Why Use Primavera: Industry Use and Work Breakdown Structure Intro

A free lesson from Skill-Lync's Project Management Using Primavera course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 3”

What will you learn in this free Project Management Using Primavera lesson?

The instructor recaps week one, covers time and budget overruns in construction and what helps projects succeed, then introduces Oracle Primavera. The instructor lists its benefits and example projects, explains the CPWD reporting requirement, and begins work breakdown structure with a building example.

  • Success factors for on-time, on-budget projects
  • Primavera benefits: visibility, resources, reporting
  • Industries and projects that use Primavera
  • WBS split of a building project

What comes after lesson 3?

Later in Skill-Lync's Project Management Using Primavera course (paid): lesson 4, Week 1 Session 4; lesson 5, Week 2 Session 1; lesson 6, Week 2 Session 2. The full course has 45 lessons (20 h 0 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

So these are the points, you know, which if you implement in the project management, we can, you know, make sure that our project will complete within a time, within a budget, you know, and within a scope. So, you know, we can succeed a project by implementing these points. Now we are going to see how we can implement this, you know, all these points through the software that is Oracle Pramavera. So now we are going to the software part and we are going to see what is Pramavera, you know, what is the benefits of the Pramavera, how you can use the Pramavera.

So we are going to see now the software. Before even going to the software, I just want to recap, you know, what we have done till now. We have seen what is project, what is infrastructure project, what type of projects we have in terms of, you know, commercial, industrial project, infrastructure project, what is the project management, what is the program and what is the portfolio and what is program and what is the portfolio management. So these are the structure that we have seen in the program and the portfolio.

So what are the stakeholder? Who are the stakeholder? How stakeholders can influence your project? Why stakeholders are so important? So we have studied this stakeholder. Then we have seen a project life cycle characteristic. We have seen this graph, how this costing and staffing level impact in our project life cycle in a phase wise, how the cost of change is moving from, you know, starting of the project to end of the project and how stakeholder influence risk uncertainty graph, you know, move from, you know, starting of the project to the end of the project.

We have seen also project management office. What is the responsibility of the PMO? How they are working? We have seen process group, how many processes group we have in the project management. So we have initiation, we have planning, we have executing, we are monitoring and controlling. Then we have the closing process. And then we have seen a project management knowledge area. So we have 10 knowledge area, the integration management, the scope management, time management, cost management, quality management, human resource management, communication management, risk management, procurement management, and the stakeholder management.

Then we haven't seen like why nowadays, you know, the project management requirement is increasing day by day. What are the project constraints? Why these project constraints are so important? So we have risk, budget, schedule, quality, resource, scope as a project constraint. So we have seen these three C's also, you know, why the demand is increasing because of the complexity of the project, because of the competition of the product and because of the customization, which is required by the customer. And we have also seen some of the, you know, facts about the, you know, investment in India, like on the infrastructure projects.

So we have seen all these, you know, investments. We have seen what are the current and upcoming projects, mega projects in India. So we have seen, you know, this industrial corridor, metro terrain project. So now we discuss about, you know, why do construction projects have higher failure ratios? So these are the some of the points which we have seen, I've mentioned, I've explained, which is like poor management, lack of planning, lack of fairness, and the actual problem. By not selecting the right people for the right job, inappropriate machines and compromise on safety expect, improper supervision and timely audit.

Then we have seen because of these failure, how our project is, you know, you know, overruns. What is the status? What is the average value of, you know, time overruns? And what is the average value of the budget overrun? And then we have discussed like how we can, you know, make sure that our projects are going to succeed by implementing these points. So how we can, you know, implement these points? So by looking at the tool, which is like, you know, the software. So we need to implement all these, you know, points, all these project management techniques now in the software.

So software, when I say the software, so now we are going to learn about the Pramavera. So Pramavera is the software which is used in the industry for project planning and management. It is widely used in the most of the industries, almost, you know, 70 to 80% of the market or companies, they use Oracle Pramavera to manage their projects. So we are going to see what is Pramavera, what are the key benefits of the Pramavera, what are the key features of the Pramavera, what makes Pramavera great.

Then we will, you know, start our, you know, learning Pramavera, how you can, you know, use Pramavera, how you can create a project, how you can create a schedule, how you can do resource management, cost management, you know, knowledge area, which we have seen the scope management, how we can do scope management through the Pramavera, how we can do schedule management through the Pramavera, how we can do cost management through the Pramavera, how we can do resource management communication management procurement management you know risk management through the primavera software so primavera is an oracle product so full name of the primavera is uh oracle Primavera P6 enterprise project portfolio management primary is basically a robust and easy to use integrated solution used globally for prioritizing the project we need to prioritize our project our activities we can plan our project we can manage our project and we can execute our project program and the portfolio as a name suggests you know we have discussed about program and the portfolio so primavera is basically a portfolio management solution that means not only project but we can manage our portfolio as well through the primavera history of primavera just to give an idea so uh it was developed by a company called primavera system in 1983 but in 2008 oracle acquired primavera and the latest version of primavera is 20.12 so what are the key features of the primavera through primavera we can create a project like you know we have let's say we have a road construction projects so how you are going to prepare a plan for a project now in terms of what is the plan like how you are going to execute your project what is the time required for this project how many funds or cost is required for this project how many resources are required what are the risk factors so complete project uh you know we can create through this primavera we can do scheduling so scheduling is a technique by which we will do this time management we'll find out what is the exact amount which is required to finish our project project so as experience you know um let's say you are experienced you are you are you have 12 20 or 30 years of experience and you want to set up a power plant so power plant you can say okay it may take you know three to four years but what is the exact amount of time in number of days uh required to complete the project you know that can be calculated by the uh primavera software now the resource management you know we we know that you know to execute a project we we required a resource resource resource can be like your you know man machine material and money so how you can do the resource management and how you can optimize the resources then when we start the execution part how you can track your progress like you know uh your your project is uh executing at the site your excavation is going on your you know uh the laying of pipe is going on so installation of you know machinery is going on how you can track whether my project is on track uh you know whether my project is executing as per my plan or not so we can track our project progress then integrated risk management that we have already discussed like you know uh we can do risk management uh through the process so we are going to see what are the type of risk we have how we can create a risk register how we can you know make sure that you know in our project we can minimize all these risks a streamline enterprise reporting um you know that you know from this you know from the ukg like you know at the end of the uh our year we will have a you know our scorecard similarly in a project we on a regular basis we need to submit lots of reports to our client to our stakeholders so how we can streamline all these reporting how we can prepare a dashboard so dashboard is like you know a single screen where you can see all the information about your project and it's like a live dashboard you know so how you can create the dashboards that that that is the features of the primavera now through these features what are the benefits you will get as a you know as a you know corporate employer as a company if you're running your own you know construction company so what are the benefits you will get the first benefit is it will increase the visibility visibility across visibility that means we will have a clear picture what is happening in my project you know um when you're talking about a project project is nothing is not like you know one team is executing a project in a single project we will we need to involve so many team you know different different team different different functional manager different different division so it's starting from you know our engineering and design team you know our procurement team our you know uh structure team our MEP team our HVAC team lots of contractor we need to involve lots of you know vendor we need to involve uh right so how we can increase the visibility because everything in this software that's why you know everyone can see what is happening what is we have seen the tracking the progress you know so everyone can see what is happening in my project at any time so it will increase the visibility which ultimately reduce the you know uh dispute between Different vendors, different contractors, different parties, improved project delivery.

Obviously, if you have a complete visibility across your project, if you know where I'm standing, so let's say you need to set up a cement plan. So to set up a cement plan, it will take three years time. So you need to deliver the cement plan to your client within three years. So how you can improve your project delivery? So if you have a proper plan, if you track your project, if let's say there is something happen and your project start getting delayed, so you can, you know, you will get a notification, you will, you can see through the reporting that, you know, something is happening.

And because of that, your project is getting delayed. So you can take an action, you can take a decision on that point only. So it will help you to, you know, finish your project within time. So it ultimately improved your project delivery dates. Effective resource planning. So, you know, we have seen, you might have experienced, like, you know, you, like, you know, in a project, we will have hundreds of resources, like, you know, hundreds of labor, you know, hundreds of site engineers, operator, welder, you know, carpenter, you know, we need design engineers also.

So how we can prepare a plan? So, you know, through this resource management, you can track your resources, even, you know, hourly wise, like, you know, where is my resources? This is how I'm, you know, he's allocating on a project. It should not be like, you know, there are two design engineers. One is having, you know, it's like, you know, the work that, you know, four hours work in a day and one is having, like, you know, 12 hours of work in a day. So it's like, you know, one is giving is, you know, 200% and one is just allocated 50%.

So the software will give you the clear picture, a clear visibility of about your resource allocation. And through that, you can, you know, improve, you can optimize your resources and you, it will be like, you know, help you to for the effective resource planning. The easy stakeholder reporting, as we discussed, like, you know, reporting is one of the most important part of the, you know, project. So every stakeholder, like, it's your client, your contractor, they need reporting, you know, on a, like, say, monthly wise or weekly wise.

So you need to submit lots of reports to your client. So how you will, you know, are able to, you know, how you are going to submit. So by this software, we can, you know, schedule a report and, you know, you can easily, you know, submit stakeholder reports. So the software is completely based on the user base, you know, user base means, you know, we have a Facebook, you know, ID. So every person, so let's say for me, I have my own account for you, you have your own account.

Similarly, the software is user base. So if you're working as a planning engineer and there are five planning engineer. So the software is like, you know, you will have your own account, you know, on access to the software and other, you know, for planning engineer, they will have their own access. So the software is like multi-user access. So even we can put restriction. It's like the security wise, the software is very, very powerful. Like, you know, I'll show you how, you know, you can log in.

So it's like, you know, you need to enter your user ID and password and let's say you are a project manager and you have three, you know, junior project engineer and you don't want that, you know, they can, you know, update the cost. You just want to update them like, you know, the activity status only, the dates only. You don't want to, you know, allow them to, you know, change the cost. So that also you can do. Like we can put some restriction based on the roles and responsibility of the users.

So let's say, you know, you are working on a one project and your senior is working on a multiple project. So he can give you the kind of accessibility for having the, you know, visibility on only one project. But your senior may can, you know, can see multiple projects, but you can only see only one project. So that also is possible in the software. So we create a multi-user access and we configure the software, the users also based on their responsibility, based on their KRA. Based on their department, like, you know, we can create that.

So what makes Pramavera great? So I have, you know, here I have just put some of the, you know, biggest project that is completely managed by the Pramavera. So the first is like, you know, this Sweden-Denmark bridge. So the complete planning was done in through the Pramavera. It was in 2000. Then we have this, you know, Canary Raff, which is in London. So it was completely planned and executed through the Pramavera in 1991. Then we have, you know, China Dam, which is in 2006. Then we have Patron's Tower, which is in Malaysia.

So I'm sure, you know, most of people somewhere seen this, you know, tower. So Twin Towers also, they used to say in Malaysia. So 1998, you know, so complete, you know, planning, the execution, everything was, you know, done through this Pramavera only. World Trade Center, you know, Statue of Liberty renovation. In 1986, you know, 83, they have Pramavera, you know. So in 1986, you know, the U.S. used the Pramavera for, you know, managing this renovation of Statue of Liberty work. So Taipais, which is again, you know, one of the biggest building.

And then everyone knows about the Burj Khalifa Dubai, which was completely managed. The planning, the execution, everything was done through the Pramavera software only. I have just taken some of the, another example, which is like Petrobras, which is a refinery, rebuilding the Prama canals. You know, Hong Kong airport, Disneyland Paris, Disneyland Hong Kong. So the purpose of showing you, you know, different, different, you know, example is the Pramavera is not only like, you know, for one project or one type of project. You can manage any type of project.

So first is like, you know, this project is related to the bridge. This is like, you know, you have the smart city. This is a dam. This is a tower. This is a building. Then this is again building. This is a renovation work. This is again building. This is, you know, multi-level building, the world's largest building. This is the refinery setup. You know, this is the rebuilding the Prama canals. Then this is again, you know, kind of hospitality or, you know, kind of entertainment, you know, projects.

And this is Hong Kong airport, the airport projects. You know, even Pramavera is used in, you know, manufacturing industry also, like, you know, most of the manufacturing company, like, you know, discrete manufacturing company, they use Pramavera for, you know, managing their projects. You know, this commercial satellite launch vehicle that is also managed by the Pramavera, automated transfer vehicles. You know, all these, you know, projects, I have taken a live example and all these big projects are managed through the Pramavera. Now, let's talk about in India, you know, now, you know, most of the Indian projects are managed by the Pramavera.

The first example I have shown you is like, you know, super thermal power station, Delhi Metro. So now in Delhi Metro, we have four phases. The two phases are already in operation. Third phase is in underground. Third phase is in under construction and fourth phase is also started. So all, you know, complete Delhi Metro, you know, construction is managed through the Pramavera. Then we have a bridge, Vivekanand Bridge, Kolkata and China Tata Highway. So highway industries, you know, infrastructure industries, power industries, transport industries. So every industry use Pramavera to manage their project.

And, you know, I just want to, you know, highlight a few more things about like in India, what is the scope of the Pramavera? Like, you know, we all know about CPWD, which is like, you know, central department for, which is center public was department, which is like, you know, responsible for, you know, a building, which is responsible for making a buildings. Now, there is a clause in the CPWD that you can check on Google. For example, the contractor who are going to, you know, work with CPWD should have or must have Oracle Pramavera if the project cost is above 20 CR.

And as a civil engineer, you must know 20 CR is nothing like, you know, to have a 10 story building, 20 CR is nothing. So, you know, if your project cost is more than 20 CR, as a builder, as a contractor, as a construction company, you should have a Pramavera software. Even in CPWD without having a Pramavera software, if let's say your company don't have Pramavera software in your company, you cannot participate in the CPWD tender. Your billing will not process until you will submit a Oracle Pramavera schedule, you cannot start your project.

You need to submit, you know, a regular report, like monthly reports, the Pramavera reports to the CPWD, then only they will release your payment. It doesn't matter if you have done some work on site or not. They want, there's a clause that, you know, if the contractor will submit a Pramavera report, then only they will process the bill. So this is like how the scope of the Pramavera in India. Now, how this Pramavera fulfill the requirement in a different, different industry. So I've just put some kind of points, you know, just to give you the overview, you know, because as a civil engineer, you might work in architecture, you know, public sector, utility industry.

So how this Pramavera is going to help you to manage their project in a different, different industry. So let's say, let's talk about architecture, engineering and construction firm. So we know that, you know, in the construction industry, you know, we, there are so many. Vendors, contractors are involved, like, you know, subcontractors, there's so many, you know, MEP vendor, electrical vendor, you know, painter vendor, you know, lots of vendors are involved. So, you know, and because lots of vendors are involved, everyone, whenever there's some kind of issue, everyone start blaming on each other.

Like, you know, let's say there's some kind of delay. So, you know, one vendor will say like, no, this is not my fault. Some other vendor did some mistake and because of that, our project is going to impact. So, how to avoid all these claims and disputes? So, Pramavera software will improve the coordination and collaboration between the different, different vendors. Ultimately, it will avoid the project claims. In the public sector and the aerospace and defense, it will help you to manage large program with a multiple supplier and the contractor.

We all know public sector, you know, we just discussed about the CPWD. We know aerospace and defense, like, you know, they require lots of parts, you know, it's like kind of the, you know, the manufacturing or DRDO, you know, they require lots of parts. So, how parts means like they have multiple suppliers or subcontractors. So, how they can manage, you know, all these suppliers, subcontractors and how they can improve the accountability and meet regularity requirements through this software. Now, when it comes to utility, like power sectors, energy sector, oil and gas sector, especially in the refineries, we have a maintenance shutdown time period, like every, you know, refinery.

So, there are two types of, you know, work, one is refinery operation, one is to set up a refinery. So, to set up a refinery is kind of the infrastructure project, but even refineries start operation. So, we will have, you know, on a regular period, probably six, within a six month or every year, we will have a shutdown time period where we need to do the maintenance of all the machinery. So, Primera is going to help you to manage short duration, high intensity, outreach and the shutdown projects because these shutdown projects are very high intensity.

Like, you know, we have a 10 days time and we have to complete our, you know, all the maintenance within a 10 days. We cannot say like we need five days more. So, the Primera will help you to manage this, you know, short duration, high intensity projects. It will also help you to increase the productivity and the speed of the project delivery. Now, when it comes to the high tech and the manufacturing industry, it will help you to bring the right product to the market within a market window.

It will also help you to collaborate across the global supply chain. Like, you know, in the manufacturing industry, like they have to supply their material, you know, they're also getting raw material. So, it will help you to manage their supply chain also. Now, when it comes to the IT and services industry, it will help to prioritize project based on strategic objective. Like, in IT industry, they have multiple projects are running. Like, you know, it comes to like InfoSeries or TCS, all these IT companies are there.

They have hundreds of projects which is running, you know, simultaneously. So, how they can manage and prioritize the project. And they can also, Primera will also help them to optimize assignment for the resources. Like, you know, if they have a multiple projects, they have hundreds of projects at one time. So, they need to optimize the resources as well. So, Primera is going to help you because we have seen the resource management is the part of the Pramavera. So, Primera is going to help them to manage the resources.

Now, this is just to, you know, show you like how industries are using the Pramavera. So, you know, out of top 600 engineering and construction firm, 570 firms are using Primera. You can name it, whether L&T, DLF, you know, Shippurji, Tata Projects, you know, Adani. So, all of, all these companies are using Pramavera to manage, like, Godrej property. So, you name it, any, you know, construction firm in India, 90% of these firms are using Pramavera. Power companies, top, you know, top, you know, 70s out of 20 power companies are used Pramavera.

Like, power company, you name it, any power company in India, whether it's like NHPC, you know, NTPC, all these companies, like, you know, Adani Power is there, Limes Power is there, you know, Tata Power is there. So, all these companies are using Pramavera to manage their project. Nine of top 10 oil companies, you know, you name it again, you know, oil companies, whether it's Indian Oil, Oil India, Hindustan Petroleum, Bharat Petroleum, you know, ONGC. So, all these refineries company, like, you know, in India, we, I guess, you know, have 20 to 25 refineries, like, you know, and all these refineries are using Pramavera at some extent to manage their project.

Nine of top 10 aerospace defense contractors. So, you know, so, you know, all these aerospace and defense contractors, you know, manufacturing like DRDO, you know, Alden's factory. So, they use Pramavera to manage their project. Now, we are going to learn about the Pramavera, you know, how you can utilize, you have, as of now, like, you know, you have learned or you have heard lots of things about Pramavera, you know, what is the importance, what is Pramavera, how it is used in industry, how many industries are using, what the Pramavera is going to give you, what is the benefits of the Pramavera.

So, everything, you know, you have gone through, I have gone through with all these slides. Now, we are going to start how you can use Pramavera, it's like, you know, on a ground level, how you can do planning, how you can prepare a schedule, how you are going to do the resource management, cost management, the communication management, then procurement management. So, everything now we are going to learn. So, the first is, like, I have shown you, like, you can create a project. So, just to recap, a project contains a set of activity.

We know that, like, project is basically a set of activities performed in a coordinated arrangement to create a product, services, and a measurable business result. So, this is how project looks like in a Pramavera. I am going to show you the complete software, but just, I have taken a snapshot just to give you the idea about how project looks like in a Pramavera. So, client is one module of the Pramavera. So, you can see, like, Pramavera P6 Professional. So, here, you can see this is a project.

So, we have project tab. So, here, you can see ATR Construction Organization. So, this is a one construction company, and then they have all these projects. So, if you see this, you know, folder symbol is a symbol of your project. So, we have all these projects. So, in Pramavera, you can manage N number of projects. If you have 100, 200, 500 projects, you can manage all these projects very easily in the Pramavera. Now, once you create a project, we need to do the work breakdown structure.

So, what is the work breakdown structure? I am just giving you the idea about so that when you study in the detail, you will already know all these terminology, WBS, and all these things. So, work breakdown structure, or WBS, is the deliverables-oriented hierarchical decomposition of the project work. WBS decomposes the project work into smaller and more manageable piece of work. If you remember, like, we have seen portfolio. Then, portfolio is like a group company. Now, they have this group companies divided further into the programs, which is like a group of similar projects.

Like, you know, we discuss about the L&T. So, we have L&T. L&T group is there. After that, we have L&T construction, L&T power, L&T IT. So, these are, again, the further we have divided L&T group into multiple division or business units. Then, we have L&T constructions. Now, in the L&T construction, we further divided into number of projects, which we have seen here. Okay. So, these are the number of projects. So, after that, what we do, we further divide this project into the WBS. Okay. To manage, you know, in a proper way.

So, I will give you an example. So, let's say construction. So, you are going to construct a building. In this building, so, this is your project. Okay. After, in this project, you have divided this project into these WBS. Normally, what we divide WBS as a department-wise. So, just for this example, for a construction. So, this is a master WBS. So, you can say project. Now, we have divided this construction, you know, project into first WBS, which is site preparation. So, first, what we need to do, we need to prepare a site.

Because site can be like, you know, in jungles or in remote locations. So, we need to prepare a site. So, that first reason or first milestone would be the site preparation. So, once you complete your site preparation, then only you can move. Then, the second part, which is, you know, you divide it as a pile cap or ground beam. You need to set up a ground beam. Then, the third is structural beam. You need to put a structural steel on your site. Then, which is external.

Then, floor slab, brickwork, mechanical and electrical services. And then, we have a finish work. Now, these are the WBS. So, what you did, you divided your project into the further division-wise. For example, I will give you another example. You have a construction of your one residential project. Now, what we need to do, first could be approvals. You may require lots of approvals. So, first, WBS could be approval. The second, WBS could be engineering and design. Like, you know, first, you need to prepare a design, okay?

Once it is approved, then only you will start other things. So, design and engineering. The third one could be like procurement. Once your design is finalized, once you have BOM, which is, you know, bill of material, okay? The quantity of the material which is required to build that residential project. Now, you need to procure a material. So, there's a procurement, you know, WBS. Once your procurement starts, simultaneously, you can start the construction. So, this is the construction. So, in the construction, further, you can divide as, like, site preparation, okay?

Now, the construction work, you can divide as, like, substructure work. The structure work and then the finishing work. So you can divide WBS at many level as you want. So further if you say the site preparation, so we have divided further, so it could be activities or it could be WBS. If you want to divide more, if you want to go into more details, you can divide further WBS also, which is like a sub WBS you can create. So we have here is site preparation, we have divided into the mobilization, that resource mobilization.

Then we have divided into the excavation. So now once the mobilization was done, we need to start the excavation. Now after excavation, we need to start the piling work. So this is how you can create. So now as I said, you can divide the WBS. Now if you don't want to divide the WBS, then you need to enter the activities. So this could be your activities like mobilization, excavation, piling. So this could be your activities as well. So activities are basically called as a fundamental work element of the project, like the work which you are going to execute basically at small level.

You know, they are the lowest level of the work breakdown structure and activity should have certain duration, cost, resource, roles, requirements. So we are going to work on the activity, activity like, you know, to paint a wall, a brick work, like, you know, a plaster work, you know, shuttering work, you know, excavation work, you know, pipeline work, the installation of, you know, electrical panel. So these are some of the example of the activities. Okay. So we need to enter the activities. So these are the, you know, if you see, this is a project, you know, we have foundation, we have external construction, we have internal construction and further.

So this WBS, we have further divided into these, the activities. So in the foundation, what we need to do, you need to do excavation and further activities, which I'm going to show you on the software as well. Okay. So now we are going to see the software. So what we have seen till now is just to recap again. So we have seen Pramavera, we have seen history of Pramavera, we have seen the key benefits of the Pramavera, we have seen key features of the Pramavera, we have seen some real time, no example, a great projects, which was executed with the help of Pramavera.

And then we have just seen like what is project, what is WBS and what is activity. Now I'm going to show you on the, I'm going to take you on the Pramavera software.

Want the rest of Project Management Using Primavera?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Project Management Using Primavera course

The remaining 42 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Project Management Using Primavera course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.