Construction Project Basics: Site Operations, Time, Money and Planning

A free lesson from Skill-Lync's Project Planning and Scheduling course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 1”

What will you learn in this free Project Planning and Scheduling lesson?

The instructor defines a project as a temporary endeavour with a unique product, using an airport trip and a 52-second tyre change as examples. The lesson covers site organisation, why time and money decide success, quoted causes of project trouble, and how a birthday party maps onto planning steps.

  • Definition of a project, temporary and unique
  • Site organisation and execution team roles
  • How planned duration and cost are linked
  • Planning steps shown through a birthday party

What comes after lesson 1?

The next free lesson is lesson 2, “Steps in the Planning Process: Phasing, Proactive Action and Guidance” (42 min). Later in Skill-Lync's Project Planning and Scheduling course (paid): lesson 4, Week 2 Session 2; lesson 5, Week 2 Session 3; lesson 6, Week 3 Session 1. The full course has 30 lessons (15 h 3 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Welcome to this session of Project Planning and Scheduling. Week by week, we will be taking you through a course of how the project planning and scheduling is taken up in the construction projects, which is a very vital, important part of the construction project management. This week, we will be taking you through concepts to delivery. The contents we will be covering in this week's session will be how the transition phase from the college to the challenges in the construction field are being taken up, what are the basics of the project site operations, what are the reasons for success and failures, and what are the basic steps of project planning, and what is a planning process called as, and how the steps in the planning process, and how the steps in the planning process are taken one by one, and then last, it compares in that whether planning can be considered as a rocket science, or it's really a simple science, or it's an art.

The key objectives of learning, what we will be keeping in mind through this session will be, what are the basic project site operations, how to determine the success and failure of a project, what is project planning, and why is it required, and basic steps involved in project planning. To begin with, let us think that anybody, any student, anybody who is taking up the course in the construction project management, really has to have a go through this transition phase, and these challenges. What is this transition phase?

You all must be in the colleges, you all must be in your different study fields, where that life and the professional life is totally different. You have the comfort of your home, or a PG, or a hostel, guest house, whatever way, that's a comfort you are having. I am not commenting on the complexities of a hostel life, or in the guest house. The point is this, there is a carefree attitude in your approach, and you are free to either bung the classes, manage your time as per your own wishes, and fancies, and requirements, and aspirations, and in the last, you can burn the midnight oil, give you 100% labor, manage the crisis, what you have spent time in some other works, and somehow get the grades, by doing that last minute preparation.

But, this construction field is totally different, there are extremities of the job conditions, now that disciplinary attributes what you are lacking in your college life has to be different. You need to reach the working place at a stipulated time, you need to perform something or the other as assigned to you in that particular time period window. And, now you don't have that easiness of getting somebody's help, and doing some midnight crisis management, because you lack that subject knowledge, which was very handy for you when you were in the college, but at that time, you thought that this subject is not much of importance, and you ignored it, and somehow just paused it, mugged it up, and got the grades.

But, when you come to the field, okay, this subject itself, which was taught in the second year, now is most important. Like, take the consideration of the civil engineers, the surveying part, the estimating and costing parts, getting taught in the second year or the third year. And, both these two things are the most vital when it comes into the construction project. So, people used to forget, well, because they are passing it out, and after that they realized, okay, that was taught in my second year, and now I have really switched over to the workplace, and what subject I have not taken seriously is the most important part.

So, these are certain things, which are the missing links, what we can say, which makes the people uncomfortable when they come into this transition phase. So, I am not making you all afraid, not to worry about, you have lot many options, you have lot many ways to succeed in this field. The first thing you have to keep in mind that, you need to have an adaptable approach, you should have a good grasping power, or you have that, and you need to inculcate that, you should have an interest to learn, that's the first and foremost thing, I think, or to say that, and then the willingness to cope in the long run.

If these attributes are there in your personality, or even if you are accepting this as an important part, then definitely, you can succeed in this. So, in summarization, what mostly goes wrong, the classroom studies and the field performance are altogether different ballgames. Then, plunging the right attitude and knowledge makes you disinterested. Lack of exposure on how project site works and the mega structures get built. That exposure doesn't happen in the college days, so that's why when you come to the construction project sites, you feel somewhat disinterested.

So, now, what can be done again? The curriculums need to be modified and adjusts lots of basic concepts of project management. Rather than the theoretical progress, MSP primary and all, there has to be the basic concept of the project management, step by step, much more on the practical learning, online and the virtual certifications for practical and trending courses to be explored, industry interactions and the guidance. So, this is how we are coming up with this, that we are trying to get this industry experience and the practical learning and sharing of the experiences and the modes and the ways what are being adopted at site in a course curriculum, that how the project planning, scheduling and the construction project management happens at the sites.

To begin with, the basics of the project site operations has to be understood by you all. Now, let us understand what is a project. The first question in your mind that project management, nothing much is being talked about on this. What is called as a project? Even if you plan your trip of a vacation to Goa or any hail station, that itself is a project. Even the smallest part, what you are planning to say that if you want to visit even from your home to your airport, you are planning it, it's a project.

Because the way you thought, okay, there is my flight is at some 5 o'clock. Now, the time is 12 o'clock. Okay, I need to pack my bags. I have already web checked in. So, my maximum time I can reach the airport, being evening hours flight is 3.30 or 4. I stay in so and so place, which is so much and far. And being a working day, that might have been traffic hassles. So, I will start my journey. I will leave my office by so and so time.

Take example as 2 o'clock or 2.30. So that I reach this midway. Some cross sections and some intersections will be reached. There you will decide which way to be taken. If that time you will see your watch, that if, okay, the watch allows you to go to the longer path or any shortcut has to be taken, you decide in the due course and then change that course or go in the same course and then reach at your time. So, that particular thing has got ended. The mission or the project task taken from starting from home and reaching the airport has been completed now.

You know, what is the smallest of the project and what is the biggest of the project? Biggest of the project, you can say space missions, construction project. There are some long lasting project duration. But there is a one of the smallest project which is having the smallest duration which can be called as a project. If you all can think it off, but being an online curriculum, I will just update you here. Formula car racing. Whenever the driver decides that he needs a vehicle change, a tire change, if you have observed that in your TV screens, how much time that the team assigned takes to changing that tire?

You know that? It is 52 seconds. In 52 seconds, the tire has to be changed because then the driver and your team will be out. So, that is also the minimum project duration. What I can visualize, there might be some way. 52 seconds, they change that project. It is a task. There are resources. There are teams assigned. There is a predefined way. He will flag it off. He will change that lane course. He will come into that lane. Things will be changed. The tires will get changed.

And flag it off. Then again, the driver is on the race. So, that is the project. That is also called as a project. So, what we call here is a project is a temporary endeavor that creates a unique product or a service. If you go with a theoretical definition. Why it is called temporary? Because every project has a definite beginning and a definite end. Recall your example of airport visit or a plan. A project ends when the objectives have been achieved. Unique product or service also you can call.

Because project involves doing something which has not been done before. It is not the case that it is something you are being discovering or inventing something. Not been done before means you have not traveled to the same course at that particular time. On a certain date, 8th May, 10th May, between 11 to 3 p.m., you have not traveled that. So, that is called as a unique because it is not done before. It is not the case that nobody has traveled on that road or you have not traveled on that road.

Point is it because at that particular time and duration, it is not done at that time. So, you are transiting at that particular phase as a first. That is why it is called as unique action. Because you might have driven from the same path yesterday. But at that time, there might not be any construction going. There is no diversion. But today, you are going and PWD is having a diversion and they are just averting the route. So, that is a hindrance. That is a new thing.

So, you do not know that. Now, the Google Apps are there. Google Maps will tell you there is a jam. There is a congestion. But it is fine that you might be traveling. But it is a unique thing for that particular day and time. Therefore, it is called as a unique. So, project is a temporary unique product or service which is having a definite end. So, that is why it is called a project. So, you can term it in a different way. But when you come to a bigger construction project organization, the things would totally get different.

Planning or a project with a small trip or airport visit or a vacation trip is... Different than planning and building an entire airport, entire highway, entire residential complex, entire mechanical industry, whatsoever name you call. The construction project management has different organization where the teams are large, where the involvement is more and where the collaboration and the stakeholders are, big stakes are being involved here. So that's being a different project site execution. So as a definitely temporary way to stand out alone for the things at site organization, I have mentioned here, as site organization have temporary establishments like your offices, spaces, your batching plants, labor colonies, stores, reinforcement yard, farm work yard.

There are certain ways of site organization where a particular sites are being observed. Then there are execution teams, which as in hierarchical structure called as to deliver that particular project. There are project leaders, there is a planning and technical department, there is execution engineers and foreman, there are safety and quality department, then there are accounts and administrative department. You will go through the transition of all these three departments in the entire course curriculum. Step by step, you will be understanding importance, relevance of every department, then how the entire construction project is being delivered.

So what is defined as success and failure of the construction projects? Just two, keep in mind, always in life in the construction project management phases, there are only two vital factors. What are those? Time and money. I repeat, time and money. Two important vital factors, time and money. See, those days have gone that when you keep on building a Taj Mahal for 20 years, 20,000 labors, keep on investing, rejecting a model. I don't like this black, I don't like this granite, I need a white marble and keep on reinventing the things and all.

But that's not the way, we are not in the era of kings and rulers and we have exuberant money. We are accountable to the society, we are accountable to the economy, we are accountable to any of the setup. So the most important factors are time and money because both are interlinked. How they are interlinked? I will show you a small snapshot on that. Like was I told, what is the definition of a project? Start, project has a planned time duration, project has a planned cost, project has a finish.

So there is a planned duration was this, okay. By so and so time this will happen, by so and so cost this should happen. What eventually happens, sometimes projects gets delayed, keeps on getting delayed, extended because of the other reasons, sometimes land handover, sometimes labor agitation, sometimes wrong management, sometimes lack of decision making. Actual duration goes, so automatically the actual cost also goes up. Now take a second scenario, there is a start, there is a planned finish, that was the planned duration. Now, if being a very progressive way of tracking, that now the pressures are more, that you have to finish that project into that particular time.

And if you have done a wrong planning of the cost, the actual cost will go up to meet the same end date. So now if you want to remain, the time is constant with the wrong planning, your planned cost definitely will shoot up and you will land up with a higher circle dia of the actual cost. So that's why the thing that why the construction project planning is very much important. If you plan well, then definitely you can act well. And when you are acting well, then definitely you have some better control on the outcomes.

So what is the influence from all these scenarios? In both the scenarios, the project performance parameters are not achieved. So let's see some statistical figures. Why the projects land into trouble? For the study done and then from tentative work have been shown by in some lot many construction curriculum print media, where you can experience that if you group with the feedback of the experience, that the project management problems contribute 32%, failure to define objectives sometimes 17%, lack of communication 20%, inexperience in scope and complexity 17%, technical issues 14%, sometimes technical issues do cope up because of some other wrong assumptions in the design criteria, then that these things cope up in, but that contributes somewhat less, but still the major contribution what we find is a project management problem.

Now, who is the major responsibility for this project delays? The stakeholder owners, owner, the client who is investing money or the who is putting up the capital or the contracting firm who is building that project or some other external factors, the major performance lies in the 34% is coming in the poor construction management. So our focus is that to have a skill set of people, which are what coming up into this field to have a attributes and skill set where we can attend to these incompetencies so that the entire construction industry is somewhat getting benefited with a much more edge on the deliverance.

What is then project planning? What you see that when the planning requirements keep on increasing, why they are so much important now? Because as you see that the complexity of the projects are getting more and more as the time getting changing, the complexity is getting increased. That's the way the symbolically it has been shown in the slides also. The complexity increases with the time. So the same, the skill and the requirements do also peak up. What skills that people were having 10 years back are definitely not the skills that the present pass out people should have.

They really need to have an upgraded version of the skill set. So that's the way that as the complexities of the projects get increased, the planning engineer's requirements is taking up its peak. So now what is planning? Why is they planning altogether a different ballgame? Is planning really a science? Is planning really an art? Is planning only some particular planning engineer's job? Or really it's something out of the word with this Western world and some new scholars have made it. And now they are making us to realize that really we really need to plan.

I totally don't agree with this statement. Because I will take you to the small basic example. Back to your kids days when you were small kids, some 8-12 years you can take at that age group. And considering the backward and not the modern times when you plan your birthday parties at some restaurants and some clubs. But there was a time then definitely and still there are a lot many percentage of people there who are kids that still they are planning their small birthday parties at their home with their mother and parents doing 95% of the job and some parties only getting back off-rooted within the market and all.

But it's key the mother is getting planning in the kitchen, the entire birthday party of the kid. So how mothers used to do that birthday parties? Mothers don't have any professional knowledge on the project management courses. Neither she had did MBA, neither she did anything. They might be educated but they don't have an additional qualification on this. But still they manage your birthday parties very well. So have you seen that what mothers used to do? If you recall that once you say definitely they will remember your birthday dates.

For example, your birthday is on 10th of the month. Take a month as January. Let's start to begin with. Take the month as the 10th of January. Your birthday lies on 10th January. You are making her remember that mom my birthday is coming. So I need to celebrate. So I wish to call all my friends. What is the first question moms ask? Moms ask that how many friends you are planning? How many friends you are projecting, you are thinking to call them? You will say some 10 or 20.

You keep note all these things, whatever questions mother is asking. These are the basic fundamental questions when you come to the project management. Mothers ask that how many friends of yours are supposed to come? Then she asks that have you any aspiration? Have you any wish list of the menu? Or in that category of the menu, how many are girls? How many are boys of your friends? How many are vegetarian? How many of non-vegetarian? What type of knowledge she wants to inquire from you? Whatever possible if you want to provide.

Okay. Then she starts doing her work. Now based on that menu and second thing all, she will also again ask one more question. That what is the time you are planning? Post school that evening hours you are calling. So that I need to plan a dinner for them. Or you are planning on a Sunday, any birthday party. So that I need to plan a lunch for them. So all these questions she will ask from you and she will definitely being mother. She will try to dictate that and she will try to say that this way it has to happen.

If you are in the consensus both then okay the birthday, day, time, menu gets fixed on that. Now her work starts. Based on that menu or based on the date and time she starts preparing her work. Like if you plan a dish that it has to be served on 10th of evening. Now she knows the recipe that particular dish something ingredients need to be soaked wet or cleaned one day before and kept in the freezer or kept in the underwater submerged. That she will woke up especially on 9th or take care before sleeping.

She will do that arrangements before your birthday date. She is doing that. She will soak that because with her experience she knows that 24 hours, 16 hours, 8 hours. She will do that and kept that ready on the 9th night itself or 9th evening itself. The 10th morning comes. In the morning she will allocate that what all menus the maid and the cook assigned will make. What all menus she will do. Anything has to be done from the external market has to be purchased. That work will be given to the father, the dad.

He will be assigned that okay bring so and so by this much time. Then according to menu the soup dish whether it is in house or whether it is an outsource. According to you might be given the task or some older brother of you. Those might be given the task okay but from that particular shop which is at the some corner of the city at so and so much time at 7 o'clock this is required order that place order and somebody has to drive that and bring that or whether it's a home delivery that all she does that and she starts preparing in that also she allocates the labor some chopping cutting will be done by some sister or the helping hand of her she will do the main basic cooking and that also she will categorize okay chapati is pudi or rice something has to be served hot okay so that will be cooked at 7 o'clock because people are coming at 8 o'clock some long lead items like vegetables are being cooked from 3 o'clock so all whole day she organizes herself delivers you the birthday party calls your friends coming in the she serves the very nice food welcomes everybody you all celebrate and went up and your birthday party is a very great success and you are now hit in your class that okay very great party you all gave to your friends so how that happened she doesn't have a planning skill but she managed very well what all she did she did she did the basic project management without any degree because she has developed a strategy she had a thought process based on the experience she has outlining the task she had accomplished the goal because she has scheduled what has to be done on 9th evening what has to be done on 10th morning what has to be done on 10th 3 o'clock what has to be done on the 10th of 5 p.m. what has to be served at 7 p.m. and how people will be welcomed at 8 p.m. she has scheduled everything and now she has accomplished goals it is a fundamental property of the intelligent behavior there is a basic definition of the planning please understand keep that in mind it is a fundamental property of intelligent behavior any task please intelligently think it over how you want to break down the task how the strategy has to be done give a thought process before jumping into the conclusion jumping into the preparation have developed that strategy that particular thing is called as planning a comprehensive plan have realistic view of expectation it will have a framework of operations it will have a financial perspective so now you link this slide what I am trying to explain here with what all the questions your mother used to ask in that example a plan enables a person to handle three basic principles of management what how and when what what to produce she asked you the menu how many friends are coming what do you want in the menu what do you want in the menu based on that how it has to be produced she decides when to perform on the night what has to be done on the 9th evening what has to be done on the 10th morning which hour people has to be located when to perform and enact these are what how and when the three basic questions in the construction management are being answered when we plan a project so when you take it as an organizational point of view it provides you the blueprint for the growth and success it's a road map towards a sustainable development development of the project and then in all together in a big company when you go all projects are having successful and definitely the company will grow so it's a sustainable development for the projects make the sustainable development of the company the planning connects the past experience to the proposed action for producing a favorable results in the future planning is a preventive measure to minimize negative consequences or unforeseen events reducing confusion waste and inefficiency so now again to recall that to make it easy to understand the essential components of the project management as what what has to be produced what is your scope remember recall that what she was asking how many people are coming what is the menu what this is called in the construction project management as scope define your scope what work is in your hand what all the things are the key derivatives you need to give then after defining the scope you really need to understand how it has to be done that means the technology what you are going to use this is the way when she decided which menu and as per that her experience because she has not it's a small kitchen it's a small organization you don't need all these additional efforts she knows with her experience what type of menu what technology whether she has to cook in the oven whether she has to cook in the gas stove whether she has to give something in tandoor whether she has to cook in the rice cooker she knows the technology she knows she knows the technology she knows that so but when you come to a project you really understand that whether you will go for a precast whether you go for a inside cast in c2 production whether you want to go for a outsourcement so that what technology you want to adopt for your delivering your scope then scheduling entire project has to be scheduled what product and what stage what when has to what happen that's called scheduling so it is called as when you are planning that particular thing to be delivered or to be acted upon so that's called as the scheduling which is the critical part of this week and the schedule module how much all these things will cost you something also which at the back end when you are planning a birthday party in the kitchen is being taken care by her as a monthly budget and the back side the father is being taking care of that so definitely you have to also keep in mind in the project management cost is very much important and vital to be considered now this is who who these is for whom you are producing for this and the birthday example case the who customer was the kid mother was producing the entire birthday party for the satisfaction here the customers are not the friends they are the national stakeholder what you can say they are coming for the enjoyment but the main customer who has demanded this customer is the kid here and now you can recall here the client gives you the who all uses that mall who all uses the residential they all are stakeholders but the entire customer is that who is putting the money who is having the wish list sometimes the government is there here in this case the small kid was the small kid was the customer of the mother that i want a birthday party of mine to be celebrated at home see the example of a palm all the five fingers are important and where these five and people are fingers are getting closed is on the palm that is why why and where this is called as what is the intent of the project what are the key attributes and attributes and goals what we are aiming for and where it is getting acted upon the locations also the geographical locations of the country geographical locations of the city geographical location of the project also changes the entire other there might be a steam weather conditions or cost limit go up the resources might be different the scheduling will be different because it's why and where is also very important so and how who is controlling all these five fingers and five fingers and the wrist and palm is your wrist so that the wrist is being placed at the strategy position so now as a planning professional these strategies are being made so that you can control all these five fingers when to close when to open so the strategies are being important for that strategy you really need to have experience you really need to have a skill set either adopted externally or with gaining experience or with sharing experience or adopt and adapting courses to learn from the practical knowledge where you learn from the practical knowledge where you can really understand that how all these five fingers are working as essential components of the project management so what I want to show here is that if you are failing to plan you are planning to fail means that if you really are not coping up with your work and if you are not giving a full concentration in developing a strategy in developing a plan in developing and breaking the entire structure into a different time management windows then definitely you are planning to fail a comprehensive plan does not guarantee success but lacking a sound plan will definitely ensure failure so lack of the plan will result in poor execution of the plan is that eventually results in time and cost overruns customer dissatisfaction project loss to competitors now to summarize this it's very important and crucial and crucial and crucial here to understand it's not the case that everything planning has to take care the point is it if you are really planning it well that means if you have any strategy if you have an approach where you really understand what's your scope that where you are working or whom you are working who is your client what is your geographical location what are the key external factors influencing that particular location what is your key derivation what is your scope what all activities you have to deliver what are the methodology for doing that particular job like if you are driving to an airport if you take an auto if you take a motorcycle if you take a cycle if you take a hand rickshaw it all depends upon the time factor how much you are having left to reach that airport and even also the geography I am telling if your location is congested with jams and all definitely you will ask your friend if you have one single bag okay you help me out to drop me at the airport because he can maneuver between the traffic jams but if you take a cab if you take a cab or if you take your own car you can't driving to the congested roads of the city so that depends what methodology you are planning what approach you are taking up so that really depends and drive your end result if you are really taking a congested road of any city and the market in the peak hours you are planning to reach airport and you start from your home very late and you want to maneuver and reach airport time definitely you will your flight is going to get missed because you are getting struck up in a jam but at that time if you have taken a methodology of taking your calling your neighbor or your friend with on a bike as a pillion rider you just hold your back and he drives across the zigzag with all the maneuvering around the jams and makes you reach to the airport so that depends on how you are planning it Geography of the location, planning, sequencing of that work, what action you are taking are very, very important because unless and until you really foresee, I am not telling you can foresee anything and everything at one particular time.

But whatever maximization you can do on that, remember that line, fundamental intelligent behavior. Intelligently really need to think it out, what all things has to, where I will get struck up. If you really chalk that out in your vision, then definitely you can chalk that out in the paper. Then any of the software you can use, BA Primavera, BA Microsoft Project, Excel, whatever way you want, you really need to understand and develop the fundamental concept of this project management that why it is being done, how it is being done, whom it is being done and where it is being done and at what stage it has to be done.

Then the softwares are there to facilitate and help you out to manage the complexities. It's said for activity job, you don't need an MSP Primavera to plan your trip to a vacation. You don't need a Primavera or software or MSP software, MS Microsoft Project software to plan your trip to the airport. But when it comes to the construction project, because there are thousands and thousands of activities involved. So definitely you need a software help. So but fundamentals and the concepts remain same. And in the fact that you will find that once you start doing this, then definitely your deliverance level, your productivity level definitely keeps on goes on a upward vertical scale.

As soon as that grows up, it's not only as an individual you will grow, you will start contributing to any of your organization, even to your own startup, even to your own as an individual, then definitely the growth is unstoppable. So now once it comes to the construction planning at site, we will try to find that to link the all these previous slides and the additional explanations and examples what I quoted for you all. So that how this construction planning at site is being achieved when you take up a project and construction projects are altogether different as compared to any of the medical industry, factory production, construction projects are very unique in nature.

So that the same concepts has to be planned out, you really don't know external weather conditions, how the things are going to implement, even the different of geodemographical surveys and all still how the earth will react after you start your excavation work and the foundation was you really particularly can't predict that to the 100% efficiency. Things might go here and where, so that is the thing that construction planning at site is a totally different ballgame, but all these concepts and approach has to be kept in mind and definitely step by step you are trying to achieve a successful planned approach for any construction project.

So to summarize in a theoretical way, the construction planning at site can be said that how would the planning of the activities systematically to achieve the target within the given time frame economically with high quality and utmost safety. Keep that in mind, keep that in mind once it comes into the project field from your college days, the last words which are the high quality and safety, this is utmost important. All the companies and organizations are very much professional and now we are accountable and answerable to the human safety and the quality of life and the quality of the product what we are being supposed to deliver.

So quality and safety comes hand in hand and that goes with the projects, that's why it is being also mentioned separately and it is being highlighted separately, but still along with the line that it is part and parcel of the activity that whatever you do, it has to be under the safety standards and high quality because human lives are very important. And when it comes to mega projects, this quality and safety standards are really, really need to be high being in the design parameters, being in the execution parameters, because any compromise on this of your actions will definitely can land into disasters.

So this is the first change in the attitude once it comes into the field that now you are unanswerable and accountable, every action of yours might impact others in the team. So you need to be accountable. So that's why I am again emphasizing activity systematically to achieve target within given time frame economically with high quality and utmost safety. Now, what is the objective of this construction planning? It ensures the good practices that we have are following uniformly in the respects that our procedures, modalities of work are transparent and become known to all concerns within our organization.

See, what happens that when you do the construction planning and we go in an organized way and when you go in a systematic way, so as a planning engineer man, he tells that this is the planning way, this is our project plan, this is the way I am doing. So it's called as a communication, that is nothing like a secret, the planning will have the data with its own people and they will not share. And because anything is communicated, the communication flow doesn't happen. So construction planning has to be there, it has to be shared because every down the line people from who are supervising your work, they need to know the schedule, what has to be delivered, what are my quality standards, what is to be done, when it is to be done, when it is to be done, when it is required, how my actions are depending and affecting others.

They really need to understand, so there has to be a formal procedure set up and that has to be formally shared and that has to be formally monitored as a construction planning process, which really needs to help the entire people in the organization to have a transparent approach of work. Thank you.

Want the rest of Project Planning and Scheduling?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Project Planning and Scheduling course

The remaining 27 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Project Planning and Scheduling course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.