Challenge

Preparing Schedule & Cost Estimation for a building using REVIT

  • PREPARING SCHEDULE AND COST ESTIMATION FOR A BUILDING USING REVIT
  • QUESTION : 1
  • Use the shortcut keys in Revit discussed in class to complete the following tasks and list them below
    a. Using 3D model create a section box
    b. To create similar doors and windows in a floor plan layout
    c. To reduce the thickness of lines visible in plan views
    d. To apply override settings to a floor in the model section view
    e. To increase the range of visibility in a plan view
    f. To select the previously selected items
    g. To add annotations to the model views
    h. To bring the model elements in line
    i. To rotate the model elements
    j. To move an object to another location
  • k. To copy a model element
    l. To mirror an element about an axis
    m. To create an array of model elements
  • ANSWER :
  • AIM :
  • GIVE THE LIST OF SHORTCUT USED FOR THE FOLLOWING TASK :
  • a. Using 3D model create a section box : BX
    b. To create similar doors and windows in a floor plan layout : CS
    c. To reduce the thickness of lines visible in plan views : TL
    d. To apply override settings to a floor in the model section view : VG
    e. To increase the range of visibility in a plan view : VR
    f. To select the previously selected items : ctrl+<
    g. To add annotations to the model views :DL
    h. To bring the model elements in line :AL
    i. To rotate the model elements : RO
    j. To move an object to another location : MV
    k. To copy a model element : CO
    l. To mirror an element about an axis : MM
    m. To create an array of model elements : AR
  • QUESTION : 2
  • Using Revit and the project used from week 6 to 8 prepare a schedule for the following
    a. Walls
    b. Doors
    c. Windows
    d. Material – Concrete/Wood
  • ANSWER :
  • PROCEDURE :
  • AIM :
  • PRAPARE THE SCHEDULE FOR FOLLOWING ELEMENTS :
  • STEP 1
  • start the revit 2023 software
  • then homepage of revit is open as shown below
  • STEP 2
  • then click on open option from that homepage
  • select the residental appertmet file
  • select it and open it
  • STEP 3
  • prepare the shedule of walls
  • for that go to the view tab
  • click on shedule
  • then click on schedule quantites
  • then one dialogbox is open
  • then select the walls option from there as shown below
  • then click ok
  • then give the wall parameter as wall type , count , family , area , volume etc as shown below
  • then click ok
  • then wall shedule is prepared as shown below
  • WALLS SCHEDULE :
  • do same process for doors also
  • and prepare the door schedule
  • DOOR SCHEDULE :
  • RESULTS :
  • WALL SHEDULE :
  • DOOR SCHEDULE :
  • WINDOW SCHEDULE :
  • QUESTION : 3
  • Using Revit Calculate area and volume of each room in the model with appropriate room tags applied to each room. Prepare a schedule report for area and volume of each room.
  • ANSWER :
  • PROCEDURE :
  • STEP 1
  • start the revit 2023 software
  • then homepage of revit is open as shown below
  • STEP 2
  • Click on OPEN option from that hometab
  • select the file and open at
  • STEP 3
  • prepare the schedule for room
  • so that go to the view tab
  • click on schedule option
  • click on shedule by quantites
  • then one dialogopex is open as shown below
  • then give the category name as room
  • and click ok
  • then select the parameter as count , name, area, volume parimeter etc
  • and click on
  • schedule of rooms is created as shown below
  • RESULTS :
  • QUESTION : 4
  • Using the same schedule using the unit cost rate for materials available in the internet, prepare total cost of materials used in the project
    a. Total Cost of Materials
    b. Individual Material Take off
  • ANSWER :
  • AIM :
  • PREPARE THE SCHEDULE REPORT OF TOTAL COST OF MATERIAL USED IN PROJECT :
  • PROCEDURE :
  • STEP 1
  • Start the revit software
  • then homepage of revit is open as shown below
  • STEP 2
  • Click on OPEN option from that homepage
  • select the file name as archictural appartment which is alrady created in week 7
  • select the file and open it
  • STEP 3
  • prepare the schedule of total cost of project
  • so that go to the view tab
  • click on schedule
  • then click on material takeoff
  • then one new dialogbox is open
  • select the category as wall
  • then selct the parameter as shown below
  • then click ok
  • STEP 4
  • select the dublicate column name as assembly point
  • and go to calculated option
  • and give the forumla there give the name of column as total cost as shown below
  • then click ok
  • in this way we calculate the total cost of wall material sown below
  • in this way prepare the some materials schedule
  • as shown in results
  • RESULTS :
  • WALL SCHEDULE :
  • WINDOW SCHEDULE :
  • DOOR SCHEDULE :
  • QUESTION : 5
  • Using the concept of Visual Programming discussed in class, list a flowchart for the following scenario
    a. How to decide framings for a structure using Dynamo ?
    b. If there is no water coming from the pipes
    c. If request for money from client has been declined for the project
  • ANSWER :
  • CASE 1 :
  • How to decide framings for a structure using Dynamo :
  • CASE 2 :
  • If there is no water coming from the pipes :
  • CASE 3 :
  • If request for money from client has been declined for the project :
  • QUESTION : 6
  • List the parameters associated with each model element
    a. Wall
    b. Floor
    c. Door
    d. Window
    e. Table
    f. Building
  • ANSWER :
  • LIST OF PARAMETER ASSOCIATED WITH EACH MODEL ELEMENT IS GIVEN BELOW :
  • 1. WALLS
  • wall material
  • wall volume
  • wall area
  • wall type
  • wall length
  • wall height
  • wall parimeter
  • wall cost
  • wall description
  • FLOOR :
  • floor material
  • floor area
  • floor volume
  • floor thickness
  • floor description
  • floor width
  • floor cost
  • floor type
  • DOOR :
  • door type
  • door material
  • door height
  • door width
  • door aram
  • door cost
  • WINDOW :
  • window type
  • window material
  • window height
  • window length
  • window cost
  • window description
  • TABLE :
  • table type
  • table height
  • table material
  • table width
  • table discription
  • table cost
  • BUILDING :
  • building type
  • building height
  • building material
  • building location
  • building area
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.