Wiring harness routing & packaging Rules Week 3 Challenge
1.P Clamp
- The P clamp is first uploaded in the part design workbench.
- We define the entry and exit point after cerate plane of entry, exit and base plane.
- Change the part design workbench to electrical part design.
- We define the entry and exit path of wire by using the support part command.

2.BackShell
- The cad file is first uploaded in the part design workbench
- We define the points for back shell connection & bundle connection
- The axis systems are placed on the back shell connection points
- The orientation of the axis system is not specific we just need to follow a similar orientation for all the parts.
- Change the part design workbench to electrical part design.
- We define the back shell connection point & bundle connection point

3.Corrugated tubes
- First open the part design work bench to change electrical part design work bench.
- Select the protection part command input the required data.
- After cerate the corrugated tubes and store the catalog files.