Challenge

Project 2

Model & Design a Proposed PEB Warehouse using STAAD. Pro with following Technical specification.

Aim:-

To Model and Design a Proposed PEB Warehouse using STAAD Pro.

Procedure:-

Step 1:-

  • Open a STAAD Pro software and Create a File.
  • In Geometry Tab, Create Model using Nodes and Beam commands.

Step 2:-

  • In Specification Tab, Create and Assign a Sections for the Model.

Step 3:-

  • In Specification Tab, Create a Moment Release and Assign to the Gable End Columns.

Step 4:-

  • In Support Tab, Create a Fixed Support and Assign the supports to the all Columns.

Step 5:-

Load Calculation:

Seismic Load:

Zone Factor = 0.16 (Zone III)

Response Reduction = 4 (Ordinary Moment Resisting Frames)

Importance Factor = 1.0 (Category 4)

Soil Type = 1.0 (Hard Soil – As per Staad)

Type of Structure = 3.0 (Steel Moment Resisting Frames = As per Staad)

25% of Live Load on roof shall be considered for calculation of seismic forces.

100% of collateral load on roof shall be considered for calculation of seismic forces.

50% of (Live load + Collateral load) on mezzanine floor shall be considered for calculation of seismic forces.

100% of Dead load shall be considered for calculation of seismic forces.

Dead Load:

1) Self weight - Assigned to the entire structure as shown in the print screen given below-

2) Purlin - 10 Kg/m2 and 10 kg/m2 for roof sheeting are as per calculation and print screen given below-

= 20 x 6 (Bay width along span of truss) = 120 Kg/m2

= 1.2 kN/m2 on main rafter

&

0.6 kN/m2 on Gable frame

3) Mezzanine Floor – Load due to 230 mm thick and 4 m height wall around the periphery of Mezzanine Floor.

= 20 X 0.23 X 4 = 18.4 kN/m (on Both Mezzanine Floor)

Collateral Load:

On Gable frame - 2.12 kN/m

On Main frame - 4.24 kN/m

Live Load:

On Gable frame - 2.28 kN/m

On Main frame - 4.56 kN/m

On Mezzanine Floor - 4 kN/m2 or MEMBER LOAD = 6.8 kN/m on all secondary beams except end beams where load will be 3.4 kN/n (4 kN/m2 x 1.78 m (spacing of secondary beams)

  1. MEMBER LOAD = 6.8 KN/m on all secondary beams except end beams
  2. MEMBER LOAD = 3.4 KN/m on secondary beams at ends

Wind load:

Basic wind speed = 39 m/s

K1 = 1, K2 = 1.05 (Terrain category), K3 = 1, K4 = 1 (Cyclonic zone)

Design wind speed Vz = Vb x K1 x K2 x K3 x K4

= 39 x 1 x 1.05 x 1 x 1 = 40.95 m/s

Wind Pressure Pz = 0.6 xVz2 = 0.6 x (40.95)2

= 1006.142 N/m2

Ka = 0.8245 (for column)

Ka = 0.8 (for rafter)

Kd = 0.9

Kc = 0.9

Ka x Kd x Kc = 0.8245 x 0.9 x 0.9 = 0.68 < 0.7 so taking least value as 0.72

Design Pressure Pd = Pz x Ka x Kd x Kc = 1006.142 x 0.7 = 704.3 N/m2

= 0.704 KN/m2

Cpi = ±0.2

h/w = 10.05 / 60 = 0.1675

l/w = 170 / 60 = 2.833

External pressure coefficient for walls for rectangular clad building From Table 5 of IS 875 ( part 3) for h/w < 1/2 and 3/2 < l/w <4

Wind Angle

Cpe

Cpe

Cpe

Cpe

Wall

A

B

C

D

0°

+0.7

-0.25

-0.6

-0.6

90°

-0.5

-0.5

+0.7

-0.1

External pressure coefficient for PITCHED ROOF of rectangular clad building From Table of IS 875 ( part 3) for h/w < 1/2

Roof Angle

Wind Angle 0°

Wind Angle 0°

Wind Angle 90°

Wind Angle 90°

EF

GH

EG

FH

-0.86

-0.4

-0.8

-0.4

On Canopy:

Roof angle = 2.86 degree

Cp( -ve) = -1.08 (Uplift)

Cp (+ve) = + 0.35

Force on Canopy = -1.08x0.704x8 = 6.08 kN/m (upward)

Force on Canopy = +0.35 x 0.704 x 8 = 1.97 kN/m (downward)

For θ = 0° and Cpi = +0.2, Pd = 0.704 kN/m2, MF Spacing = 8m, EF Spacing = 6.75m.

Half of load acting in the Gable Frame

Surface

Cpe

Cpi

Cp = Cpe – Cpi

Wind force on frame

A

+0.7

+0.2

+0.5

+1.41 / +2.82

B

-0.25

+0.2

-0.45

-1.27 / -2.54

C

-0.6

+0.2

-0.8

-1.90 / -3.80

D

-0.6

+0.2

-0.8

-1.90 / -3.80

EF

-0.87

+0.2

-1.07

-2.99 / -5.97

GH

-0.4

+0.2

-0.6

-1.69 / -3.38

For θ = 0° and Cpi = -0.2, Pd = 0.704 kN/m2, MF Spacing = 8m, EF Spacing = 6.75m.Half of load acting in the Gable Frame

Surface

Cpe

Cpi

Cp = Cpe – Cpi

Wind force on frame

A

+0.7

-0.2

+0.9

+2.53 / +5.06

B

-0.25

-0.2

-0.05

-0.14 / -0.28

C

-0.6

-0.2

-0.4

-0.95 / -1.90

D

-0.6

-0.2

-0.4

-0.95 / -1.90

EF

-0.87

-0.2

-0.66

-1.87 / -3.73

GH

-0.4

-0.2

-0.2

-0.56 / -1.12

For θ = 90° and Cpi = +0.2, Pd = 0.704 kN/m2, MF Spacing = 8m, EF Spacing = 6.75m.Half of load acting in the Gable Frame

Surface

Cpe

Cpi

Cp = Cpe – Cpi

Wind force on frame

A

-0.5

+0.2

-0.7

-1.97 / -3.94

B

-0.5

+0.2

-0.7

-1.97 / -3.94

C

+0.7

+0.2

+0.5

+1.19 / +2.38

D

-0.1

+0.2

-0.3

-0.71 / -1.42

EG

-0.8

+0.2

-1.0

-2.82 / -5.64

FH

-0.4

+0.2

-0.6

-1.69 / -3.38

For θ = 90° and Cpi = -0.2, Pd = 0.704 kN/m2, MF Spacing = 8m, EF Spacing = 6.75m.Half of load acting in the Gable Frame

Step 6:-

  • Load Assignment and Load Combination creation and Assignment.

Step 7:-

  • In Analysis Tab, Create and assign Parameters to the Model.

Step 8:-

  • In Design Tab, Create and assign Design Parameters to the Model.

Step 9:-

  • In Analysis Tab, Click Run Analysis.

  • Output shows 0 Errors.

Result:-

  • The Proposed PEB Building was Modelled and Designed using STAAD Pro successfully.

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.