Direct and Indirect Costs: Item Rate Analysis and Worked Examples

A free lesson from Skill-Lync's Project Cost Control course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 3”

What will you learn in this free Project Cost Control lesson?

The instructor compares two ways of presenting cost to a client, a three-part summary and unit rates, with a gypsum board item rate analysis. Direct and indirect costs are then contrasted for a house and a factory, including rough ranges of 80 to 90 percent direct and 10 to 20 percent indirect.

  • Cost summary versus unit rate presentation
  • Item rate analysis for gypsum board installation
  • Direct versus indirect cost examples for a house
  • Four differences between direct and indirect cost

What comes after lesson 3?

Later in Skill-Lync's Project Cost Control course (paid): lesson 4, Week 2 Session 1; lesson 5, Week 2 Session 2; lesson 6, Week 2 Session 3. The full course has 38 lessons (17 h 57 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Hi friends, welcome back. So we were in the discussion mode for week 1 introduction to project cost control. So we will continue with the cost explanation of when we were talking about direct cost, indirect cost and the design cost, the various associated cost in the project. So as a representative, how do we represent in the market or how we represent to the our customer or as a contractor, how we represent. So there can be two samples like sample one is if we are claiming. So as a contractor side, if we are claiming, we claim to our client as three components. One component is direct cost, second is indirect cost and third is the design cost.

And another sample is like sample two claim is direct as unit rate with hidden indirect and design cost. So here to say indirect and design cost cannot be given away with it. It is only like the ball may be in the contractor's court or in the consultant court or on the client side. But those costs are very much associated with the project. So we will see in more detail. So we will see in more detail how this cost can be representative in detail. So here is sample one cost summary wherein we clearly announced all the three components to the client.

This is like if you can see, this is like if you can see, we mentioned the sample format here, a project name, say ABC project or XXX project and here is the cost summary. So first is component A, direct cost. So we have eight components of this wherein what all tangible items we can see and we can visualize. We can calculate in terms of quantity and unit price each. That is in detailed BOQ we can prepare and submit. For example, foundation works, superstructure works, electrical, firefighting, HOAC, plumbing, interior and all other costs.

So such costs are called direct costs and here is how we represent them. Then moving forward, another component, the B section indicates the indirect cost, which is like a temporary expense, a general expense or the statutory compliance expense. Then finally the C part design cost is like the architects or the MEP design fee or the authority approval fee. This is kind of representation and it is also used like in a lump sum projects from the client to the contractor. Then the contractor gives us lump sum breakup, say foundation. It might be the requirement of the contract whether to submit the detailed BOQ or not.

However, so based on the contract condition, the document is prepared and submitted. So further this could be split into say foundation works, there is a detailed BOQ, say how much is the excavation, how much is the form work, how much is the reinforcement work or how much is the concrete work or else only the foundation work, there could be a lump sum. So that calculation can be kept as a secret with the contractor for his inner works and not shown to the client. So this is how the sample one like overall picture of representation of direct, indirect and design cost is done.

And of course, taxes add to it and form the grand total cost for the project because these without these costs, the project cannot be executed. So hence we announced clearly all these components for the client. So this is another example of direct unit rate. So like an or an item rate analysis. So we have like for each particular item, we submit there is a BOQ and we submit the quantity and the unit price. So here the quantity is either given by the client in the form of the tender documents calculated by either the client or the consultant or any other third party or also the contractor.

So we can see here, this is a sample example of an interior finishing item, say 12.5 mm single layer gypsum board fixing installation. So supply and installation. This is an item rate analysis on how we derive at a unit price. So in this, what I want to highlight is there are several components like the material component, the material cost of what is the supply of this gypsum board, what are the accessories required? For example, the screws or the jointing compound or the glass fiber or the backer road and all those materials or I can say in order to do this job, what all things I need to procure from the market are all comes under the number one heading material.

Number two is installation. Now I have brought the material. And in order to install this material, how do I mark it so that I can count this much cost is required, say material handling charges, scaffolding or shuttering charges or any other equipment charges or the installation charges. So installation charges basically include the number of workers who will be required and based on the productivity, how much is required. Then indirect costs. Now we see the detail on this indirect cost, how the indirect costs are calculated. I'll go one by one. We can see indirect cost A is on site wastage first, which is wastage of material, say 3%.

So first point I want to say is this percentage is might vary from item to item and also from project to project. There will be several conditions. So this is just a sample and this percentage is not to be taken as a standard mode of measurement. Then another is tools and plant charges. So what all tools or equipments which are likely to use, for example, a screwdriver or a drill machine. So you will you need to buy that or you need to repair that or you need to invest some money into that.

Then comes the electricity distribution cost. Of course, for working, you need some electricity power, then water charges, then safety charges. So what is safety charges? Safety charges is like the kind of PPEs, the personal protective equipment that are being provided to the workers or the staff. For example, the helmet, the safety shoes. So all these come at a cost. So that is kind of indirect costs which are hidden. So for that particular item, gypsum board installation, there are so many indirect costs hidden which are on site.

And another component of that is off site, which is like site establishment charges. So if some worker have to perform a work on a site, then they have to move to that site. They have to arrange some accommodation. They have to bring their office or they have to bring their tools or sundries, something like this. So they need to basically establish the site before they start work. They simply cannot just start the work. We contact them and please do this gypsum board and they simply just start.

So they need to see the site, survey the site, do some set up, basic set up before they can start the work. So that is how what we call a site establishment charges. Then another is administration charges. So it's another indirect component cost, which is like there are several components to it. So the worker comes and they need a toilet. They need a drinking water to drink. They need basic facilities. They need some some tools. They need some store to manage. They need some compliance documents. The next is contingencies, which is like emergency funds, which are assumed that this much risk factor is there.

Then overheads, then overheads, finance charges, and finally the contractors profit. So, so on and on. So this is one of the sample component of a item rate analysis. This need not be submitted to the client unless and until asked for by any contractor. So what I want to highlight here is like as we did the sample one, which was basically split into three cost only direct indirect and it is kind of lump sum contract and sample two is like direct unit price based contract. So there will be a specific BOQ. So in this like 12.5 mm single layer gypsum board. So that will be one particular item and such several items would be there in the contract.

So for each of those items, the contractor is required to fill up the unit rates and then submit to the client. And here lies the importance that once we are required to calculate the unit prices. So such kind of rate analysis as shown on your screen, this will be quite useful. So you can do it in house as a trial basis. And I would suggest all of you who are able to see this course or attend this course must try out this for some sample exercise.

So we will now start to compare and discuss more about this direct cost and indirect cost. These might be little confusing. So in order to clear the concept and clarify the direction here on your screen is the sample examples what components constitute the direct cost and what components constitute the indirect cost. So let's see here like see direct cost is like the labor wages. So all the workers involved in the project, those are the labors. So that cost, what are the costs associated with their wages? Like their direct salary, they may be paid daily basis or they may be paid on the measurement basis.

Say if they are going to do the reinforcement, they made, there might be a specific unit price, say 6,000 rupees per ton, which has to be paid. Or also there could be a wage rate of say 500 rupees per day for each worker on site plus overtime. So that is one of the direct cost. Then number two is like wood, glass, cement, any material which we buy. So these are like sample material examples, most common in the construction industry. So whatever we buy, that is part of direct cost. Then some hardware, handles, locks, hinges or any other raw materials.

So anything what we buy, like material and labor, that component are as like direct cost. Then we have the indirect cost example. There will be several examples like the advertisement cost. Say if you are running a real estate project and a residential project in the upcoming metro city and you want to really sell it, then there will be some advertisement cost associated with that project. So if you want to advertise, you want to advertise your name. You want to advertise your name. You want to advertise the consultant's name or the owner's name in the near vicinity so that if any more project is coming up, people might like to see your project site and offer you more job. So you will put up some signage or a big banner board outside your project and focusing on that. So some cost is associated with that.

Then the project management cost. So there will be several management staff over there or there has to be some kind of royalty that has to be given to the parent company. This project is being executed. So in order to manage, we need your help of the parent company, say a monthly basis or a weekly basis. So that kind of costs are associated. Operational costs. So the day-to-day operations. Say for example, if we are running a site office, then a very simple thing, we need a printer to run our office. So someone need to print and someone need to take care of the documents.

So that kind is the operational cost. Or we say for the site office, we need the electricity or the air conditioning to be running for the staff can sit and work on. Then insurance. So for any construction project, definitely insurance is being taken. So normally it is also called as contractors all risk policy, wherein everything is most of the things are covered. So again, depending on the company policy. So this is again an insure example of indirect cost. Then coming is the next is the depreciation.

So of course, whenever there is a project being executed, you are having some of the assets at the site. The simplest example I would take is, say the laptop or a desktop, which any staff is using in any project. So before this project, there can be again two cases. Suppose first case is, we buy this laptop new in this project for say 50,000 rupees. And once the project gets finished after six months, you transfer it to another project. So you cannot get back 50,000. Maybe you have to add some depreciation value and say you transfer it at 40,000. So this 10,000 becomes your depreciation value, which cost is being borne by your project.

Another example similarly could be, you did not buy a new laptop, but you are using an old laptop. Say you paid 40,000 to another project. Now for the next project, you are going to transfer it at a 35,000. So in this case, this 5,000 depreciation cost, this will be called as indirect cost and loaded to your project. Such kind of indirect cost. So all this, what we shown are just basic examples for you to understand the concept and visualize what is direct and what is indirect.

There will be several more examples coming up in this course as we sail through. So now we can just look at this like, you consider the, you are constructing your home. Then as in sample exercise, what are the direct costs and what are the indirect costs associated with you in this project? So I will pause for a while for you to contemplate and then we take it further. Say if you are constructing your house coming back. So what is the direct cost involved in this? Say cement, of course, without cement, that is one of the raw material, the electrical cable or the air conditioners, or if you are not installing air conditioners, then some fans, then the paint material, which you will be using on the walls or the worker who would be processing this material and then converting it into your house.

So these are some of the examples, which are involved in other examples for direct costs while constructing your home could be like say floor tiles or some sanitary fixtures or some curtains or interior finishing. If you are involved, which are involved or the fascia, the glass, the windows, the doors, so there are several components of the direct cost and direct cost here to say constitute the major component of the cost. We cannot define the percentage since it's quite difficult, say around, but roughly around in the range of 80 to 90% of any construction project is the direct cost.

It will vary. There will be several factors which are not so easy to define. Once you get experience, you can understand those. And here, we continue with the indirect cost associated with the construction of your home. So like if your house falls on the public road, then you need to do some safety, you need to take some safety measures to arrange some barrication of the public road. Of course, you don't want to harm your neighbors or disturb your neighbors while you are constructing. And definitely you don't want police coming to you and complaining you and putting you behind the bars.

Then the worker hutment. So these might be a small thing, but without this, the construction will not be possible. Say for example, like your workers, when they are coming to work at your home, so where will they be staying? So say they are doing 9 to 5 job at your work. So from 5 p.m. to 9 a.m. where they are staying? So is the hutment provided at your construction site or is the hutment provided nearby or the transportation facility is there? So that all constitute the indirect cost.

Then the temporary electricity. So until and unless you have the state electricity board permanent power connection, you need to run some equipments during the construction. So that maybe you might be using a diesel generator set or you might be using another source like an inverter or borrowing it from your neighbors or there could be several other methods by which you are arranging the electricity. So the point is electricity is required and there will be a cost which is which falls under the indirect cost. Then the soil investigation. So that is required for the design of the foundation.

So how deep the foundation should be? What should be the size of the foundation? So this basically how much the soil can carry the capacity of the soil to carry the load of your house, especially required when you are constructing a multi-story house, say a four-story house or a three-story house or a five-story or say a 10-story building. So that of course depends on the money you have. So herein we can see like I believe you can all easily associate this cost in your minds like while you are constructing your home because you all would have surely seen if not experienced by your own some or the other house being constructed in front of your eyes.

Maybe it could be your friends or neighbors or your own. If it is your own, you can very well imagine this kind of direct and indirect cost. Then we move on little further and we take another example like we list out the direct and indirect cost associated with the construction of a factory project. So now please understand why this is being done, why it is kind of repeating or kind of more detailed comparison among direct and indirect cost. Because for any, we are talking about the project cost control and these are the most basic concepts of the cost control.

So if you have the concept of direct cost and indirect cost is very, very clear in your mind, then the confusion will be negligible or zero confusion in the future. And you can understand the further concepts more easily if you get confused in what is direct and indirect, there could be trouble in the future. So that is why we I am doing kind of repeating and explaining you in more detailed manner for a factory project. If we talk about an industrial factory project, which is say located 100 kilometers in this rural area of a metro city.

So here, what could be the direct cost? So these direct costs could be like a concrete material. Or if the concrete is not being supplied there, you are manually making it on site, then you need some raw materials of of course cement, sand, aggregate and water. Without those, you won't be able to do the concrete works. Then the rebar supply or the reinforcement or also called the TMT bars. Then the concrete and rebar laying cost, including the workers and the tools. So this is like the labor wages again.

So if you compare this direct cost versus the direct cost of your home, this is the same thing. There is no difference. The basic thing to remember here is direct cost is like material component and the labor component. And now we talk about the indirect cost. Indirect cost for an industrial factory project like construction of a temporary entrance gate and an excess road to the site. So the industry might not be very small. So you need to have some inside vehicle access and define some roads wherein the movement can happen.

Even the staff may not be very small. Even the staff may not be able to walk from the boundary wall. So they need some car or some another vehicle to go in through the site office. And you need to develop a site office. Then site office and furniture where the site team can work, sit and operate the project. Then of course electricity and water. So here again to emphasize like indirect cost of factory project or your house project is the same. The percentage of indirect cost will vary. The nature of the indirect cost will not vary. However, there could be several components depending on the project.

So if it is a house project. So if it is a house project, the indirect cost will be less. Factory project indirect cost will be higher. But it is always calculated as a percentage of the total project cost. So again to say the indirect cost could be around 10 to 20 percent roughly on an average for the projects. It's something close by. So how the difference is there in between the direct cost and the indirect cost? So let's see what all differences are there. So number one.

Direct cost is there. Direct cost is easy to determine considering the scope. Indirect not easy to identify. A detailed analysis is required. Why so? The main reason is direct cost can be easily visualized. We can see in front of our eyes what is required. Say we want to build a building. Then of course the foundation is required. So what kind of foundation? We can refer to the designs. So once we go to the designs. So once we go to the designs. Then we can calculate volume and the quantum of the work. Once the volume and quantum of the work is there. We can put a price to it and calculate it. Indirect cost? Not so easy. For say for this foundation which are required. We can visualize foundation is required. But there are always assumption factors like how much workers will be required or how much material will be required.

There might be 10 foundations that are required. There might be 10 foundations that are to be constructed. And two foundations while constructing might be defective which you might have to dismantle and recast. So these two foundations this alpha you cannot assume when you are estimating on the originally. Of course you can estimate those 10 foundations and understand how much cost is going to come. But those two foundations you cannot estimate. So that is why this indirect cost is not so easy. There has to be several permutation and combinations. And hence I say a detailed analysis is required.

So direct cost is quite attributable to clearly to a particular scope or an activity. And indirect as the other way to multiple project activity. So for this direct cost we talk about particular scope. We say a carpenter working. He is only working for a shuttering activity. And how much square meter he will be giving the productivity. And how much square meter is required for a particular project. Then we can definitely understand. And we can calculate the direct cost. Now considering a project engineer. He will not only take care of shuttering work. But he will take care of multiple jobs. And multiple workers assigned to him. Say the reinforcement works. Or the concrete works. And as well as the excavation and the soil works. So from that. That is how this indirect cost. So that's the staff salary or that engineer salary. Is attributable to the multiple projects activities. Then continuing with the third difference. The variable cost that change based on the quantity. So if the quantity of any activity is varies. Then the cost will change. For example. If the concrete volume is changed. The quantity will variable cost will change. If the quantity doesn't change. It won't change. But in a project there will be certain variation.

In the quantity. Why? Because before the beginning. Why? Because before the beginning. There are several assumptions. And that is only an estimate. That is not actual. It could be very close to the actual. But there could be some differences. Indirect cost is normally fixed cost. Then number four is. Direct cost of course directly proportional to the project progress. So the percentage of the project executed. Say 50% completed. Then that means 50% volume entails this 50% of the cost. The indirect cost. The indirect cost might be independent of the project progress. It might be dependent. And it might be independent. So for example. The 50% of the project is executed. But for the balance 50% you need more manpower. You need more machineries. You need more things. To finish that project. So then that is not directly linked to the project progress.

So it is not. We cannot say that is directly proportional to the project cost. So in a nutshell. To say like direct and indirect. There might be some overlapping also. And could create a chance of confusion. But if you go through all these data and information once again. And think carefully. You can easily identify. You can easily identify. The direct cost versus the indirect cost. Involved here. So moving on further. For this session. So week one. We conclude this session. With this kind of summary here. So what we have covered. In this week one. Information. Is. The importance of the project cost control.

So not only. So not only for the construction industry. But as well as the entire economic scenario. If you can remember. Or recollect. We considered it. We compared it. With the entire country's budget. Or the state's budget. Or any organization's budget also. So it's. And any project control process. Is an ongoing one. It never finishes. Until and unless the project gets finishes. So as the project is on. The project control process. Is continuous one. The frequency could be different. But it has to be a continuous one. And it doesn't require extensive economic or business acumen. We don't need a sharp knowledge. And I am quite confident. That your fresh brains. Or what you are trying to understand.

You can easily learn. You can easily learn. From what I am teaching. Or you already know. What the more. From what I am teaching. Then. What is required. Is only a basic knowledge. Of income and expenditure. So this basic knowledge. Is. That there will be something. Incoming into our pocket. And of course. Something outgoing into. Out from the other pocket. So it's a two way channel. Incoming and outgoing. It's not like a row traffic. But it's like a money. Transactions. Which are happening. Which are happening. Then. Then. The process involves. The cost estimation. Budgeting. And controlling. Which are the key words. As. Explained to you earlier. Then this also. We. What we covered was. The project's health. How. At a pre-decided time. We can understand. The project health. So as we are. If we go to a doctor. And carry out. Some diagnostic test.

For say blood test. Or. Say blood test. Or. An other test. ECG. Or anything. So at a pre-decided time. We can consider. And know. The project's health. And also. We can understand. What variance is there. Or. What is the difference. Between plan. And actual. And that is why. We can take. The right. Next action. After analyzing. The due. Situation. Of the project. And it keeps. The. All the stakeholders. Posted. At various stages. Of the project. It helps them. A lot. It is. Not. Actually. The numbers. But it is. The money. Involved. For the stakeholders. And it can be carried out. By the project team. Or the project support team. At the HQ. Or the regional office. So there are. Several ways. Of doing it. Either the project team. Itself. Does it. Or the HQ team. Does it. Or the regional office. Does it. So. But it has to be.

Done. And controlled. That is how. The project cost control is. So here. We conclude. And. Looking forward. To see you all. In the next week's. Session. Thank you very much. Have a nice time. Thank you very much. Thank you very much.

Want the rest of Project Cost Control?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Project Cost Control course

The remaining 35 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Project Cost Control course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.