AIM: To generate the report for steel building design
Procedure:
1. Selecting the report icon
2. Selecting the model report and genarating the report




2 Answer:
AIM: To generate the report for Concrete building design
Procedure:
1. Selecting the report icon
2. Selecting the model report and genarating the report





3 Answer:
Aim:Update the layers settings in the model and generate plan drawings and details from the model
1. Selecting Settings
2. Selecting the drawing option
3. selecting scale and adjustion the scale