Planning an Elevated Metro Corridor: Survey and Alignment

A free lesson from Skill-Lync's Design of Elevated Metro Viaducts using STAAD.Pro course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Planning of Elevated Metro Lines”

What will you learn in this free Design of Elevated Metro Viaducts using STAAD.Pro lesson?

The instructor explains how a topographical survey locates constraints between two points of a city, such as shops, houses, a river, a national highway, temples and flyovers. The lesson shows how each forces the alignment to shift, why two or three alignment options are costed, and the life cycle from feasibility study to tender, construction and trial run.

  • Purpose of a topographical survey
  • River width, discharge and highest flood level
  • Realigning around highways and flyovers
  • Alignment feasibility study and costing

What comes after lesson 3?

Later in Skill-Lync's Design of Elevated Metro Viaducts using STAAD.Pro course (paid): lesson 4, Challenges in Planning Elevated Metro Corridors; lesson 5, Week 2 Session 1; lesson 6, Components and Structural Components of Bridge Superstructure or Elevated Metro Superstructure. The full course has 48 lessons (19 h 46 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Hello and welcome to this next session on the course on Design of Elevated Metro Wired Up and this is the second part of our first week of the course and in this particular session we will be talking about planning of the Metro Wired Up so basically in this session you would want to have a look at various aspects that a design engineer needs to take care of while he or she is planning an elevated metro wider, what are the challenges that come up when you plan an elevated metro wider corridor, how to overcome those challenges, what are the various technical difficulties during construction that you might encounter and how to come up with a solution of those technical issues and finally how to design a safe and sound structure which caters to the need of the people using that particular metro corridor.

So let's start with this session, let's quickly have a recap of the last session wherein we discussed about the operational metro projects in India, the metros which are under construction at the moment, the proposed metros, government's future future plans with respect to construction of new metro corridors and then we also looked at the three components of the metro corridors, namely the underground metro, the elevated metro and the station part. So we covered in detail all of these aspects and saw that the government is putting a huge emphasis on construction and maintenance of metro corridors and it is trying to open new metro services to the people of different cities in the country which brings to us engineers great opportunities in the metro domain for employment and that is precisely why we are here to understand the many things that a design engineer should know about the metro wider planning as well as design.

So in this session you will be looking at the topographical survey, what exactly is a topographical survey, why it is done, what is the need for a topographical survey, the possible changes that we might have to do when we plan a metro corridor between two points of the city. What are the challenges that we encounter, how do we overcome them, we will look at the possible solutions of those challenges. So this is going to be an interesting session and it will give us an insight on how to plan an elevated metro corridor.

The learning objectives for this session would be that by the end of this session you will learn about the topographical survey for metro construction, the possible changes that are required in the process of planning and designing a metro corridor and you will understand the various challenges that are faced by the engineers in the planning, design and construction of metro corridors and their possible solutions. So here we see again the same picture that we had seen in our last session. We will look at it in greater detail now.

So as pointed out to you in the last session, this is a river bridge which caters to metro loading on the top deck and highway loading on the bottom deck on the right side of your screen. It is a frame kind of a structure which is made of a combination of beams and columns, longitudinal transverse beams and columns. This beam column frame type of a structure is supported on a foundation which is well below the water level resting on the river bed. Somewhere 25 to 30 meters or even more below the water level that we see here on the screen.

Now it is important to understand for us how do we plan this structure. So let us try to have a few insights on that aspect of a design engineers job. So you see here, before this bridge would have been built, first and foremost, there would have been a topographical survey which would have been conducted to locate the possible locations, possible sites for construction of this particular bridge. And then finally the engineers would have decided that this is the site which is feasible for construction. And what are the parameters that would have affected their decision?

Let us try to look at them one by one. First of all, the width of the river. Second is the discharge and the highest flood level of this river. The width of the river would decide how much long bridge we need to construct. The HFL or the highest flood level would decide how much high we need to construct this bridge. Because obviously for movement of traffic, we cannot allow water to overflow on this bridge. Therefore, the lower deck of the bridge should be sufficiently above the highest flood level.

And the depth of the river bed below the water level would decide the point of placement of the foundations. So at this location it is quite possible the river bed would be at its highest point so that the piers or the columns of this frame type of structure are the shortest at this particular location. Which would obviously save us a lot of cost in construction of the bridge. Similarly, this would be a site where the width of the bridge, width of the river would be the shortest.

And therefore, a shorter bridge is required at this point. So once the location of the bridge is specified on a river, we go ahead with the planning of the structural arrangement of the bridge. We see here a frame kind of a structure. This could well have been a single pier which would be supporting two decks on two levels. It could have been a structure where a single pier would have been provided and then there would be cross arms or cantilever arms which would be supporting the decks for the vehicular traffic.

But here we did not go for that kind of a structure. We opted for a frame kind of a structure. So the options could be many but we need to decide on one of the options depending on the ease of construction at that particular site. The contractor who has been employed to do that construction and the authority which is getting the bridge constructed. Everybody should be comfortable with the idea, with the structural arrangement, with the location of the site. And once all of these things are done, which is known as a feasibility study.

After this feasibility study, we move to the detailed design stage of the bridge. In that detailed design stage, a more exhaustive survey is done. We locate the levels exactly. We try to calculate the exact cost of construction operation of the bridge. We try to get the approvals for the budgets for construction of the bridge and its maintenance from the government. And once all of those things are approved, we have the budget available. We go ahead with the floating of tenders for the construction of this or any other bridge.

Once the construction tenders are floated, that is they are made available to the contractors. There is a bidding process and whosoever comes up with the least bid and who has the highest technical competency. A combination of the bid value and the technical competency finally decides who will get to construct this or any other bridge. The tenders for which have been put. It could be any of the agencies, contractors who have bid for that particular bridge. Once the contract is awarded, a mobilization advance is made to the contractor to make when material and machinery available onto the site.

And then construction activity is commenced. When certain milestones of the construction are achieved, phase-wise payment of the agreed cost is made to the contractor. When the contractor completes their work or schedule, they are made full payment of the work. And then this bridge is subjected to a trial run, so to say, wherein trains and vehicles are run onto the structure. Test vehicles and test trains are run onto the structure for a period of around three to five, four, three to five, six months. And if it performs satisfactory under those test loads, then it is open for.

So this is the normal life cycle of a bridge before it is open to the public for their daily commute. So in this course, we will study about all of these things. And in this session, we will discuss in little more detail about these aspects. So topographical survey is the first and foremost and an important part while locating the position of the bridge. So what we do in a topographical survey? Let us say we plan to build an elevated metro viaduct between two points A and B in a city.

These points could be quite far apart, maybe around 9 to 10 kilometers apart. The preferred option would be to go straight, to build a straight corridor because that would be the shortest route. And it would also be the quick route for flying over the metros. So metro train could be... From point A to B, shortest, by the shortest route in the quickest time. And that would mean that we have a straight line, a straight corridor, and it is a quick service. But then, life is not that simple, isn't it? We have quite a few complications as a design engineer. Let us try to look at them one by one.

In the topographical survey, we try to locate the various geometrical and geographical constraints which are there between these two points, A and B, in the area wherein we are trying to construct the elevator metro wider. What could these constraints be? So, let us see what all could be the possible constraints. There could be some shops and offices along the way. And when you plan a metro corridor, you cannot relocate those shops and offices because they are already approved buildings. They are commercial hubs. They are the points which generate employment for the people who would be finally using this metro corridor. It is for those people who are building this metro corridor.

And we cannot dismantle these shops just to make this metro corridor because that would defeat the purpose of building this corridor. So, what we do? We realign our corridor. So, you see a blue line here. Instead of going in a straight line, we have realigned this corridor. There could be more houses for which again a realignment would be required. Going further, there could be a river which would be crossing this alignment right? Of our metro for which we might be required to build a long bridge just like the bridge we saw in the starting of the session. Okay.

And that bridge will have to be first of all located with respect to the constraints on this river. So, it is not possible to locate that bridge exactly at this point on this straight alignment due to the reasons that we just saw in the previous slides. So, it is quite possible that we might have to locate this bridge somewhere here or here or here anywhere up and down the street. So, that would again change the alignment of this metro corridor. See a river bridge here. We have a river bridge. This bridge could have been constructed here also or it could have been constructed beyond this point also.

Why only this side? It is because this would have been the most preferred option with respect to the width of the river channel, the availability of the bedrock below the water level and the discharge at this point. So, this is the preferred location of the bridge and the metro corridor has to be realigned with respect to this preferred bridge location. Going forward, there could be a national highway and this national highway would necessitate the changing of the alignment of our metro corridor again because you see if we cross at a point here which is on the red straight corridor, we would have to build a longer bridge to span this national highway whereas if we cross it at an angle or preferably perpendicular to this national highway then we would have to build a smaller span of our metro corridor above this national highway.

So, due to this structural reason, it would be preferable to shift the alignment at an angle to this national or the straight line. So, this would mean that we would have to again realign our corridor. So, you see here from the red dotted line straight alignment we have made certain deviations which are shown in the blue line. If you move ahead we might encounter some religious places, some temples, places of religious importance which you cannot relocate because they have got a sentimental value with the local population and the local population would never want a place of pilgrimage to be shifted for the construction of a metro corridor.

So, again as planning engineer, we would have to shift our corridor slightly, we need to off track from this alignment from the blue alignment and then we need to shift it further. Again, there could be some existing flyovers when we start to move ahead on this line, there could be some existing flyovers which we need to again cross and we would have to again shift our alignment to avoid this flyover falling in our metro alignment. And avoid this crossing this flyover is because if we cross this flyover, we would have to raise the level of the metro.

Flyovers are already constructed above the ground almost 6, 7, 8 or 10 meters above the ground. And if we have to cross our metro corridor, if we have to cross this flyover or make our metro corridor above this flyover, it would mean that we will have to go additional 6, 7, 8 or 10 meters above this flyover which would unnecessarily increase the height of the metro corridor and therefore the cost of the structure. And we do not want to do that because as we are in a development country, we are short on budget, we want to build good infrastructure projects at minimum possible cost.

So, we can take a detour and we can shift our metro alignment on the side of this flyover. That is what exactly has been done here. And then finally, we can reach to our point B. So, what you see here are the various constraints or various geometrical, geographical features that you would encounter in any typical elevated metro wider project because these things that are shown here are not specific to any one city in particular. I mean, you would always have shops, you would always have houses, rivers, flyovers, temples and places of religious importance built across the city wherever you are planning a metro corridor.

So, these are general and most commonly occurring constraints which you would observe in any other metro corridor that you go ahead to plan and design. So, there we need to realign our structure and we need to come up with these. This is just one of the option. This is just one of the option of the alignment that we can follow. The one we see in blue line. We could have taken a different approach. We could have taken a different alignment also. I mean, we could have crossed here and reached point B.

You can see the location of my cursor. We could have reached point B like this or from any other route also. So, this is all known as alignment feasibility study. And a design engineer has to study the options of two or three possible alignments and then present to the client that these are the three alignments that are possible. Which of the alignment should we go ahead with? And then cost of all these alignments also needs to be calculated depending upon the final length of the alignment, the constraints that we have, the levels that would be required to be achieved and in the heights of the corridor that needs to be achieved.

And then finally, after working the cost and everything, we finalize one alignment with the help of the authorities or the client, which is in charge of construction of this metro corridor. Alright. So, there could be other constraints also that like railway lines crossing and everything. I mean, this is just a general idea of what are all the constraints that we would encounter while we go ahead and plan our elevated metro wider. So, I believe this would have given you a fair idea as to what are the construction challenges or rather the challenges during planning stage that you would encounter.

And all of these challenges or all of these geographical features are identified by the help of a topographical survey. So, an agency, a specialized agency is engaged by the contract, by the client to do a topographical survey of the area where the metro alignment is to be designed. And once that topographical survey results are available with the designer, we know exactly at what coordinates all these constraints like shops, houses, rivers, national and state highways, the religious spaces, the existing rivers and the existing railway lines are there on our alignment.

And on basis of that data, we can provide to the client a best possible route which can be adopted and finally constructed. So, these are the challenges that we encounter during planning. There could be various other challenges which we will look in our next session. And those challenges are mainly encountered during the construction of the project. So, we will see in detail all those challenges and we will discuss one by one what are the various solutions to those challenges. So, we will meet again in the next session and I hope this particular session was useful to you.

Want the rest of Design of Elevated Metro Viaducts using STAAD.Pro?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Design of Elevated Metro Viaducts using STAAD.Pro course

The remaining 45 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Design of Elevated Metro Viaducts using STAAD.Pro course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.