-0.25
  • Cpi =-0.5
  • Cp= 0.25
  • Pz = 0.968KN/m^2
  • Load = 0.242 KN/m
  • Along face C

Interior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =-0.6
  • Cpi =0.7
  • Cp= -1.3
  • Pz = 0.968KN/m^2
  • Load = -1.25 KN/m

Exterior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =-0.6
  • Cpi =-0.7
  • Cp= 0.1
  • Pz = 0.968KN/m^2
  • Load = 0.0968 KN/m
  • Along face D

Interior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =-0.6
  • Cpi =0.1
  • Cp= -0.7
  • Pz = 0.968KN/m^2
  • Load = -0.6776 KN/m

Exterior

  • H= 18m
  • L= 90m
  • w= 38m
  • Cpe =-0.6
  • Cpi =-0.1
  • Cp= -0.5
  • Pz = 0.968KN/m^2
  • Load = -0.484 KN/m
  • Loads to roof considering one part as EF (Slope = 18 degree)

Interior

  • H= 12m
  • L= 90m
  • w= 38m
  • Cpe =-0.4
  • Cpi =0.7
  • Cp= -1.1
  • Pz = 0.968KN/m^2
  • Load = -1.06 KN/m

Exterior

  • H= 12m
  • L= 90m
  • w= 38m
  • Cpe =-0.4
  • Cpi =-0.7
  • Cp= 0.3
  • Pz = 0.968KN/m^2
  • Load =0.2904 KN/m
  • Now we have to apply the loads along each face of the model

Calculation of Crane load:

  • Weight of crab = 35KN
  • Weight of crane = 160KN
  • Crane capacity = 100KN
  • Wheel base =3m
  • Distance between gantry rails = 20m
  • Distance between gantry column = 6m
  • Max wheel load = Max point load + Weight of crab =135KN
  • Self weight of crane = 160KN/20 = 8KN
  • Taking moment about A,

Rb*20-135*1-8*20*10 =0

Therefore Rb= 86.75KN

  • Taking moment about B,

Ra*20-135*19-8*20*10=0

Therefore Ra= 208.25 KN

  • Max load on each wheel =Ra/2 = 104.13 KN
  • Assume self weight of gantry girder =1.5KN/m
  • Total dead load =1.8KN/m
  • Taking moment about C,

Rd*6-104.13(0.75+3)-104.13*0.75=0

Therfore, Rd = 78.9 KN

  • Taking moment about D,

Rc*6-104.13(2.25+3)-104.13*2.25=0

Therefore, Rc=130.15KN

Now, Rc+Rd = 208.25 KN

  • Bending moment under wheel load due to live load = 78.9*2 = 156.18KNm
  • Bending moment due to impact = 0.10*156.18 = 15.618 KN
  • Total bending moment due to live load and impact load = 171.79KNm
  • Bending moment due to dead load =WL/2 = 8.1 KN/m
  • Max bending moment = 171.79 + 8.1 = 179.89 KNm
  • Max shear force at D , Rc*16-104.13*6-104.13*3=0 . Therefore Rc= 156.18 KN
  • First we will have to draft a rough postion of beams and columns in the plan using paint tool

Ground floor :

First floor :

  • The rough beam and column position are created for ground floor and first floor .
  • after this new tekla file is opened and save it as project 1 .
  • New > Model > construction levels .

  • Construction levels
  • Base level > ground floor > 0.5 m
  • Ground level > first floor > 5m
  • first floor > roof beam level > 7m

  • After this we have to go to the base level
  • Add the grids
  • First we add the vertical grids according to the dimensions
  • select grid lines , pick the first point > grid 1
  • Then select quick parallel >grid 2 > 6m .
  • 12m > grid 3 > 18m >grid 4 > 24m > grid 5 and soo on till grid 16

  • Now select perpendicular grid line and name the grid as A

  • After this parallel quick is selected and grid B is drawn with distance 8m
  • 14m > grid C , 5.070 m >grid D , 4.925 m > grid E

  • After this in the base level rc columns are created till ground floor Level
  • Manage property sets > Concrete column > 400 x 800 section > M45

  • Then steel column is added
  • Manage property sets > steel column > ground floor to roof beam level
  • ISMB> Universal columns > section > 365 X406 X393

  • After this primary and secondry steel beams are added
  • In ground floor , first floor and roof floor
  • Manage property sets > steel beam >uk > universal beams >1016X305x437

Ground floor :

First floor :

roof beam level:

  • Click on frame option and select grid 1

  • draw grid lines at each end of distance 1328 mm with the help of construction line
  • and draw the mid point the help of the construction line
  • as we known the slope is 18 degree
  • horizontal distance is 18 m , therefore vertical distance is 6 m
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.