Network Diagrams, Gantt Charts, Resource Plans and Budget Control
A free lesson from Skill-Lync's Project Progress Measurement and Reporting course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 3”
What will you learn in this free Project Progress Measurement and Reporting lesson?
The instructor reads a network diagram with ten activities, early and late start and finish times, and a sample Gantt chart with finish-to-start links. It then covers resource loading, budget with direct and indirect costs, earned value management, cost to complete, issue escalation and updating the baseline plan.
- Network diagram predecessors and successors
- Gantt chart with finish-to-start links
- Resource plan and resource loading
- Budget, EVM and cost to complete
What comes after lesson 3?
Later in Skill-Lync's Project Progress Measurement and Reporting course (paid): lesson 4, Week 1 Session 4; lesson 5, Week 2 Session 1; lesson 6, Week 2 Session 2. The full course has 49 lessons (19 h 34 min of video); see the course overview or its price and syllabus.
Lesson transcript
Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.
So next one is network diagram and Gantt chart. So this is an example of network diagram if you can see this. So there are different activities like A, B, C, D, E, F, G, H, I, J. Okay. And we have another two activities start activity and finish activity. So if you can see this boxes. So I have also represented the box here. So you can see. So the A is name of the activity and 5 is the duration of the activity if you can see the first box. Okay.
So your A activity, the predecessor to A activity will be your start activity. Similar in case of B activity, it has a duration of 4 days and its predecessor will be start. Now we talk about A. So successor activities for A are 3. D activity which is having duration of 4 days. E activity which is having duration of 6 days and C activity which is having duration of 3 days. Similarly, successor activity for B will be F, F activity which is having duration of 4. Now if you go further, so G activity will have predecessor as D. Also H, if you carefully see this H activity, it is having two predecessors.
One is D and one is E activity. And the duration for this H activity is 6 days. Now F activity is also same. It is also having two predecessors. C activity is one of its predecessors and B is another. So F activity is having duration of 4 days. Now comes your J activity and I activity. So J activity is having duration 4 days and it is having two predecessors. One is G activity and another one is H activity. Similarly, I activity is having duration of 6 days and it is having only one predecessors which is F activity.
Now these both J and I activity will have a successor activity which is finished. So if you go deeply into this network diagram, so this box represents once left side it will represent name, right side it will be represented as a duration. And we can also calculate floats also with the help of this network diagram by the use of if you see the EST, EFT. So EST is the early start time. EFT is your early finish time. Then below it is late start time and late finish time.
So we perform a forward pass and backward pass to determine a critical path that will be calculated and I will explain it in the next upcoming modules. So this is just a basic understanding of what the network diagram looks like. So basically it is a graphical representation that shows the logical relationships amongst the project schedule activities. In this case there are A, B, C, D, E, E, F, G, H, I plus finish and start. So network diagram is an arrow diagram like you can see in this slide which shows the interdependencies and the precedence relationship among the activities in the project.
So it is a graphical representation of logically and sequentially connected arrows and nodes representing activities and events of a project. So essential technique to construct a model of the project that includes the following. First one is a list of all activities required to complete the project like we have done in this slide. The time duration that each activity will take to complete like A is having 5, B is having 4 days duration. So these also we have done here. The dependencies between the activities. So these dependencies are shown by the arrow if you can see. Like I explained you in terms of the activities which are having 2 predecessors.
Like H activities having 2 predecessors. One is D and one is E. So that is represented by an arrow and this line. Next one is Gantt chart. So what is Gantt chart? So it is a graphical representation of all the activities against a time. So if you have seen in the right side of this slide you can see a demo of a project schedule. Okay. So in the left side where we have mentioned task name, duration, start, completion, predecessor. So this is a project timeline and schedule.
Okay. And in the right it is Gantt chart which is represented by a graphical representation. Okay. So here activities are linked by arrow. You can see the linking. So it is used as a planning tool in the project management. It gives a clarity on the project start and end date. If you take an example of task A in this chart. Okay. So it is you can see 9th May 2011. So it is starting on Friday. Okay. It is starting on Friday and it is completing on Wednesday.
So this Gantt chart represents the starting date and completion date. It represents the project tasks. The task start and task finish date. The task relationships. Like you can see the relationship between task A and task B. Then task B and task C. So these arrows are representing the relationships. The resources assigned to complete the work. It also gets clarified from the Gantt chart. So basically the Gantt chart is a type of a bar chart. In the Lehman language it is a type of bar chart that illustrates a project schedule.
So what is the purpose of the Gantt chart? The major purpose of the Gantt chart includes the. It is used to illustrate the relationship between project activities and time. It is used to provide a summary of the project tasks on one chart itself. It is used to illustrate project scheduling easily and simply. So by seeing this Gantt chart and this schedule it is not necessary that project planner has to be there. A simple person or a stakeholder who is not expertise of planning. He can understand by looking into this Gantt chart that what activity is completing when and which activities will start after which activity and which is the predecessor and successor activity.
So this is such a simple representation. So this is a real time example you can see on your presentation. So this is a type of MSP which is prepared. So if you see a project management work plan its duration is of 80 days. So it is starting on 27th of December 21 to 15th of April 22. So if you see upwards in the Gantt chart so it is mentioned by a line you can see. So next is initial phase it's for 13 days it starts from 27th of December and it will complete by 12th of January.
So this is also represented by a line at the right side if you see in Gantt chart. So these are the milestones okay. So these are not activities that's why these are not linked. So if you see the activities which are represented in Gantt chart in a blue color. So those are linked with the relationships. So next is next your milestone is the requirements gathering and analysis. So this is also represented by a line. Then we have activities below this defined process for gathering requirement. This activity has a duration of 1 day.
So this is also mentioned on the right side in a blue. So this is having a relationship of finish to start. So you can see after the completion of this blue line there is a link between the activity 4. This is document project stake interviews. So it is directly linked. Its start is linked with the activity 3 completion. If you are able to see and this predecessor column we have mentioned 3. So 3 means 3 FS. 3 finish to start. So document project stake holder interviews.
That is activity 4 it has a predecessor that is activity 3 and it has a relationship of finish to start. And it is having duration of 1 day. Then comes your next activity which is activity 5. That is analyze requirements. Its duration is also 1 day. Okay. And its predecessor is as it mentioned in the predecessor column is 4. So which is phone number activity document project stake holder interviews. And it is written 4 that means it is having relationship of finish to start. So whenever your activity 4 is going to finish then only it can the activity 5 that is analyze requirement can start.
So it is also represented here in the right side in the Gantt chart. Similar in the case of activity number 6 create requirement. Its predecessor is 5 with a relationship of finish to start. So that is also represented at the right side. So this is this is the way in which we can simply we can you know we can explain the what the schedule is. So people need to look at Gantt chart and they can easily relate with the left side of the schedule. So next one we gonna learn is resource plan.
Then what is the resource plan is. So basically resource plan it identifies all the resources which are required to complete a project. It contains all the resources types such as labor, equipment and materials. And also it provides the requirement in quantity and duration also. And finally you need to schedule the consumption of each resource with the project. So to prepare a resource plan following things are required. First is determining the resources needed for the project. Then we have to match the right resources to the right task at the right time.
Okay then we have to include the budget in the right amount of time for each resources. Then we have to schedule resources based on projected availability. So we cannot assign resource if he is not available like some resources already engaged in some other activity or some other project. So you cannot assign him. You have to check his availability. It also to prepare a resource plan we have to keep a track on project progress and also we have to expect to make adjustments. So these things are required to prepare a resource plan.
So what is resource loading an assignment? So actually to prepare a logical schedule it is very important to calculate, assign and commit all types of required resources. So resources can be manpower, material, machinery, equipment etc. to every activity in the schedule. That is why a schedule is incomplete till all the activities have resources assigned to them. Because that will give you actual tracking and actual progress update. So the proper and specific role and responsibility need to be assigned to all resources for completing the activities in the stipulated time frame.
So that is very important you know. So there has to be proper roles and responsibility which has to be assigned to all the resources. There should not be any confusion between two resources for one activity. So this clarity comes from your resource loading and assignments. So, as I told you earlier, resource assignment matrix also gives clarity in that in assigning roles and responsibilities for particular task to particular team member. Now, we will go to budget. Say, what is budget? So, what the budget is? So, it is the approved estimate for any project or work breakdown structure component or schedule activity is known as budget.
It is one of the most important constraints of a project that needs to be monitored and tracked regularly. You know, I have told you earlier that we prepare a pre-start estimate, PSE, against that budget has to be tracked in different phases with the help of CTC exercises. CTC means cost to complete. So, now, you know, project is feasible only when the profit margin is there. If the project is overrun, then it's very like unfeasible for a contractor to continue with the project. So, it has to be tracked. This constant is very important. So, this ensures profitability to the entity if it is under control.
So, if the budget is under control, then it is ensured that the project is profitable. It should not be overrun. So, the proper language if you talk about budget. So, it is the approved estimate for the project or any work breakdown structure component or any scheduled activity as I told you. So, it means the overall cost which will be incurred for its completion. It will include direct cost and indirect cost, fixed end variable, overhead, salaries, etc. So, what is direct cost? So, direct cost is the cost which is incurred directly in a project activity. Like it is a labor cost, material cost, equipment cost.
So, those costs are known as direct cost. And what are indirect costs? Indirect costs are like office expenses, your salaries, the overheads. So, these comes under indirect costs. If the project cost is more than the budget, the project is at a loss or we can say overrun is there. And if it is lesser, the project is profitable. So, it is very much prime responsibility of a project manager and project team to keep the project under your budget. And also, project should be in timeline. So, project health is measured with majorly two constraints. One is budget, another one is time.
So, if the project is in time and the project is in budget, then the project is doing fantastic. So, for calculating the project cost or a budget is within limit or not. So, we have many, many techniques in place which are agreed upon in the initial stage by all the stakeholders such as EVM, earned value management, where we rigorously track the budget and timelines with the help of your earned value, planned value and actual cost. So, which gives you fair idea, the cost is in under budget or not. So, this project manager has to ensure that. So, these exercises, budget controlling exercises needs to be done very periodically like CTC exercise, like cost to cost to complete exercises as a standard practice, all the companies used to perform it quarterly.
But it has to be done rigorously. And after every month end, there should be a cost report generated and it should be communicated to all the stakeholders. So, it will give you a fair idea at end of every month or every quarter that where your project is in terms of cost. So, a cost should be always be controlled and it should be within a budget to maintain the profitability of all the stakeholders and of the organization. So, these exercises are very much required by the project team and project manager to keep the project in track in terms of budget.
Now, we will see what the project execution and implementation is. In this phase, generally all the activities are executed with proper sequencing and proper action plan. So, if you see the execution model at your presentation. So, step there are four steps involved for this project execution and implementation. So, step one is we perform the tasks. So, during this all the activities are executed with the as mentioned in the project plan. Then second step is track progress. So, in this whatever activities have been performed. So, those are tracked against your baseline. And it explains and it tells you that the project is within timeline or it is delayed.
Or any activity particular activity is delayed and what reasons are there. The next step is manage changes. So, while executing and tracking. If project team finds that there are some changes in terms of time or scope or budget. Then the management of those changes has to be done during this step 3. Then comes your step 4. So, during the step 3 the team comes to know about all the changes related to scope, time and cost. So, those are analyzed first with the help of experts and other stakeholders and approve.
After the approval they need to be updated in the plan. So, a revised plan needs to be prepared. So, that is step 4. Then again again with the help of that revised plan and again the perform task. So, this is a cyclic process. And this is also part of a resolution mechanism. So, this execution model you we have seen the four steps which we will see in the upcoming slides. So, first step is perform tasks. So, it includes the actual execution of activities. All the activities as per the specifications which are mentioned in your contracts.
As per the GFC design. GFC design means good for construction design and drawings. Allotted budget with the help of all the vendors, suppliers, subcontractors and other resources. It includes all the executed activities shall be as per the quality and safety standards and adhered to the agreed timelines. So, while executing all the activities, the project team shall ensure that all the activities have been performed within the quality and safety standards. And for that generally there are checklists, there are numerous checklists for all the activities which needs to be followed.
And work method statements are there for each and every single activity. Those needs to be approved from all the stakeholders. And adhering to those checklists and those work method statements, activity needs to be performed. Suppose, I will give you an example of a casting of slab is there, casting of floor is there. So, there will be a pre-concreting checklist, there will be a checklist for reinforcement, there will be a checklist for your shuttering, there will be a checklist for pouring concrete. So, all these checklists needs to be signed from all the team members, client and also the work method statement needs to be followed for that activity.
It makes sure that all the activities are done as per the meeting the standards. So, all the standard and agreed checklist and parameters are to be followed before, during and after the execution of activity. As I told you, I have given the example of concreting. Then comes your step two. So, this is track progress. So, project performance in terms of time, cost, quality, scope, progress, etc. shall be tracked. And this tracking shall be done, I told you many times that this tracking shall be done very periodically.
If it is required weekly, it should be done, then periodically, monthly, quarterly, it depends upon the nature of the constraint which we are tracking. Suppose, time tracking is very essential. So, time tracking can be done daily on the basis of daily because, you know, schedule can be divided, can be broken into monthly targets, then monthly to weekly targets, then weekly to daily targets. So, that should be tracked with the help of DPR, that is daily progress report, WPR, weekly progress report, monthly progress report. And of course, if you track a cost, then it has to be monthly and quarterly because you cannot track your cost every day.
Why? Because the cost depends upon your invoice booking, bill booking, and that take place in once or twice in a month. So, that has to be taken into the consideration. So, cost, but time, in terms of time, quality, progress, it has to be daily and weekly basis, as mentioned in the standard procedure. They are then monitored regularly. So, these activities are monitored regularly with the help of various reports, records, communication systems, meetings, site visits, MRMs, monthly review meetings, PRMs, project review meetings with client, with senior management, quarterly reviews of cost, budget, time, quality, etc.
And weekly reviews. So, these reviews includes all the aspects of a project, either you can say scope, quality, safety, environment, time, budget, everything has to be part of these reviews. So, progress shall be monitored and tracked against the baseline schedule and budget that was agreed upon amongst all the stakeholders during the initiation phase. So, we had a pre-start estimate or a budget which was initially agreed upon, which like schedule also, which was initially agreed and accepted among all the stakeholders. So, those baseline schedule and budget needs to be followed and tracking needs to be done against them.
The next step is to report project progress. So, after the tracking and monitoring, so whatever conclusion is there, whatever status is there, that has to be transparently reported. So, it has to be reported through progress review meetings, PRMs, it can be with various stakeholders like your senior management, with client, your subcontractors, vendors, etc. So, project by also project reports such as DPR, which is daily progress report, WPR, weekly progress report, MIS, management information system, MPR, monthly progress report and four weeks look ahead. So, basically, what all things are included in these reports.
It will be including your labor report, your staff report, how many staff and labors are present, what all material is in stock, what materials need to be procured, what is daily activity planned yesterday, what is the plan for tomorrow and against that plan what we have achieved on this particular date, in this particular week, in this particular month. And it also involves your quality, best practices, safety best practices, if there is some, like if there is some injury or some accident happened inside, it should be part of those reports.
MIS, which is strictly for the management, senior management, it includes management information system, it includes each and every aspect of the project, it is monthly report. So, you have to report the progress, your cost, your budget, your next month plan, your cash flow, your next month plan. Next year plan, your billing, your invoice detail, so everything has to be part of that MIS, your progress pics, progress photographs, your 4 week look ahead is a plan of the next month, what you have planned for the next month.
If there was a lag in the previous month plan, then it has to be captured with the next month plan. So, these are the previous reports. Also, the budget which to be tracked through CTC, that is cost to complete, COC, cost of construction, PSE, pre-start estimate, etc. So, as we had, in the earlier reports, we have tracked the project progress. The budget also needs to be tracked on monthly and quarterly basis, as I told you earlier also, through CTC, your cost to complete exercises, your COC, your cost of construction, PSE, pre-start estimate, etc.
So, work done for the project to be monitored. So, work done means, whatever the work you have done in terms of amount and in terms of quantity, it needs to be monitored on the regular basis for tracking of cash flow of the project. By the help of this work done report, you will be able to know, your management will come to know that, what are your liabilities which needs to be begged or which needs to be billed yet, which you have, suppose you have taken a complete activity, out of which you have taken the bill from client, but you have not paid to contractor some amount of that.
So, that will be under your liability. So, those revenue, liability, cost will be part of this work done report. So, your management will be very well aware, okay, what are the liabilities, what we have got from the client and what we still need to be paid to the contractor. So, you know, project profitability and profit and loss statement will be depending on this work done report. Project progress review meeting, PRM. So, what all things are included in this. So, first one is review of action items from the last meetings.
So, whatever has been discussed during the last meetings, whatever commitments have been given by the project team in the last meeting, those needs to be reviewed first in the current project review meeting. Then, next will be the update on the activities and schedule. So, this currently, the difference, the time gap between the previous progress meeting and this progress meeting, there were some activities committed. So, those activities needs to be updated in terms of your cost, in terms of your time and it has to be incorporated in the schedule.
So, that will be the part of your progress review meeting. Then, next thing will be problem identification and corrective actions planned. So, suppose there are some problems which are like forecasted or which has already incurred. So, those has to be part of those review meetings and what all actions are planned or executed. So, those also needs to be mentioned in the progress review meeting. There has to be review of all the issues. Either it is closed or it is open or new. Any new which can occur in the future.
Suppose we are reviewing in the month of, suppose, May, the project review meeting we are doing this. So, we know that all the stakeholders know that there is a monsoon arriving in the month of June or mid of May. So, there has to be proper monsoon mitigation plan. So, this will be kind of issue which we need to, which the team needs to resolve and they should have a proper monsoon mitigation plan in action with their progress review meeting. That has to be discussed. Next is change request status.
So, whatever changes have been incurred or whatever changes have been identified from the team. So, their status needs to be tracked during this meeting. Like, are all changes incorporated in the change request forms or the working needs to be done. So, this gives a proper clarification in terms of your changes. Next one is risk status. So, there are many risk lists which are listed out in the risk reports. So, this status needs to be there like risks are open or closed. What are the mitigation plans for closing those risks?
What are the impact of those risks? So, that needs to be captured in this risk status report. Then, plan for the next period. So, plan of action for the next period like either it is next month or next week. Four week in terms of four week look ahead or monthly progress or quarter or full year. So, that also needs to be part of that progress review meeting. So, next step of the project execution and implementation is manage changes. So, it includes while executing the project. So, there are many changes and in terms of changes and variations in terms of your scope, time, budget, design, material, etc.
So, that can lead to the change management process at the project. So, before starting a project, as I told you earlier and we will study it later also. Okay. With this project management plan, when we are preparing the project management plan during the planning phase, the change management should also be established and agreed upon all the stakeholders. Because while execution of an implementation stage, if there are some changes, those needs to be managed, recorded and reported as per the procedure and the system, which already has been mentioned in your change management plan.
So, every variation or newly added scope or change should be regularized using a specific and standard change process that was initially agreed by all stakeholders and that constitutes a part of your change management plan and project management plan. So, this change management process includes change request forms which are commonly known as CRFs and variation orders post which existing order needs to be amended. Like, suppose there is a scope change. I will give you an example. Suppose there is a construction of residential building, ground plus one level.
So, the concrete estimated during the budget preparation and project management plan was 100 cubic meter. And suppose there is some change in design in a foundation due to which there is an increase in a concrete by 20 cubic meter. So, for that 20 cubic meter extra, we don't have any budget, we don't have any quantity in an agreed BOQ. So, it cannot be paid from client because 20 cubic meter we don't have. So, for that, a contractor need to raise a CRF, change request form, mentioning that due to this reason of design change, the quantity is increased by 20 cubic meter.
So, kindly accept and provide this quantity in our next amended order with this rate which was agreed. Okay. So, it may be the same rate, it may be the increased rate depending upon the time at what stage the change is coming. So, that needs to be amended and the fresh and new purchase order needs to be issued to the contractor incorporating these changes. Next part is addressing project changes. So, what all activities are included in addressing project changes. First of all, our team meeting needs to be arranged including all the stakeholders which are associated with decision making for the changes.
All have to understand the nature and extent of the change that what type of the change is it. Is it a quantity change, scope change or change due to design or change due to material specification. Then, during that meeting, we need to obtain feedbacks from all the team members and experts. Then, all needs to brainstorm and identify an alternative corrective options that what all actions can be taken to manage those changes. Then, a decision matrix needs to be prepared including all observations and opinions from all the stakeholders.
Then, commonly thus recommended options needs to be selected. Then, this communication for the changes needs to be done to upper management or customer for formal approval. Then, after the approval, the implementation for approved course of action needs to be done. Next step will be resolving the issues. If there are some disputes or miscommunications arose due to these changes, then these needs to be issues. So, all disputes, disagreements and uncertainties shall be resolved within time to avoid delays in the project and ensuring smooth functioning of the project through the following steps.
So, these steps we need to follow for proper dispute resolution. So, these all disputes and disagreements and issues shall be documented first. Next step will be an individual or a team shall be specifically assigned to address those issues. Okay. They will work upon jointly over those issues. This shall be scheduled for the resolution. So, there has to be a proper timeline for the resolution of those issues. It should not be open-ended. It has to be completed within time frame. Then, these issues shall be tracked and checked periodically and regularly if proper actions are taken for the resolution or not.
Then, after making the timelines and tracking, they shall be escalated through proper channel for timely resolution. So, this resolution technique should be properly escalated as per your communication plan and communication channel. Finally, these issues shall be resolved after passing through the above steps. After we have performed all the above steps of tracking, finalizing, identifying, binding them in a time frame, escalating them to seizure management. Then, these issues shall be resolved. This is like a proper matrix of how to resolve the issues. Many organizations have their internal dispute resolution teams or committees for quick and timely resolution of a issue.
So, what you can see in many projects and many organizations. So, initially, before starting the project, while identifying the project team, they depute some team members with the additional responsibility of this dispute resolution. And they are formed into an internal dispute resolution committee or a team. So, those are responsible for the dispute resolution during that project life cycle. And after these three steps of project execution and implementation, after the third step of manage the changes, now what we have to do next step is update the plan.
So, what comes under updating the plan? So, the baseline plan, schedule and budget shall be updated periodically and regularly whenever some changes are occurred. So, whenever there is method and it gets approved, then it has to be updated in the plan. So, the plan needs to be updated. So, these updates needs to be done only after the approval of senior management and all relevant stakeholders. As I told you, after the changes goes through a process, then they will get approved from your senior management client or relevant stakeholders.
Then only these needs to be updated with your existing plan. These amendments or changes shall be updated. and regularized contractually and made part of contracts. So while updating this project plan with these changes, so it should be contractually agreed and accepted and it should be made a part of the contract. Whether you can, as I told you earlier, we can issue a separate change order or a new and fresh purchase order incorporating all these changes. So that will be a contractual. It will be made part of the contracts.