Project Management Basics, Life Cycle and Process Groups
A free lesson from Skill-Lync's Project Progress Measurement and Reporting course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 1”
What will you learn in this free Project Progress Measurement and Reporting lesson?
The instructor defines a project and project management as per PMI and PMBOK, then walks through the life cycle and the five process groups from initiating to closeout. The lesson also covers the project manager's role and the documents kept in the project pre-plan, plan, implementation and closeout.
- Definition of project and project management
- Initiating, planning, executing, monitoring, closeout
- Role of the project manager
- Project pre-plan and closeout documents
What comes after lesson 1?
The next free lesson is lesson 2, “Plan Phase: Statement of Work, WBS and RACI Matrix” (18 min). Later in Skill-Lync's Project Progress Measurement and Reporting course (paid): lesson 4, Week 1 Session 4; lesson 5, Week 2 Session 1; lesson 6, Week 2 Session 2. The full course has 49 lessons (19 h 34 min of video); see the course overview or its price and syllabus.
Lesson transcript
Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.
Hi friends, the topic we gonna discuss today in the upcoming sessions is project management, progress measurement and reporting. So what is project progress measurement and its reporting? So project progress measurement involves determining and analyzing on tasks, activities and project progress in terms of timelines or schedule, cost or budget, quality, scope, etc. And this shall be reported, recorded in a standardized manner and communicated to all relevant stakeholders with the help of standard and agreed reporting systems and methodologies. So basically this is a part of communication management which is a process of project management.
So to understand that what is project progress measurement and reporting, we need to deep dive for the basics of project management, communication management and systems, monitoring and reporting system which we will cover in our upcoming sessions. So first we will start with introduction to project and project management in this week 1 part 1 module. So what is project? So project is a temporary endeavor undertaken to create a unique product or service. So this is a definition as per project management institute or PMBOK, project management book of knowledge.
So project is a unique set of coordinated activities with a definite start and definite end and it is undertaken by an individual team or organization to meet specific performance objectives within defined timelines or schedule, cost and performance parameters. So for introduction to project and project management, the following points are there which are covered in this presentation. So contents are project management, project life cycle, what is project management process and inputs, tools and techniques and outputs involved in this, who is project manager and who are stakeholders, what is a project plan, what is project notebook, what is a plan phase, what is a statement of work and what is its importance, what is a work breakdown structure and how it is prepared, what is responsibility assignment metrics, what is a project schedule, and how we develop a project schedule, what is a network diagram and Gantt chart, what is a resource plan, how a budget is prepared, what is a project execution and implementation, what is project closeout and some examples of project management.
So these are the topics which we are covering in this week 1 part 1 presentation. So after completing this week 1 part 1, we will be able to know that what project management is and the processes involved in it, what is a project life cycle, what is the role of managers and stakeholders of a project who are directly or indirectly associated with the project, what is a plan phase and what all things are included in it, what is a project closeout and how a project manager and team is involved during this phase, during handovers to client.
And some real examples of project management in our day to day life, what is project management, what is project management, project management is a very vast topic but we are taking the basics of it, so project management is the process of planning, organizing, directing, monitoring and controlling the activities of a project. So this definition is as per PMI and PMBOK, project management also includes the allocation of resources, so resources may be human resources, machinery, equipment deployed at a project or funds which are required to run a project.
So project management is the application of knowledge, skills, expertise, tools and techniques to project activities to meet the requirement of a project, any project undertaken should be technically feasible, economically viable and socially and politically acceptable. So project management is the coordinating effort to fulfill the goals of the project. The project manager as the head of the project team is responsible for all these efforts and its ultimate results or outcome. Project management uses their expertise, knowledge, skills, tools and techniques, methodologies to these following things. First project scope, so it is articulating the specific work to be done for the project, so it includes everything which needs to be done.
Next is second one is project time, so it is setting the finishing date of a project or completion date as well as any interim deadlines for phases, milestones and deliverables. So project time includes your completion date also and some intermediate milestone completion dates also. Project cost, it is calculating and tracking the project costs and budget. Project human resources, signing on the team members who will carry out the tasks of a project. Project procurement, acquiring the material and equipment resources and obtaining any other supplies or services needed to fulfill the project tasks or completing the project.
Next is project communication, conveying assignments, updates, reports and other information with team members and other stakeholders who are associated with the project. Project quality, identifying the acceptable level of quality for the project goals and objectives. So these quality standards should meet the specifications which are set in the initial stage by project owner. Next is project risk, analyzing potential risks and response planning. So next topic is project life cycle. According to PMBOK, a project life cycle is the series of phases that a project passes through from its inception to completion.
So project start comes first, which means inception, then comes your organizing and preparing, then comes your carrying out the work and at the last end of the project. So these four parts are there in a project life cycle. So it includes five processes out of which initiating process, it comes under project start, then comes your planning, which comes under organizing and preparing. Execution, it means carrying out the work, monitoring and controlling, it also comes under carrying out the work and then you are closing. So it is the end of the project.
All projects basically go through a typical life cycle curve. The project starts with the initiation or conceptual phase, then it passes through a planning or definition phase and then into an execution phase and monitoring and controlling phase. Finally, the work gets completed into a close out phase and the client accepts the project. So the project execution phase and monitoring and controlling phase accounts for major and most of the project resources with either it is human resources or a fund or cost. So it becomes the focal point of the life cycle curve.
In most cases, a single project manager or a team does not handle a project completely throughout the full life cycle. So many organizations have experts and specialists who develop the initial or conceptual phase and other specialists or team who handle the execution phase. The conceptual phase, which has majority of pre-construction activities involved, has research and development, market analysis, licensing and listening, finance and economics. The early phase requires a set of skills which are very much different from those required in the project execution phase. The life cycle curve majorly grows during the planning phase where design and procurement starts gaining momentum and it peaks during the execution and construction phase.
The major component of financial and human resources occurs during that part of the project. As I told you earlier also, during execution and monitoring and controlling phase, major and most of the resources are being consumed in terms of time, in terms of money, in terms of schedule, everything. That is also the time when the project master plan must be in place because all the pressure on budgets and schedules increases during that phase, especially during construction. So what is a typical project life cycle looks like? Projects are divided into phases as we have seen in this slide.
The project will have at least a beginning, intermediate and ending phase. Number of phases actually depends upon the complexity and size of the project and its scope. Many reviews are conducted at different time intervals and at the end of each phase to measure the performance against the baselines or expectations which are being set by the client or various stakeholders. These phases and reviews allows the stakeholders to decide if the project should continue or it should get nullified. So the collection of phases is generally known as project life cycle.
The project life cycle defines the beginning and end of a project. So as we have seen different phases are involved in a project life cycle. So we will learn one by one. So initiating process group authorizes the project. Planning process group plans the course of action to achieve the various objectives which are set during the initiation phase. Executing process group uses the resources to carry out the project tasks. Monitoring process group measures progress to identify variances. Closing process group it formalizes product acceptance and closure. Now is project management process.
So as you can see project management process. So these are different process groups. Like initiation comes first. Then Planning, Execution, Monitoring and Controlling and then Closeout. If you can see these three processes, we are planning, execution and monitoring. These are cyclic in nature. So first we will plan for an activity, then we will execute it, then we will monitoring it. During monitoring, if we found that the project is, there is some flaw or variance, then we again to catch up that, to mitigate the flaw, we will again plan, we will again execute and again we will measure, monitor and control.
Then after we are satisfied that the project activity has been executed as per the specification, then we will go to closeout phase. So what is there in initiating process group? So in this process group, we conduct cost benefit analysis for the project like we are preparing a business case. We determine and define the business needs and the project scope. So project scope is finalized during this initiating process group. We know the project boundaries and all the constraints related to that project in terms of political, social, socioeconomic and everything. We identify high level risks. We understand the required project organization structure during this process group. We estimate budget and resource requirement during this process group. We always assign a project management during initial stage. We obtain the project charter approval for this stage and we formally authorize to start a new project or phase in this process group.
So this is all about initiating process group. Then comes your planning process group. So in this project team determines how you will plan and develop the project management plan. How do we develop the project requirements in detail and agree the final scope. So final scope is agreed and communicated during this phase. We determine the required project activities. So we list out all the activities which are required to complete the project during this planning phase. With the help of this list of activities, then we develop a schedule using the estimated resources and the cost which is going to be incurred during these activities. We agree what quality standards will be met by the project and how. During this phase, we define how project staffing will be done.
We establish the communication requirements and how it will be fulfilled. We establish the communication requirements and how it will be fulfilled. During this process group, we identify what can go wrong and the plans to deal with them. We document what products or services will be acquired from outside the project, what we will outsource from the outside. During this process group, we gain formal approval and buy in feedbacks from everybody involved in the project. Either it is senior management and many stakeholders involved or client, everyone. So this is what about planning process group. Now we will go to next process group which is executing process group. So here we execute activities as per the project plan. We procure required project resources. We complete project work packages. We document what are the lessons learned by executing the activities or whatever risk or we have faced, whatever mitigation we have done.
So we document it as a part of lesson learned. We implement approved changes, corrective and preventive actions during this process group. We ensure processes are being followed at project activities. We hold team building activities and boost morale and efficiency. So during this process group, many morale boosting activities between team members are being organized so that the motivation of all the team members is high. We manage resource allocation and utilization during this process group. We hold progress review meetings and distribute progress reports. So during this process group, periodically, we keep on doing the meetings with various stakeholders, vendors, suppliers and we communicate what is the status of the project in terms of cost, procurement, contracts, etc.
So that all the stakeholders are on the same page. Project team keeps everyone focused on the project goals during this process group. This is all about the executing process group. Next very important process group is monitoring and controlling process group. Here we measure project performance using the documented technique in the plan. We identify variances and recommend corrective actions to get back on track. Here we approve changes. Here we approve changes, defect repair, corrective and preventive actions. We resolve if there is any conflicts and issues between the team members or with client or with various stakeholders. We manage changes to scope, time and cost. So whatever the variance and changes are there in terms of scope, time or cost, we manage during this monitoring and controlling process group with some defined and standard techniques.
We perform impact analysis to approve or reject changes. So whatever changes have been incurred during execution phase. So we perform the analysis during this phase. We obtain formal acceptance of deliverables or output from the customer and client. We monitor rigorously and periodically the status of risks and identify new risks have emerged or not. And periodically we also communicate these risks to relevant stakeholders. And also the team members. And also the team members performance is being measured during this monitoring and controlling process group. Now last but not the least closing process group. So here we confirm all project requirements are met. We obtain formal acceptance of product from the customer during our handing over taking over stage.
We hand over the completed deliverables to the operations team. We compile all the lessons learned which will be used for the future projects. We measure customer satisfaction. We measure customer satisfaction. We archive all the project data and documentation and information for future references. We release resources to work on the other projects. So these are the various process groups of a project management process. Now we will learn about manager and stakeholders. Project manager. So we have defined a project management and project. So now let's define a manager.
So if we talk about literal meaning. A manager is a person charged with the direction of an institution, organization, business or project. So you may call him administrator, executive, supervisor and boss. So at one time or another the project manager will perform all of those functions in executing the projector. Sometimes he will act as an administrator. Sometimes he will act as an administrator. Sometimes he will be as an executive. Sometimes he will work like a supervisor. And sometimes if he has to direct his team, he will be like a boss.
So project managers are an important component and play a very pivotal role in the functioning, executing and success of projects. Project managers engage in an exchange of numerous relationships with various members and stakeholders throughout a project. A project manager is a person who is responsible for the project and its success or failure, defining and managing customer expectations, coordinating the development of the project plan, monitoring and controlling the project work according to the approved plan, communicating the status of the project by preparing status reports, conducting progress review meetings, establishing and following a change management process, leading the project team.
He is a project leader, resolving the conflicts between the team members. If there are some miscommunications or conflicts or issue between the team members. So it is a prime responsibility of the project manager to resolve them for smooth functioning of the site or project, maintaining the project notebook, conducting a project closeout activities in which handing over and taking over takes place and in which clients accepts the product or deliverable, which has been delivered by contractor, maintaining and providing the historical data recorded and collected for future projects for future projects. This is also one of the most important responsibility of a project manager.
There are some more roles and responsibilities of project manager coordinating and integrating activities across multiple function lines. So there are multiple functions involved to execute a project like there is a contracts department, design department, there is a billing department, accounts department. So he is the bridge between all these departments. He defines and maintain the integrity of the project. He is responsible for development of a project execution plan. He is responsible for organizing for the execution plan. He sets targets and development of systems and procedures for accomplishment of project objectives and targets.
He is involved in negotiations for commitments from suppliers, vendors, clients and project members. He directs, coordinates and controls the project activities. He is also responsible for non-human resource management, including financial matters. He is responsible for management of personal, that is man management. He is responsible for management. He is responsible for management of cash surplus for project objectives and attaining the higher productivity. He is responsible for managing human interrelationships in the project organization. He is also responsible for maintaining the balance between technical and managerial project functions, coping with risk associated with project management.
So if we, if you want to know a very great example of project managers, so you must be knowing, so I'll tell you, so in our country can anyone complete the project within time and budgeted cost and that to a very large government urban transport project, which involves award of many contracts, land acquisitions and recruitments, right under the very noses of our top politicians, that is in our capital, Delhi. I am talking about Delhi. I am talking about Delhi. It was a very prestigious project in a capital city, a capital city, Delhi, and without any major traffic jams and demolitions.
Yes, I am talking about Mr. E. Shridharan, who has executed the most prestigious project of India. Yes. Thank you. Delhi Metro project in 2005. So the media have famously called him as a Metro man. You know, so he is a very best example of project manager and project management. So he has done his work with high integrity, single-minded commitment to work, managerial, acumen and punctuality. He has a very simple lifestyle and he considers works as a service to God. He creates a conducive and professional work culture amongst his team members. He motivates them. He pries them. Picking up the right people is also very important.
ability and potential of a project manager. This along with the freedom to innovate and no punishment for unintentional mistakes makes the employee put up their best show even with government salaries or less salaries. So a project manager can direct his team like a, you know, command team. Now we learn about project stakeholders. Who all are project stakeholders? Stakeholders are the people who gain or lose from the success or failure of the project. Some of the important project stakeholders are customers, clients, project project team, project team, project manager, project sponsor. So project stakeholders can be individuals and organizations involved in the project. They are those who will be directly or indirectly impacted by the project deliverables.
So stakeholders. So stakeholders should be identified throughout the project. It is very important for a successful project execution. They may have a positive or negative influence on the outcome. So project manager is very much, you know, he has to be proactive for identifying the stakeholders at every stage of the project. So stakeholder influence goes down as the project progresses. So highest influence of stakeholders is there during the initiation phase and it's very low during the closeout phase. So key stakeholders, they may include a project manager, customer or user, performing organization, project team members, project management team and the sponsor or financer. So project stakeholders or a team members are those who identify the work tasks which needs to be executed during a project.
They estimate the duration of work tasks by preparing a timeline. They help prepare the project network diagram and they are honestly reporting the work status to all stakeholders. They keep the project manager informed on project issues. They attend schedule progress review meetings. They raise issues which are very important to the project success. They keep their functional managers updated in addition to the project manager. They participate in the project closeout. So now we will learn what is project plan. So project plan is like a Bible to a project manager and the team or you can say it's like a Google map for a person who wants to reach his or her destination. Project plan is the roadmap of action for the project team. So all stakeholders should be in accord with the project plan like project plan has to be accepted and agreed upon by all the stakeholders and team members. So this is a fixed document forms which forms an integral part of the contract.
So project plan is a very important part of the contract which is agreed upon by client contractor and every stakeholder. Any changes in the scope or plan shall be agreed contractually by all the stakeholders. So if there is any change in terms of scope, budget or cost or schedule then it has to be recorded and it has to be amended and agreed upon contractually by all the stakeholders and recorded it should be recorded in the project plan. Then it results in the amendment of a revised plan.
So once the project plan becomes the baseline plan. Like once the project plan has been approved from all the stakeholders it becomes the baseline plan. So it serves as a benchmark for evaluating and reporting the project progress, project quality, project performance of the activities. So basically a project plan includes baseline. So baseline is in terms of schedule. Baseline is in terms of budget and cost. Then comes forecasts. So we have forecasts under this project plan like four week look ahead, three months look ahead, yearly look ahead, yearly look ahead cash flows.
It also includes periodic reporting like weekly, fortnightly, daily. So these type of reporting includes in the project plan. So it also includes change and change management. So it includes all the changes and how these changes are managed at project. Measurements, it includes phases, sequence of all the activities. It also includes risks. It includes resource planning and assignment. So this is all about project plan. So now we will learn about project management process. So if you can see on this slide, it's like a chart which I have prepared. So if you see there are three basic phases like first is plan phase, then comes your implement, then comes your closeout.
So and there are major four processes which are required to complete these phases. That is first one is project notebook, then your meeting, then reports, then lesson learned. So first plan phase includes forming of a project team, statement of work, responsibility metrics, network, can't budget, work breakdown structure and resource plan. So statement of work, if you know statement of work, it is a binding document that provides a description of a given project's requirement. It defines the scope of the work being provided, project deliverables, timelines, work location and payment terms and conditions. So these all are included in the plan phase.
Next come implement phase. So here we perform tasks, we track progress, we manage the changes, we resolve the issues and then we update the plan. So these five activities comes under implement stage. Then last is closeout stage. So we perform, we conduct closeout meetings, we share lesson learned and we evaluate the success against the baseline set during the initiation phase. So these three basic stages like plan stage, implement stage and closeout stage, this completes the project management process. So we will learn and we will deep dive into it activity by activity. So first is project notebook. So what is project notebook?
So it contains data and records for phases like project pre-plan, project plan, project implementation and project closeout. It also has documents related to project administration. So what is what all there in project pre-plan? We can also call it a pre-construction plan. So it includes background information or historical data of all the stakeholders, all the vendors and everything about project. Then it includes stage wise designs. So this includes CD and SD and DD. So CD stands for conceptual design, then schematic design and then comes your detailed design. So these stage wise designs are there in the project pre-plan.
Then customer, client or end user data. So this also is included in the project pre-plan. Then comes your third party data. So through all our third party, subcontractors, vendors, suppliers, etc. Next is project plan. So what is what all there in project plan? Statement of work, work breakdown structure, organization chart, responsibility matrices. So a statement of work I have already explained that it is a document that provides a description for your all projects requirement. It includes project deliverables, timelines, work location and payment terms and conditions.
Next is your work breakdown structure. So a work breakdown structure or in short, we can say WBS. It is a project management tool that takes a step by step approach to complete large projects by breaking down the complete scope into smaller components, which may also be termed as work packages. Next is your organization chart and responsibility matrices. Then your schedule data. Then comes your pre-start estimates or budgets or COC, cost of construction. So what is there in pre-start estimates? So it is prepared for a project in the initial stage when the contractor wins the bid.
So there is, against every activity, there is a budget assigned to it and that constitutes your pre-start estimates. So it's like a baseline budget against that your project will be measured in terms of costing. So against your PSE, your CTC, your cost to complete will be prepared every month and your project profit will be measured by this. Next is risk management. Now in project implementation. So it includes meetings including agenda and minutes of meetings. It also includes team, management, customer, third party, progress reports. It also includes customer change requests, decision matrix issue, resolution forms and reports.
Then finally project closeout. So final evolution of measurable success indicators are part of project closeout. It also includes your closeout meetings, agendas, minutes which involves the handover stages, taking over reports. Then your final project reports. It also includes your reference letters and all the lessons learned during the project activity or during the complete project life cycle. Those lessons learned are recorded during this project closeout. So project notebook also includes your project administration. So what all are included in the project administration? So first one is contractual documents. Next is invoices for all the vendors or contractors and expenses incurred at that project.
All the correspondences which took place during the project life cycle and the contact log. 整 that call Dob нормers. The Any�로 Court. The Any�로 Court. Go.