Project 1 Q1) What would the simplest work breakdown structure for this project? WBS ID WBS Name 1 Clearances 2 Design 3 Procurement 3.1 Civil 3.2 MEP Items 4 Construction 4.1 Sub structure 4.2 Super structure 4.3 Steel / Enveloping Works 4.4 Finishes works 4.5 External Works 5 Testing…
Mithun M
updated on 03 Nov 2022
Project 1
Q1) What would the simplest work breakdown structure for this project?
WBS ID | WBS Name |
1 | Clearances |
2 | Design |
3 | Procurement |
3.1 | Civil |
3.2 | MEP Items |
4 | Construction |
4.1 | Sub structure |
4.2 | Super structure |
4.3 | Steel / Enveloping Works |
4.4 | Finishes works |
4.5 | External Works |
5 | Testing and commissioning |
6 | Closure |
The same has been attached to the sheet.
Q2) Construct a project network by deciding on predecessors and successors for each activity.
Every activity has to have a predecessor and successor except for the start and end of the project activities.
The diagram has been attached to the sheet.
Q3) Identify constraints, dependencies and milestones.
Constraints: It is a condition that limits the progress toward the objective or goal. Constraints are limitations and restrictions. Every project has four basic constraints that are scope, time, budget and quality.
For the above project the below points are examples of constraints.
Sl.constraints | Constraints for the project |
1 | Design Input by the contractor (If not received at the correct time it delays all further detailed design and all the further activities) |
2 | Dislocation of local shops (If not cleared it affects the material delivery and construction activities) |
3 | Access release to the contractor (If not cleared it affects the material delivery) |
4 | Finishing the project within 5 months -( If not finished it will lead to liquidity damages) |
Dependencies/Activity Relationship
Activity Relationships are ordered links between 2 activities representing the order of execution. The relationship types are:
FS – Finish to Start
SS – Start to Start
FF – Finish to Finish
SF – Start to Finish.
FS – Finish to Start : In a finish-to-start relationship, a successor activity cannot start until a predecessor activity has finished.
SS – Start to Start : In a start-to-start relationship, a successor activity cannot start until a predecessor activity has started.
FF – Finish to Finish : In a finish-to-finish relationship, a successor activity cannot finish until a predecessor activity has finished.
SF – Start to Finish :In a start-to-finish relationship, a successor activity cannot finish until a predecessor
Milestone
A milestone is a specific point within a project's life cycle used to measure the progress towards the ultimate goal.
The milestones that can be considered for the above project are
Sl.No | Milestones that can be considered for the project |
1 | Start of the project |
2 | Finish of design work |
3 | Finish of structure works |
4 | Finish of all fineshes works |
5 | Finish of all testing & Commisioning |
6 | Closure of the project |
Q4) Ensure that every activity has to have a predecessor and successor except the start and end of the project
The schedule has been prepared and attached to the sheet.
Leave a comment
Thanks for choosing to leave a comment. Please keep in mind that all the comments are moderated as per our comment policy, and your email will not be published for privacy reasons. Please leave a personal & meaningful conversation.
Other comments...
Project 1
1) 1A) To select the right corridor for Kochi Metro, different possible options were tried.The three main options tried were Alwaye to Vytilla Kalamassery to Thripunithura Alwaye to Thripunithura Based on the expected ridership of the corridor, Alwaye to Thripunithura was selected. For this corridor, two-extensions…
19 Dec 2022 06:33 AM IST
Project 1 - Developing the Schedule for the “Construction of Police Station Building”
Project 1 Q1) What would the simplest work breakdown structure for this project? WBS ID WBS Name 1 Clearances 2 Design 3 Procurement 3.1 Civil 3.2 MEP Items 4 Construction 4.1 Sub structure 4.2 Super structure 4.3 Steel / Enveloping Works 4.4 Finishes works 4.5 External Works 5 Testing…
03 Nov 2022 04:28 PM IST
Project 2
Q1) & Q3) Aim: Develop the schedule after creating the new project, Create and assign resources Procedure: Step 1: Creating the project 1)Go to the Enterprise menu and click on projects 2)Go to the file menu and click on new 3)Choose the EPS node under which you need to create the project.(Same as that of project 1) 4)…
03 Oct 2022 10:04 AM IST
Project 1
Aim: To schedule the construction of a main school building (G+2) Procedure: Step 1: 1) Open the Enterprise tab 2) Select OBS 3) Click add and add the new obs as Project Manager Step 2: 1) Click Enterpriset tab 2) Choose EPS and click add 3) Rename the eps as Skill lync education 4) Assign OBS as Project manager…