Process Groups, Knowledge Areas and Why Projects Fail

A free lesson from Skill-Lync's Project Management Using Primavera course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 2”

What will you learn in this free Project Management Using Primavera lesson?

The instructor covers stakeholder influence and the cost of changes over the life cycle, the role of a PMO, the five process groups and the ten knowledge areas. It then looks at project constraints, large Indian infrastructure projects, and reasons projects fail, with Nokia and Kodak as examples.

  • Stakeholder influence and cost of late changes
  • What a PMO does for project managers
  • Five process groups, ten knowledge areas
  • Typical causes of project failure

What comes after lesson 2?

The next free lesson is lesson 3, “Why Use Primavera: Industry Use and Work Breakdown Structure Intro” (32 min). Later in Skill-Lync's Project Management Using Primavera course (paid): lesson 4, Week 1 Session 4; lesson 5, Week 2 Session 1; lesson 6, Week 2 Session 2. The full course has 45 lessons (20 h 0 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

So next we will see about the project life cycle characteristic graph for the stakeholder influence, risk, uncertainty and the cost of changes. So again on the x-axis we have project time and on the y-axis we have a degree of influence like you know the impact that the impact of the degree of the cost of changes across the project time. Similarly for the stakeholder influence, risk and the uncertainty. So let's talk about stakeholder influence, risk and the uncertainty. So risk stakeholder influence should be or is always high on the starting of the project.

Okay as I discuss with you about this starting of the project and this preparing plan that we will involve lots of stakeholders. We will do stakeholders, we will do stakeholders study, we will gather their requirement, we do lots of surveys, we you know hire you know some agency to get the information about the market, about our customers, you know about the requirement. Then that means the stakeholder influence because we interact with the stakeholders, you know we meet them, we gather all their requirements, their expectation, you know in the starting of the project or in the preparing a plan phase.

So stakeholder influence is always and should be very high at the starting of the project that means at the planning stage and it should be very low while the ending of the project or at the completion stage of the project. Because at the last stage of the project or let's say the execution time of the you know stakeholder, it should not like you know your customer or your you know client is coming and saying that you know I need this, I need this, I need this, like you know as I give the example.

So you are as a contractor and you are making a residential project and your client is asking you know at the end of the you know execution stage that I need a one you know gym and one swimming pool also. So for you, so for you, so for you, the first thing you have already designed the layout okay so to have a you know a separate gym and you know the swimming pool you need to change you need to first find the location also like you know because you have already planned everything and you have already executed as well.

So for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so for you, so the middle of the project or at the end of the project stakeholder will ask some kind of another requirement now risk and uncertainty again as i said like risk will always be there you know the only thing is like you know how you will manage the risk like you know how you will mitigate all these risks so the risk should always be on the high at the starting of the project as a project manager as an experienced person you should list down all the resources so normally what we do that we will also see in oracle primavera while preparing a plan we will do risk management where we maintain a risk register so risk register is kind of a you know excel sheet or we have a you know module in the primavera where we will mention all the risks so let's say what could be the risk in the infrastructure project the first risk is you know my contractor got like got delayed because he don't have the resources my resources went for holidays the weather condition you know you don't know about the when the rain can come uh your financial your sponsor uh your funding company will stop you know funds right okay so this could be the risk so in the similar way your raw material can be delayed okay your uh machinery uh may require repairs or maintenance at the middle of the project so this could be all the list and you need to note down all the risks that could occur in your project then what we do in the risk we again mention like risk you know what is the probability of occurring that risk like you know let's say you know weather so weather like probability of having a rain in the upcoming month or in the next month or next week is like 5 percent or 50 percent so you need to mention the probability of occurring that particular risk yeah the risk the probability of you know getting raw material uh delay so it it could be you know 50 percent so you need to mention the probability of the risk occurring then what we do we mention the on the impact okay so if let's say you know uh the weather or rain come what will be the impact on my project or we will do all these things in details so just to give you an overview about the risk i'm telling you all these things so we mentioned like you know if the rain comes so it may impact my schedule it may impact my you know cost so what what is the impact so that also we will do in preparing a risk registered so project manager should you know uh involve all the risk uncertainty at the starting of the project only okay and it should be you know high at the starting it should be low at the what i say it should be low as the end of the project now cost of changes the cost of changes the impact of cost of changes in your project is always less uh in your uh starting of the project because at that time you have not started anything so in the starting after even preparing a plan your client is saying okay i want a swimming pool so for you because you have not started the execution you have not started the construction for you just to you know add in the document it may impact a little bit only so the cost of changes impact in your project in the starting of your project is very low okay but as soon as you are moving towards your project you know delivery or you know after some time your cost of changes impact is very high because as i said like you have already built you have already constructed you have already executed the work so the cost of changes impact should be or will be low at the starting of the project and will be high at the end of the project so to men to minimize the cost of changes or to make it zero we need to do lots of stakeholder study we have to involve our stakeholders we need to put we need to mention all his requirement the expectations we need to have all the information we need to have all the information in a document so that our risk should be minimized and our cost of changes will become a zero so this is how uh your you know three factors impact your project life cycle now let's talk about this project management office so as i said nowadays the companies they have a pmo department in the organization a good company or mnc you can say they have a separate department in the organization which is called as project management office so what is the responsibility of the this department what they do in uh in in a project so let's see so the project management office is a management structure that standardized project related governments process also it facilitates the shading of resources methodology tools and techniques the responsibility of pmo can range from providing project management support functions to actually being responsible for that management of one and more projects that means the first is like when you're talking about a project so let's say uh you need to build a road okay so there's a highway that you know a hundred kilometer highway that you need to build by a company so you need lots of approval from the uh you know different different department of the government it could be forest department it could be land department it could be any any department so you need a lots of approval first to build a highway then you need to involve so many team procurement team vendors you know design team finance team so this is a process this is we call it as a you know business process so what the project management department do so they standardize all this business process okay so their responsibility is to ensure that as a manager as a project manager of one project you will get all the required things on time and in a proper way so if you require any approval so they will help you and if you find any difficulty in getting approval so they will help you to get the approvals if you find any difficulty to get the funds so they will coordinate with the finance department and they will make sure that you will get the funds on time if you find any difficulty in getting the resource on time they will help you and they will coordinate with HR team.

They will, you know, they will make sure either the company will hire a new site engineer or designer or they will, you know, outsource this work. So their responsibility is to make sure that the process of the projects, okay, will, you know, smoothly execute. Also, like it's mentioned that, you know, the facilities to sharing the resources. So let's say because they are coordinating with all the departments on all the projects, so let's say in your company, there are five different, different projects are going on and you are the one of the project manager on one project and you may require some resources, some, you know, a crane operator, same, some, you know, hydro operator, site engineer.

And so you will send your requirement to the PMO department. Then they will check with the other projects. So there might be a situation where, you know, some, you know, site engineers or operators are available on other sites, like they don't have a much pressure on the project. So what the PMO will do, they will... You know, provide you all the resources from another project. Similarly, you know, techniques, methods, logic, the processes, tools and techniques. If you require some, you know, tools for your project, which is going to help you to execute your work in a proper way.

So the PMO department will facilitate all these, you know, services to the project managers. Now, so there are some of the process groups when we're talking about the project management. What are all these processes, process group? So there are five process groups in the project management. The first is the initiation process, the planning, execution, monitoring, controlling and the closing process. So we have seen the phases also like, you know, where we start the project, where we plan, where we execute, where we close. Now, there's another process which is called as the monitoring and the closing process.

So this is through this graph, I'm going to explain you. So let's say your project started, that means you initialize your processes, your initiation, you initiate your project. OK, then the planning process where you plan about your project, like, you know, how you are going to execute, how many resources are required, what is the budget, who's going to, you know, give you money, what is the time required, you know, how you are going to plan, at what time you required, you know, raw materials, everything we plan in the planning process.

Then we start the execution. So once your planning will complete, your execution will start. So once you execute and your executive process start, your monitoring, controlling process will also automatically start. That means while executing, you are monitoring your progress, you know, whether you are executing your process as per your plan or not. If there is any deviation, you need to control that process. So let's say for the piling work. So let's say for metro projects, for piling project, you have planned that I will, you know, do this activity in 10 days.

But while in the execution, you took 12 days. OK, that means there's a delay of two days. Now, this two days delay will impact, you know, other activities as well. So in the monitoring and controlling process, we will monitor, we will track why it is get delays and what would be the impact of these two days delay on the other activities. Now, they need to control this, you know, delay because it may impact on your project as well. So if something happened, now this monitoring, controlling process will ensure that it can be controlled with a minimum time and within a minimum cost.

Now, once everything was done, then we will start the closing process again, the documentation process, and then the project comes to the end. So every project will have five process groups, which is initiation, planning, execution, monitoring, controlling, and the closing process. Now, there are some of the knowledge area, you know, in the project management, we have seen the in the definition of the project management. It's the project management is the application of knowledge, skills, tools, and techniques. So these are the basically the techniques of the project management, what we need to manage in a project.

OK, so in a project management. So there are 10 parameters that we need to manage. The first is integrations, the project integration management. Then we have a project scope management. Then we have a time management or schedule management. We have cost management, quality management, human resource management, communication management, risk management, procurement management, and the stakeholder management. OK, so just to give you an idea, I'll just explain you all this 10 knowledge area. OK, now integration is basically the sum of all this nine knowledge area. The scope management is basically the scope is basically your work.

OK, what you are going to execute if, let's say, you want to have a residential project. So in the residential project, your scope is how many towers are there? What is the configuration of the flats? What are the facility you want? So the scope, the work or deliverables, which you are going to, for which you are going to execute. So scope, you need to manage. We will see in the primary data how you can manage your scope. OK, how you can mention all your scope, all your activities, not time or schedule management.

So there are some techniques, there's some, you know, procedure to manage your time, your schedule. OK, so we need to manage our time and schedule. We need to calculate what would be the time required to complete your project. So let's say you want to set up a cement plant, cement manufacturing plant. So as a project manager, because you already worked on the similar kind of the, you know, project. So let's say on a high level, you know that it may take two to three years. But what is the exact time do you require to complete this, you know, cement manufacturing plant setup?

Because now the situation could be different. Your location is different. Your raw material vendors are different. Your team is different. So overall, you know that, you know, it may take two to three years. But what is the exact number of days you required, you know, to manage or to execute your, you know, this project? So you need to prepare a schedule and how you can manage your schedule that you need to learn. Now the cost. We required cost to execute the project. Obviously, like, you know, everyone knows that we need some budget.

We need, you know, cost, everything. So you should know from where you are getting funds, how you are going to manage your funds. So let's say you are going to execute a project, which is worth of this project is thousand crore. Your sponsor, your funding or your finance department are not going to give you, you know, this funds, you know, in the starting of your project. Okay. So you need to prepare a plan, how you want this funds. Like, you know, probably first month you may require 1%.

In the second month, you may require 2% or 3%. You need to prepare a plan. So that is a project cost management, how you are getting funds. You know, everything you need to plan. Now the quality. Everyone, you know, know about, you know, now the customer, either you or anyone. Now everyone wants the quality, you know, the quality of the product. You know, why, you know, small contractors, small builders are, you know, failed? Because they are not able to provide the quality of the project. So the quality is very, very important, you know, in nowadays.

Like, you know, because every customer is, expectation of the customer is, you know, better quality product. So you need to manage how you can manage a quality across your project or your product. The human resource management. As I said, to execute a project, we need, you know, resources. Whether resources can be your labor, your machinery, your, you know, site engineer, your vendor, your raw material, anything. So how you are going to manage all these resources? So there's a technique. This is also that we need to manage while preparing a project management plan.

Then communication management. Again, communication is very, very important. Like, you know, the communication between the two teams, the communication between you and your client, the communication between you and your vendors. So we all know that now communication is happening through, you know, emails or, you know, verbally also we communicate something. And after, you know, sometime they, you know, something happened and this become creates some issues. So we should have a proper communication plan. We should have a proper communication channel to, you know, avoid all these claims.

Then we have risk management, as I said, as I explained. So we need to prepare a risk plan. We need to prepare a risk management plan to mitigate all this risk. Now procurement management. Again, you know, to execute any infrastructure project, we need a raw material. Okay, we need steel, we need cement, we need steel, we need, you know, lots of things. So how I'm going to procure all this raw material? From where I'm going to procure all this raw material? Who will be my, you know, vendor?

Who can provide me best quality raw material? Who can provide me cheap and better quality, you know, raw material? What will be my, you know, delivery site? You know, everything we need to plan in the procurement management. And then comes to the stakeholder management, which is like, again, you know, we have seen that, you know, this stakeholder study is very, very important. So we need to prepare a plan. How I'm going to, you know, involve my stakeholders? How I'm going to, you know, consider all their expectations?

How I'm going to, you know, convince my stakeholder if they are not, you know, convinced with the plan? So everything you need to prepare a plan and we need to learn, like, how all these, you know, 10 knowledge area can be managed. So this is like, you know, the techniques which you need to learn and which we need to apply in this Oracle Plamera software. Now, we are talking lots of about, you know, project management. So you might have a feeling that now, nowadays, like, you know, the requirement of project management is increasing.

But have you think like, you know, when you're talking about project, it's not like nowadays we have projects. We have projects from, you know, from thousands of years. Like, you know, I've just put some sample pictures of, like, Taj Mahal, you know, this Ajanta case, this China, the Great Wall of China. So Taj Mahal, if you see Taj Mahal, it's like, it was a great project, you know, but you know the facts also. You know, for Taj Mahal, it took, you know, 20, 22 years. It took like, you know, 20,000 laborers was involved and it took lots of, you know, cost also.

So then what is the factor or what is, you know, why we need a project management nowadays or the requirement of the project management is increasing day by day. So there are project constraints that we need to, you know, manage nowadays, which was not considered in the previous era. Like, you know, while managing or while, you know, building a Taj Mahal, they have not considered a risk. You know, they have not considered budget. So it's like, you know, it was a dream of the king and it was like, you know, okay, you can spend unlimited money.

There was no schedule, which was like, if, you know. Tahajmal was planned for five years. If it took 10 years, nobody's going to ask. Okay, so there is no client, there is no something like it was only king who want to build a Tahajmal. That was the scope only. The quality is he want a better quality, but there's no kind of the competition. There is sources. So if he would require, you know, 50,000, he has to arrange like he can arrange without any kind of, you know, approval or a process. And if he would require like, you know, in changing the scope, he can take a decision.

So, you know, nowadays, we have lots of things that we need to, you know, consider because we have lots of stakeholders are there. But before, you know, you know, few years or if you're talking about all these projects, there's no fixed scope, there's no fixed time, there's no fixed cost because the king has lots of money so he can spend because his dream was like just I want a Taj Mahal. Okay, but now we need to balance all these competitive constraints. We need to balance risk into balance budget because you will have a fixed budget you and you cannot exceed, you know, these budget. If let's say to set up a, you know, highway or if you to set up a refinery, if you need 10,000 crore, you have to complete your project within a 10,000 crore. Otherwise, you have to, you know, provide lots of explanation, you need to have lots of documentation, you need to explain, you need to submit lots of, you know, reports similarly schedule.

So, for every project, now we have a schedule, you know, before even starting of the project, it was decided that, okay, you need to execute this project into three years. Quality, everyone, as I said, like because of the competition, everyone expected a quality. Okay, the resources, okay. It's not like, you know, now you're asking from your, you know, client or from your senior management that, okay, I need 500 labors and at the mid of the project, you can ask, okay, no, no, 500 is not enough.

If I need, you know, 1,000 labor, they will not give you, you have to manage your project within a limited resources and the scope, like you cannot change the scope, okay. So, we need to balance this triple constant and because of that, you know, the project management requirement is increasing. Again, there's another slide which will show you why we need a project management. Because of, due to technological advancement, the life of the product is becoming shorter. Okay, you just consider, like, you know, how long you are using your current mobile phone.

Nowadays, every month, you know, every company, they are releasing a new product. You take an example of the automobile sector. So, within every six months, most of the companies are releasing their new, you know, version or operation of the, you know, car model. So, the life of a product is very, very shorter and because of that, you know, even to upgrading a car model or to upgrading a mobile phones, this is a project, right. I need to improve the services. I need to provide a best quality product with the best features, you know, if I compare with my competitors.

So, the life of the product is becoming shorter and because of that, we have a project and we need to manage a project. Okay, now, another terms are, which I would like to highlight is 3C. I used to call us 3C and they are increasing day by day. The complexity, the complexity of the project. Because we need to balance all these constraints, the complexity of the projects are increasing day by day. So, if you consider the, you know, budget, schedule, you know, resource, scope, if you want to change the budget, you need lots of approvals.

Okay, still, you are not confident that, you know, you will get the approval, you will get the extra budget. Again, in the schedule, if let's say if you need to ask from your, you know, client or from your senior management that you need one month extra time, it will take lots of approvals. Again, for resources, for scope change. So, the complexity of the, you know, because there are so many stakeholders are involved, the complexity of the projects are becoming a competition. You name it any sector, whether it's residential, whether it's a commercial building, you know, lots of builders are there, lots of infrastructure companies are there.

And as a user, you are not sure, like, you know, which product or which project you should go for. So, the competitions create lots of, you know, issue and because of the competition, again, there's difficulty in managing all this constraint. And because of that, we need a project management. Now, the customization. Now, everyone, every customer, whether it's residential customer, whether it's, you know, mobile user, whether it's car user, every customer want a customized product. Just think like, you know, you purchase your last mobile phone or last laptop or last car.

How did you purchase that? But probably, like, you know, first, you have shortlisted here all the requirements. So, let's talk about mobile phones. You have listed, like, okay, what should be a camera quality or camera size? What should be a RAM size? What should be a screen size? What are the features do you require? Then you shortlisted the product. But if you go back in, you know, 15 years back, you were not having that choice because you had only, like, you know, Nokia phones or that 1100 or something like this.

Similarly, for car, now, you know, if you go for, okay, you just type on Google that, you know, I want a car in within a 10 lakh budget, you will have, you know, 50 options. But if you consider, you know, 10 years back or 15 years back, we don't have that, you know, options. So, now, the customization, similarly, in the residential project, you know, for me, I need, you know, 3 BHK, which you should have, you know, balconies also, car facing view also, northeast facing also, it should have balconies also, it should have, you know, study rooms also, or work from home also, like, lots of requirements are there.

You know, so every customer now, first customize the requirement, then they select the service provider. So, because of that, I need to, and as a builder or as a service provider, I cannot consider, you know, all requirements. So, I need to think about in a way that, you know, all my stakeholders requirement can meet. So, the customization of the project is increased and because of that, again, the complexity has increased. So, because of the 3C, now the projects are becoming more complex, you know, execution of project has become a more tedious job and balancing these constraints are becoming difficult, you know.

So, we need a project management to, you know, to balance these constraints, okay. So, this is why, like, we need a project management and the requirement of the project management is increasing day by day. Okay. Now, let's talk about some facts, okay, some current and future futures project in India. So, approximately 304 lakh crore of investment is expected in Indian infrastructure sector till 2040s for straining the country's development. India is set to become third largest aviation in the world by 2026, which is like five years now.

Now, plans to increase the number of airports from 100 by 2024. The sector is, was to become one of the largest infrastructure sector in the country. Massive shift towards sustainable development with the aim to achieve 175 gigawatts of renewable energy by 2020. Shift to electric vehicles completely by 2030. Now, we have approximately 75 gigawatts of renewable energy and within one year, we are going to achieve 175. Five, organizations like, you know, National Highway Infrastructure Development Corporation Limited were created for managing and developing border areas, project in northeast, strategic hilly roads, and other frontiers.

These are some of the mega projects which is upcoming or which is going on. Char Dham Express, Gujarat International Finance Cities, International North-South Transport Corridor, Freight-Only Railway Tracks. We know that, you know, from Delhi to Mumbai, that, you know, a dedicated freight corridor is going to build. From Delhi to Kolkata as well, from Kolkata to Chennai, Chennai to Bangalore, Bangalore to Mumbai. So, we know that, you know, a dedicated for, you know, for goods transport, they're going to build a separate railway track. Mumbai Trans Harbor Link, Shivaji Memorial is going to, you know, build, which is similarly like, you know, that we have, you know, that statue of unity in Gujarat.

Setu Brahmaputra Project, Bharat Mala Project, and Sagar Mala Project. So, these are some of the major projects which is either going on or upcoming in India, which require lots of project management. Again, the Bharat Net, River Interlinking, Smart City, we all know that Smart City, you know, missions there, you know, in India, we will have hundreds of smart cities. This Udan Project, India to build 100 new airports by 2024 to boost the air connectivities. Again, industrial corridors, so as I said, like, you know, Delhi-Mumbai Industrial Corridor, Mumbai-Bangalore, Bangalore-Chennai, Chennai-Visag, Kolkata-Daili-Amritsar Industrial Corridor, and then we have metro projects.

Almost every major city now will have their own metro. So, Lucknow metro, the DPR is already ready, and some of the portion is already built. Chandigarh metro, DPR prepared. Jaipur metro, we already have phase one, which is in operation. Ahmedabad metro, which is under construction. Nagpur metro, recently, last week only, they, you know, inaugurate Nagpur metro. Mumbai metro, phase one, is already in operation, and two, under construction. Navi-Mumbai metro, which is under construction. Bangalore metro, again, one is already in operation. Second phase is under construction, Kochi metro, which is, again, you know, first phase is already there.

Another phase is under construction, Delhi metro. First two is already there. Second is under construction. Four also, they have started. Rapid metro, that is, again, you know, currently in operation. So, every city will have their own metro, you know, within a few years. So, this is, again, this is a, you know, major project, which is coming in India. Similarly, we have, you know, this bullet train project, high-speed metro project. So, lots of projects are coming to India in the infrastructure, and we need a... Project management for these projects.

Now, just think, you know, I want to take, you know, in another mode now, we know that what is the project management, you know, we know that lots of, you know, projects are going to happen in India and lots of, you know, project management requirements are there. But still, the construction projects have the higher failure ratio. Why? Now, what is the reason behind this? So, I have mentioned some of the, you know, points, some of the reason why the construction project have a higher failure ratio.

The first one is lack of senior management commitment. The second one is inadequate project planning. The third one, absence of users' involvement. Fourth one, newer unfamiliar technologies, lack of defined, clear, concise requirements. Let's just, you know, have a look on, you know, one by one. The first, lack of management or poor management. You know, this is not, you know, my point. This is from the one case study. You know, we know that, you know, I have seen personally in small construction industry or even in the big construction industry, like, you know, most of the management are not ready to take a decision.

Okay, so, we have a very, you know, few good example, not in the infrastructure, you know, from the industry, but, you know, we all know about the Nokia studies, you know, case study, like, you know, why Nokia failed. At one of the time, like, Nokia was, like, one of the leader in the mobile. But suddenly, like, when Android started, they refused because it was a management decision that they don't, they don't, you know, want the Android. They think that, you know, it will not work. But now everyone knows about that.

Similarly, that Kodak camera, you know, you might know about the study, like, Kodak camera at the one time. It was, like, you know, one of the biggest market of the camera, and they were not, you know, and they didn't accept that digitalization in the cameras. So, they said, it's not possible. At that time, we had a reel, and if we need to go to, you know, the camera gallery, we need to paint, lots of things are there. But then we have a digital camera where all the pictures can be cheap.

So, they refused to have these digital technologies, and we all know about now, you know, how many, you know, Kodak cameras are there. So, it was like, you know, the poor management, they are not ready to change. They are not ready to accept the new technologies. Okay, so, you know, and poor management, I just put a picture. Let's do one 40% project and get a project success at, you know, 100%. They already considered that there would be a 40% of failure here. So, the mindset of the poor management is one of the biggest reasons in the construction or infrastructure industry for project failure, the lack of planning.

So, this one funny picture I have added, we have seen that we have a separate phase, which is a planning phase, and we need to plan about everything. We have seen a knowledge area. So, there are 10 knowledge area which we need to plan while, you know, working on a project. And most of the companies I have seen, especially in India, they consider planning as an expense. And I would like to say, this is not an expense. This is an investment that, you know, every company should have.

And, you know, because if they don't plan, if they don't plan how much cost is required, how much money is required, then they'll never be coming to a, you know, a success. They are not going to, you know, execute a project in an expected way. They are not going to complete a project within a time, within a budget. Okay, so, lack of planning is another second reason of, you know, a project failure. Lack of awareness of the actual problem, you know, again, you know, we face a problem, but we ignore the problem.

We'll say, okay, we'll see at the later stage. So, it's like, you know, ignoring or we are not aware of what is the actual problem. If we'll take decision on that, at the same time only, the situation would have, you know, become better. But, you know, if you see, you know, the confidence level, like, you know, we got the idea of this point, you know, at the mid of the project, but we take a decision at the end of the project. Okay, now we need to find some solution.

But, my friend, like, time has gone, like, you know, I will not wait. So, now, you already failed and now you're finding the solution. So, lack of awareness of actual problem is another one of the biggest reason for project failure by not selecting the right people for the right job. We have seen India, like, you know, a crane operator is, you know, running something hydro or, you know, a mechanical engineer is doing a civil engineer job. A civil engineer is doing electrical engineer job, you know.

So, we are not selecting the right people for the right job and this could be another, you know, a failure for a project. So, inappropriate machine and compromise, you know, safety factors. Again, you know, this could be one of the, another, you know, great, you know, or big reason for the project failure. We are not selecting a proper machinery, proper safety expects. So, if you have seen L&T, so they are very particular on the safety, you know, they have a particular department on the safety and safety people are always on our side so that, you know, they can avoid all that because of this, you know, safety prospect.

Correct. So, most of the company, MNC, they consider the safety expects, but small company, they, you know, they ignore all this safety expect and because of that, you know, some accident or something happened outside and because of that, our project get failed. So, you know, we are not, you know, we are not, you know, tracking our project, we are not, you know, audit our project, our progress on a time. So, because of that, we are not able to find a problem and because of that, our project get failed.

So, so this is some of the study again, you know, because of the project failure, okay, 50% of the project are, you know, run, are running on a time overruns. Like, you know, they are not completing a time. So, there are on an average 24 projects which are running over time. Like, you know, they are not completing the project, okay. The average time overrun is 17%. Like, you know, every project, if I conclude on an average, every project is running like 17%. So, if you see, now, let's say the project duration is like, you know, 1,000 days.

So, they are completing the project in 100, 170 days and this 170 days, it's like, you know, the cost is involved, the resources are involved, lots of things are involved for this 170 days and because of that, cost is also will increase. So, and the budget, if you see, there are, you know, 19% infrastructure project who are completed over budget and every project will have like, at least, at least, you know, on an average 14% as a higher budget. Like, say the project is, you know, 100, 100 crore, they are completing their project in, you know, approximately 150 crore.

So, so every project, because of all these failure factors, we are time overruns and we are budget overruns. Now, we'll see why projects succeed. So, there are some of the factors that we will, you know, see that why, how we can achieve our project on time, on cost, within a cost and within a quality. So, these are the some of the project success factors. The first is sound project management process. So, we have seen project management processes. Now, we need to implement all these processes. We have seen in the project management definition itself.

So, project management definition says, it's application of knowledge, skills, tools and techniques. So, techniques are basically the project management processes. So, we need to have a sound knowledge on the project management processes and we need to ensure that we are using, we are implementing in our project. The senior management commitment, we need to, you know, we need a commitment from the senior management. We need to make sure that they provide us all the required material, you know, approvals on time. Detailed requirement. We should have a proper detailed requirement plan.

We should have a proper, you know, project plan which will state that, you know, what is the resource requirement? What is the time requirement? What is the budget requirement? A realistic schedule. We should have a proper schedule. Good stakeholder relationship. We should have a good relationship with our stakeholder. Then only we can convince them. Then only we can decrease the influence. Okay. Empowered project managers. Like, we need to give the power or authority or decision-making power to our project management because he is the only person who knows the entire situation.

He knows what is happening in my project and what could be the, you know, solution for this project. So, if we are not giving the power, if we are not giving the, you know, decision-making power, the authority to the project manager, our project will definitely impact. And the last one is talented and appropriate team members with defined job role. So, as I like, you know, not selecting the right people for a right job is one of the reasons for project failure. But if we select the right people, appropriate people, and talented people, definitely we can succeed in our project.

Now, we have seen some of the project success factors. Now, how we can achieve this. So, we'll see. Before that, I just want to conclude, you know, what we have seen. So, we have seen project life cycle characteristic of our influence, stakeholder influence, risk, uncertainty, cost of change. We have seen project management office. We have seen process groups. We have seen knowledge areas. We have seen, you know, we need a project management in this scenario and why the requirement, why the need of the project management is.

We have seen some of the facts about current and future projects that is happening in India. So these are some of the current and mega projects in India, the metro projects in India, and we have also seen like why do construction projects have the high health failure ratio? So what are the reasons? So we have seen all these reasons for project failures. So we have seen like, you know, if the project fail, what is the impact and what is the standard of time overruns and the budget overruns?

And we have also seen why the project, why, you know, how we can make sure that our project will succeed. So what are the, you know, steps that we need to take? Okay. So now we are going to see how we can succeed our project.

Want the rest of Project Management Using Primavera?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Project Management Using Primavera course

The remaining 42 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Project Management Using Primavera course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.