Challenge

Project 2

Ans=

AIM:-  To develop a schedule along with baseline and resource for the construction of 100m WBM road inside the Skill Lync Education center premises to allow access to the centre for students and faculties.

INTRODUCTION:-

I will name the project as Education Centre Road and assign a 6X24 calendar. The starting date of the project is 22nd of February 2021. Here I will accomplish the Project as per the provided information given below-

Develop the project schedule as per the criteria above
2. Use 3-Tier timescale with Year / Month / Weeks
3. Define and Add resources
4. Add a budget to your project - INR 6 cr.
5. Assign a baseline to the project
6. Add following expense:
Task - 1 - Rs 20,000/- (Item - Fuel)
Task - 2 - Rs 30,000 /- (Item - Maintenance)
7. Generate material resource costs curve

  8. Generate an activity wise cost repor

  9. Create a reflection

10. In the reflection, auto update the project at 15 days from start
11. Open a TSLD view of the project in Visualizer
12. Add curtains up-to first 15 days of the project.
13. Find out the actual cost for labour, non-labour and material cost of the updated schedule

PROCEDURE:-

Here I will execute the project in Primavera P6 as per provided information. Now I will do the project step wise as mentioned below.

Step-1:-

First open Primavera P6 and create a 6X24 Calendar for project.

Step-2:-

Now Create EPS as "Education Centre Road"and assign a Project Manager

Step-3:-

Create a project under the above EPS named "Education Centre Road"

Then select the Project start date as 22nd February 2021

Then select the Responsible manager as Project Manager

Step-4:-

Now assign P-6X24 Calendar for this Project

Step-5:-

Now add activities along with durations as provided in the question under the Project

After that add Predecessors as per mentioned data in question

Step-6:-

Add Resources for the Project as per provided resource data in the question

Then a resource tab will open and click in add

Now Create Indian currency as INR

After that define material unit as Cubic meter by the following process

Add various Roles as mentioned below

Now add resources as provided in the question

First I will add Resource-A as per provided information

Now add next Resource as B- Construction

Now add another Resource as Resource-C

Now assign Roles accordingly

Step-7:-

Now assign Resources for each activities as given in the question

Step-8:-

Use 3-Tier timescale with Year / Month / Weeks

Step-9:-

Add a budget to your project - INR 6 cr

Step-10:-

Assign a baseline to the project

After clicking to Maintain baseline a new window will appear then click to add

Click to OK

Then select the type of baseline as Initial Planning baseline and then close

Then go to Project < Assign>

Then select baseline and Primary baseline and click OK

Then Go to bars and assign baseline

By right click Bars option will be available

Step-11:-

Add following expense:

Task - 1 - Rs 20,000/- (Item - Fuel)

Task - 2 - Rs 30,000 /- (Item - Maintenance)

Step-12:-

Generate material resource costs curve

Generate an activity wise cost report

Step-13:-

Create a reflection

Step-14:-

In the reflection, auto update the project at 15 days from start

Progress updated upto 15 days from start

Step-15:-

Open a TSLD view of the project in Visualizer

First go to visualizer from tool tab as shown below

Then select the type of visualizer

Now Choose TSLD from visualiser and select the project

Step-16:-

Add curtains up-to first 15 days of the project.

Find out the actual cost for labour, non-labour and material cost of the updated schedule

Now Go to Cost group Report and Click to Activity cost Report

Now Generate the Report

Result:-

I have completed all the mentioned task and I have attached Primavera P6 project file for further clarification

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.