Planned vs Actual Cost, Who Controls It, and the Cost Types
A free lesson from Skill-Lync's Project Cost Control course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 2”
What will you learn in this free Project Cost Control lesson?
The instructor shows why actual cost drifts from plan, using a 90 lakh budget that ends at 95 lakh, a 5 percent variance. The lesson names who is authorised to do cost control, then introduces direct, indirect and design costs with earthwork and brickwork examples.
- Variance between planned and actual cost
- Roles authorised to carry out cost control
- Direct cost: material, labour and equipment
- Indirect and design cost components
What comes after lesson 2?
The next free lesson is lesson 3, “Direct and Indirect Costs: Item Rate Analysis and Worked Examples” (30 min). Later in Skill-Lync's Project Cost Control course (paid): lesson 4, Week 2 Session 1; lesson 5, Week 2 Session 2; lesson 6, Week 2 Session 3. The full course has 38 lessons (17 h 57 min of video); see the course overview or its price and syllabus.
Lesson transcript
Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.
Hello friends, welcome back. So we will continue with the session 2 for week 1 of project cost control. So here we will be starting to talk about the relevance of cost control to the construction, which is of prime importance and quite useful in terms to all stakeholders. So one question comes to the mind is, why the cost control is required? So as you can see on the screen, this bar chart, a typical Gantt chart in a construction industry, which represents some milestones and versus what is actually happening.
So here we can see the difference between planned and actual. Say we had planned something, but actual is there is always some discrepancy. Actual doesn't happen or doesn't go in line with what we had planned or envisaged originally. So you can see the dark brown lines as planned duration and the actual is the dark blue color, which is like there is a delay in terms of timeline if we are talking about or if it's the bar lines are about the volume or the cost, then actual is increasing.
So we can of course see the pictorially that there is a difference between planned versus actual. So another question what comes to the mind is, in order to reach a goal, if we have set up a goal, is actual always same as planned? Now here you need to think about your own lives and your own instincts, like what you had planned in your life. Is everything happening as per your original plan? If you have interest, a little interest in Bollywood movies or Hollywood movies, does everything go as per plan? Whatever a villain plans, is he successful at the end of the movie or is there the hero wins?
So that is how the importance and the relevance of project cost control comes into picture. There is a difference. So that difference, so here we are to understand that difference and to take certain actions which are beneficial for us as well as for the organization to counter attack or to counter all those to take counter measures against this discrepancy. So again, this slide is explaining the same thing, but in a different manner. So there is a planned cost. Say, suppose there is a project worth 1 crore and the budget estimated for that is 90 lakhs.
That is the planned cost. And actual cost incurred is 95 lakhs. Or in the middle of a project, say the project is 50% completed and we calculate the forecast and the forecast comes to 95 lakhs. So there is a variance or increase in cost of 5 lakhs. So that 5 lakhs is not a small amount. If we talk about percentage, that will be 5% of the overall project, which has a huge economic sense. So what we need to do? So that is where the project cost control comes into picture. This differential cost of 5 lakhs, which is 95 lakhs versus 90 lakhs. So this 5% difference, we need to understand why this has happened.
So this why is very, very important. So we need to go into the root cause and analyze the reason of increase of this 5 lakhs. So once we understand this reason, only then we can take the correct next action. So here I also want to highlight, we should not hurry and we should not take shortcuts to understand the reason of why. Because if we understand it wrongly, or if we take some shortcuts, we just take it for granted. We might take actions, but that might not be correct actions. So in order to ensure that our next action is the right step, the right foot we are putting forward, we need to really go to the depth of the problem and understand why this 5% discrepancy is coming and how can we minimize it or how we can counter this 5%.
Suppose we understand and we find out, yes, there is no way we can save this 5% increase in cost. Then our action could be, how do we get this extra 5% from our client? Or if we are an investor, then how do we report this additional 5% to our management so that we can seek additional budget? Or we can also, there are many other ways which you will understand during the course of this project or this session and this course. So another important aspect is where the cost control is required. So is it applicable to only certain projects or only certain construction industry? If I talk about the overall view, yes, it is required as an overall scenario.
If I talk about the nation or a country, yes, cost control is required. You might be well aware of the annual budgets which are drafted and laid down and announced in a financial year in India. Similarly, a statewide budgets are there. Similarly, each organization has some budgets. So this is how the economy is moving. So there is something planned expenditure and something actual expenditure that happens. So here we are to talk about the construction. So if we talk about the construction, there will be several types of projects that are happening.
So say if we talk about residential project, say constructing your home or say constructing a commercial residential project, the cost control is duly applicable. If we talk about industrial projects or say factory projects, the project cost control is equally applicable. What is common in both of these things is there is a set amount of money which is being invested and how much we are going to incur and there are several stakeholders who are spending this money and who are using this money to execute and giving the final product to the ultimate owner.
So that is why this cost control is required. So that is why this cost control is required in both these aspects. So here are on your screen two more aspects where the cost control is required. So this is just a major glimpse. Like if we talk about high rise buildings, which could be commercial building or a residential building again. And also like multi-use buildings like with an hotel or a shops or market or complex or shopping mall or a mixed condomium type of usage. And another is like government infrastructure. It could be a government based or a private equity based.
So in all the sectors of the construction, anything, if you think about construction, then the cost control is required. The basics are the same. It doesn't mean that for a high rise, the project cost control is a different way to calculate or an infrastructure project. It's different or a factory project. It could be some other way. No, all such project, the basics are the same. How much we are getting, how much we are incurring and how much profit margin we are giving to the company. So there are various tools which can be used to quantify the cost.
And as an owner, say if you are the owner of a particular project, you need to understand the project status in terms of cost. So you had envisaged one crore and three months down the line, you understand that already 30 lakhs the money is spent and it's gone in the execution. And you already have some half finished or partial finished project in your hand. So then you also need to evaluate. Yes, the money is 30 percent is gone, but has the progress been really 30 percent?
So that balance as an owner, we need to evaluate and check about what is in your hands or what is in front of your eyes and how much you have spent from your pocket. And of course, all the stakeholders, as mentioned earlier, like the consultants, the contractor, the client, the owners, they need to understand the variance. What is the difference between the plan versus actual? What is the current scenario of the project? And as rightly said, like the timely check is quite important to take the right actions.
And those two are the right time, because if time, the right time has gone, maybe you cannot take any action. You can always say, oh, if I had known this, then I would have done like this. So that if word is quite dangerous to say, so hence timely check is quite important. So we should notice this points like the tools and the current project status, the variance and the timely check. Then coming to who should carry out cost control. So is it like everyone involved in the project can carry out cost control?
The answer is no. Everyone involved in the project cannot do the cost control. The same is the manner like everyone in the project can do construction thing. No, like it's the say, for example. It is only the messons or the workers who can lay brick by brick and carry out the construction. So they cannot do the cost control or an engineer or the project manager will not start to lay the bricks by his own hand. He has designated workers to do that. So that is their role.
So hence in a project we have certain key staffs who can take care of this cost control. So they have a certain degree of education. They get a certain degree of training on how to do this. And only they are like authorized partners for the cost control in a project. Nevertheless to say the cost of any project is a confidential part. So it also cannot be disclosed to all and sundry. So that is a key word here which needs to be taken care. Like it is quite confidential for a particular project.
Normally for example a contractor simply cannot disclose what percentage profit he is earning from this to each and everyone involved in the project. So hence we have some authorized persons to carry out the project cost control. So who? So number one is the custodian or the guardian of the project. That could be like the owner or the investor of the project or the key planning manager for an investor. Or we can also say the consultant. If the owner is not technically sound or not financially sound.
He can hire some expert consultant in this field and he can take care. Then number two is the project manager or the director under whose directions the project is getting executed. So again the project manager or the director could be either from the owner side or from the contractor side or both. So here we need to understand there are different different roles. So as an investor always the project manager will try to save the cost. And as a contractor the project manager will of course try to save the cost for his company.
But he will also try to increase the inflow from the investor so that he can try to give more profit to the company. Then comes to the planning engineer and the cost controller. So these are the key staff. These are the actual staff who is working on the cost. So they are the persons who are actually like keeping an eye on the procurement status or on the execution status or working on the how many percentage of the project has been completed and how much is balanced.
Or through a series of formulas and said guidelines they are calculating what is the balance work due and how much is the forecast money to be spent. Or they are into the market and understanding the nitty gritties of each and everything. So that is how the construction industry works and that is here hence with what and who should do this project cost control. So now we talk about the associated costs in a construction project. So in order to understand the project cost control deeply there are some of the fundamentals which we learn need to learn before.
So that when we are talking about cost control we understand the keywords which are getting used and how the things are moving. So hence this is a small brief to make you understand what are the costs that are applicable to a construction project. So simply to say there will be three types of costs. Say direct cost, indirect cost and C is design cost. So this will be like the differentiation or the category might vary from organization to organization. But once I am sure once you understand the basics for any organization there might be different breakups.
But you can easily get a strong hold on all these topics. So what do we mean by this direct, indirect and design cost? So direct cost is something like tangible or what we can really see with our eyes. Indirect cost, indirect cost as the word says. Though the cost is there but we cannot really feel it or it's kind of hidden costs or not directly applicable to the project. And thirdly the design again as the name indicates. So it is related to the design of a construction project.
As you are aware, no project can happen or be executed until and unless it is designed. So there will be an architect, there will be a structure designer, there will be a mechanical engineer, there will be an electrical engineer. So all those are required to ensure that the design is done. So we will talk about all these three costs in a little detail in the next slides. So here we see about the direct cost. So that's a tangible items of the project such as all the contracted items in terms of say material supply, labor, equipment or the machinery utilized in the project, etc.
So this is like all anything which can be directly allocated to a particular scope. For example, if we talk about say earthwork for foundation or steel structure or brickwork. So these are all direct costs which are clearly visible. So most important component in a project cost is material. If we don't have material, we cannot construct. Second is the labor. So if we don't have labor, of course the engineers are not going to construct. So we need to have this labor. And for the labors, we of course need to have some tools, some equipments, some machineries.
Suppose for an easy example of machinery or equipment is, say we need to work on height, say we need to cast, do a concrete of the roof at 3 meter height. Then of course we need the scaffoldings or we need the ladder to go up. So if labors are not equipped with that kind of equipment machinery, we cannot do. And if we don't have the raw material, say concrete or the plywood for shattering or the reinforcement, then we cannot do the casting of the slab. So hence this material supply in terms of plywood or reinforcement or concrete or the raw materials for concrete, say, very simply to say cement, sand, water, aggregates or admixtures as and when required.
If we don't have, we cannot. And finally the labors. If there are no labors, definitely we cannot do. So this is how the few examples which you can see, like earthwork for foundation. So first and foremost, if we are making any new building or any infrastructure project, we need to do some earthwork. We need to do some excavation. We need to do some backfilling. We need to do some disposal of soil. So until and unless we start with this soil work, we cannot start the project.
So there is like for each soil quantity, there are certain aspects, say for excavation, there is a certain quantity, for disposal, there is a certain quantity, for backfilling, there is a certain quantity, same case may be applicable as and when for the steel structure, brickwork, plaster, some electrical items, some HVAC, so and so on. So how these direct costs are estimated? So can we simply say this direct cost is like simply, yes, XYZ multiply X or we multiply length, breadth and height and we calculate the volume?
To some extent, the answer is yes, but we need to have a thorough examination of all the contract activities, of all the construction method, the site conditions and the available resources. So for example, a residential project in location A versus the same residential project at location B, the cost might be different. Why? Let's say the soil condition is different. At location A, the soil condition is all black cotton soil. So we need to excavate, complete, remove that or we need to do some treatment to that black cotton soil and then move on.
And then if we talk about location B, the condition of soil C is fully rocky. So there is hard rock and not even weathered rock and we cannot simply lay the foundation on the substrata. So we need to do the chiseling of that rock and go into the depths to raise our foundation. So herein, like even though the design of the residential project might be same, but of course the foundation design will vary at both the locations A and B and hence the construction method will vary and hence the cost will vary.
The volume of the soil or the volume of the rock is the variance and hence there will be a different estimation. So it's also directly related to the project's productivity and progress output. Say how? For example, if we calculate, we take an example of brick work. So we, as a common industry practice, we calculate, we assume one mason, one worker will lay 500 bricks per day. So is that 500 bricks really happening at your project or not? So all the assumptions go into this and the direct cost is calculated.
Say brick work unit of measurement is cubic meter. So you will calculate the labor. The component of the cost assuming 500 bricks are laid in one day and then you calculate something like this but if the actual is say only 300 bricks then you will be at loss but actually if you are able to manage with 600 bricks or something anything more than 500 definitely you will be in on the profit side so that is how the things work and that is how it is directly related to the direct cost so quite important from this point of view so this is what is meant by direct cost overall so this any construction project will of course involve the building works which can be like to say RCC reinforced concrete structures or the steel or the interiors the doors etc so all this is applicable then infrastructure say the roads the drains or the utilities the electrical works what kind of electrical panels are coming what kind of electric cables are coming what kind of electric cables or what kind of light fixture you are installing all this is involved in a construction project like if you only construct the brick walls of your house see just imagine your master bedroom having only the brick walls so you cannot switch on the light you cannot switch on the air conditioner then is it or you don't have any furniture you just have a raw floor you just have a concrete raw floor you just have a concrete raw floor which is dusty and muddy can you really use that I don't think so so that is why this building infra electrical and mechanical these are quite important and until unless you use them you cannot understand then moving on to indirect cost so so far we learned about direct cost now we are moving on to indirect cost so these are going on to indirect cost so these are going on to indirect cost so these are like any site related expenditures that cannot be explicitly assigned to any single project activity so like an interrelated expenditures that are happening we can also say these are like back end and support activities which are termed as indirect cost it can also be like called as fixed or variable in nature there could be differential or we basically cannot easily identify this indirect cost costs so how do we classify to understand we can classify this as a general expense or a temporary expense or a few other categories like a contingency or overheads and talking about few examples like all the staff salaries or the accommodation related to the staffs the transportation the laboratory testing all these can be termed as part of the indirect cost so it is quite imperative for you to get this noticed that all these expenses are not so easy to calculate and not so easy to forecast at the beginning of the project so as we talked about it is simply not a length into breadth into height so in but in order to have a cost estimation or to quantify we need to assume something and there are several assumption factors factors which may or may not happen really so here as we learned before planned versus actual so that discrepancy can easily come into picture here so which we need to understand moving on further the C part involves the design cost see what all contents go into the designing of construction project so how do we design and what are the various stakeholders involved which are on your screen here like number one is the architect so any construction project design starts with an architect so that architect will of course Levi he will not do a job free of cost then comes the structure designer who designs the structure the foundation or the RCC structure or the slab design then number three comes the MEP design fees the mechanical electrical plumbing say firefighting facilities or the electrical transformers and how the power will be distributed what size of cables have to be considered then any government authority approval then any government authority approval that is required or any third party consultant any expert opinion we need over a period of time in the project so that is also quite important so we might need some help of any some third party consultant so all these five rules are just an indication of what kind of design costs are involved in a particular project however each project could have different design aspects and different cost associated with it so broadly here we talked about the associated costs which are to summarize like the direct cost which can be easily seen and forecasted and calculated number two is the indirect cost which is non-tangible and slightly difficult to assume and we really need to pay attention to those indirect costs as well we simply cannot ignore those indirect costs and finally is the design costs thank you very much