Challenge

Reinforcement Detailing of Beams from ETABS output

CHALLENGE 8

AIM:- To run the analysis and design the RCC moment resisting frame for G+4 building and To provide details of longitudinal and shear reinforcement for the two continuous beams To sketch the elevation details or draft it using AutoCAD software. To provide reasons for failure of the middle span along Grid A and the possible ways to resolve the issue. To calculate value of the maximum shear force in any one of the spans in both the continuous beams, as per clause 6.3.3 (b) in IS 13920 – 2016. Also, confirm these values from shear force demand calculated by ETABS.

PROCEDURE:

1.Open the design in ETABS

2.Go to analyze and check the model

3.Ones model has checked

4.Than run analysis the model

5.Check the animation of structure

6.Click to concrete frame design preference and check the details than click ok

7.Than design the concrete frame

8.Show the longitudinal reinforcement

9.Go to display design Info

10.Choose the shear reinforcement than apply and ok

11.See the shear reinforcement detail

12.Go to the reinforcement calculation :

1.Longitudinal reinforcement calculation:

Ast for 32 diameter = 804 .24

Ast for 28 diameter = 615.75

Ast for 25 diameter = 490

Ast for 20 diameter= 314

Ast for 16 diameter = 201

Ast for 12 diameter = 113

7 SPAN CONTINUOUS BEAM ALONG GRID 3

SL. NO

BEAM LENGTH

BEAM NUMBER

LOAD COMBINATION

STATION LOCATION

TOP REINFORCEMENT (mm^2)

BOTTOM REINFORCEMENT(mm^2)

SHEAR STEEL (cm^2/m)

1

4.5

B24

UDcon57

0.225

1408

704

13.05

2

4.5

B25

UDcon56

4.175

1308

654

120.5

3

8

B69

UDcon56

7.675

1938

969

140.45

4

8

B70

UDcon57

0.325

1940

970

14.45

5

5

B73

UDcon57

0.325

1425

713

13.67

6

4

B14

UDcon57

0.325

1301

650

13.15

7

4

B16

UDcon56

3.775

1367

684

13.08

Maximum at TOP reinforcement required 1938 mm^2

Maximum at BOTTOM reinforcement required 970 mm ^2

Maximum at the mid reinforcement required 1498 mm^2

Provided reinforcement at top 3T @32mm = 2412 mm^2

Provided reinforcement at bottom 3T @32mm = 2412 mm^2

Provided reinforcement at mid 2T @32mm = 1608.48mm^2

3 SPAN CONTINUOUS BEAM ALONG GRID A

SL. NO

BEAM LENGTH

BEAM NUMBER

LOAD COMBINATION

STATION LOCATION

TOP REINFORCEMENT (mm^2)

BOTTOM REINFORCEMENT(mm^2)

SHEAR STEEL (cm^2/m)

1

5.375

B33

UDcon67

0.325

1896

948

14.79

2

3

B34

UDcon67

0.325

2045

1022

O/S#45

3

5.375

B38

UDcon66

5.05

1906

953

15.12

Maximum at TOP reinforcement required 2045 mm^2

Maximum at BOTTOM reinforcement required 1022 mm ^2

Maximum at the mid reinforcement required 511 mm^2

Provided reinforcement at top 3T @32mm = 2412 mm^2

Provided reinforcement at bottom 3T @32mm = 2412 mm^2

Provided reinforcement at mid 2T @20mm = 628.31 mm^2

2.Shear reinforcement calculations

Grid line A (B38)

From ETABS output, Design shear force, V = 242.13 KN

Provide 2 legged 8 mm dia stirrups with 100 mm spacing

Providing 30 mm clear cover, Asv = 2x3.14/4x8^2 = 100 mm^2

Effective depth = 500-60 = 440 mm

Vus = 0.87*fy* Asv*d/Sv = 0.87*415*100*440/100 = 158.862 KN

Since Vus < V ( Design shear force), hence safe.

So provide 2 legged 8 mm dia stirrups with 100 mm spacing.

Grid line 3 (B 24)

From ETABS Design shear force = 209.58 KN

Provide 2 legged 8 mm dia stirrups with 100 mm spacing

Providing 30 mm clear cover, Asv = 2*3.14/4*8^2 = 100 mm^2

Effective depth = 500-60 = 440 mm

Vus = 0.87*fy*Asv*d/Sv = 0.87*415*100*440/100 = 158.862 KN

Since Vus < V ( Design shear force), hence safe.

So provide 2 legged 8 mm dia stirrups with 100 mm spacing.

3.Reasons for failure of the middle span along grid 3

From the above ETABS output it has been shown that the limiting value of shear force and developed shear force remains the same. Hence it is not safe

The possible ways to solve this problem can be :-

  • a) By providing higher grade of concrete
  • b) By reducing effective depth

4.Calculate the value of maximum shear for

As per IS 13920-2016, new load combinations has been added for sway combination, the partial factor for dead and live load is considered to be 1.2

Sway to left:-

V(u+a) = 70.58 KN, Mu (As) = 160.776 KN and Mu (Bh) = 233.59 KN

Vu,a = 70.58 - 1.4*(160.774+233.54)/3.9 = -70.998 KN

Vu,a = 70.58 + 1.4*(160.774+233.59)/3.9 = 212.14 KN

Sway to right:-

V(u+a) = 70.58n KN, Mu (Ah) = 154.79 KN, Mu (Bs) = 219.14 KN

Vu,a = 70.58 - 1.4*(154.79+219.14)/3.9 = -54.06 KN

Vu,b = 70.58 + 1.4*(154.79+219.14)/3.9 = 195.22 KN

  1. Detailing of beams using AutoCAD

Grid A

Grid 3

RESULTS: The following has been illustrated properly along with results:-

  1. a) Analysis and design the RC moment frame for G+4 building
  2. b) Providing details of longitudinal and shear reinforcement for beam along with elevation details
  3. c) Providing reasons for failure of the middle span along grid A
  4. d) Calculating value of maximum shear forces in any of the span
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.