BIM Project Lifecycle, Clash Detection and Information Requirements
A free lesson from Skill-Lync's BIM in AEC Industry using Revit course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 2 Part 1”
What will you learn in this free BIM in AEC Industry using Revit lesson?
The lesson covers the six stages of the BIM project lifecycle, from pre-design to as-built. It explains early clash detection between disciplines, what counts as true BIM, and the roles of EIR and the BIM execution plan including file formats.
- Six BIM lifecycle stages
- Clash detection across design disciplines
- Why a model must update across all views
- File formats IFC, RVT and NWC in the EIR
What comes after lesson 3?
Later in Skill-Lync's BIM in AEC Industry using Revit course (paid): lesson 4, Week 1 Session 2 Part 2; lesson 5, Week 2 Session 1; lesson 6, Week 2 Session 2 Part 1. The full course has 37 lessons (18 h 6 min of video); see the course overview or its price and syllabus.
Lesson transcript
Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.
Hi everyone, welcome back to part 2 of introduction to BIM in AC industry. In the previous session, we covered all the basics like what is BIM, what it stands for, what B stands for, what is I stands for, what is M stands for and the significance, all those things we covered in the previous session. In this session, we'll be covering all the trends, adoption rate and the life cycle, case studies, all those things we'll be covering in the session. Just get started. BIM Projects Lifecycle. So, BIM Projects Lifecycle is divided into six.
Pre-Design, Schematic Design, Design Development, Construction Documentation, Construction Stage and Aspil. In the pre-design stage, all the initial discussion like the contract, BIM Execution Plan, all those things will happen in the pre-design stage. All the information like the site acquiring, the other relevant details. Then comes the schematic design part. Then the design development, the structural, architectural, all these team members join together and make the designing part. And in the same stage, like all the BIM engineers, all these people will also take part and they start with the modeling effort.
And once it's done, then the construction documentation like drawing creation, then other information like scheduling, estimation, all those things will happen in the documentation stage. And once the documentation is done, like all the BIM models and everything is ready, so it will circulate with everyone. Actually, it gets circulated even in the beginning stage. There will be a common platform to share the details. So, like that way, all the details will get shared in a common platform. And then with the BIM 360, all the relevant documents and everything will reach at the site.
And all the site engineers and even the workers at the site. So, they will get all these latest drawings set and then the construction will happen at the site. So, once the construction and everything is complete, all these like concreting, then the superstructure and like all the interiors and all everything is done. Then the as built is shared with the client and at the same time, all these facility management and all this happen at this as built stage. So, this is the life cycle of BIM.
So, in this stage, architecture like engineering, construction, like all these work will happen and the architect, engineers and the labors and owners, all these people will take part in this entire process. Then comes the use, as I mentioned, as I mentioned, this is the life cycle, just a recap, pre-design stage is there, schematic design, design development, construction documentation, construction stage and as built. Okay. So, design conflict can be identified early in the project. So, many times I mentioned in the previous session, like how conflict can be identified.
So, once the architect is complete his or her part, then the structural engineers and even the MEP team, all the other trade partners are involved and they all will share a model with the coordination team. So, they will run clash detection and they will run clash detection and they can identify all these clashes before the construction itself. Okay. So, before this construction stage, all these things will cover in this stage. So, all the conflict can be identified and resolved before the construction. So, all the BIM engineers, BIM modelers and all these people are involved and they create a BIM model and with that BIM model only construction documentation is generated.
So, because the BIM model is just a replica of what is happening at the site. So, because of that, we can extract accurate information from the model. So, the quantities like how much sand or like how much cement, water, all these information, we can get to know prior to the construction. And even the budget also, we will be able to know before the construction. And so, we can easily do a budget tracking like whether we are overestimated or whether we are underestimated. Like all those things can be tracked easily with the help of BIM model.
Better coordination with all disciplines. So, this is as I mentioned earlier, different N number of if it's a multi-store structure or like if it's a airport or like if it's a large township. So, there will be N number of contractors involved. So, there will be proper coordination between these trade partners. Since we have a common platform, everyone can access different set of drawing or information related to that particular work. So, there will be a proper coordination. Like in the normal process, like one person need to finish something.
And then only then if architect finish something. So, other person need to wait for architect to finish his or her work. Then only another person can enter. So, because of this BIM, N number of people can collaboratively work and like they can coordinate each other. So, better control on time, cost and quality. So, as I mentioned just at this point, like the quantification and budget estimation is accurate. So, like if we can create an accurate quantification or estimation. So, then of course, there will be control on time, cost and even the quality.
The quality like many modular construction and many prefabrication works are involved in this. Because of that, all these modular parts, prefabricated units, everything is built in a factory. So, there the manual errors are really less. So, most of the cases, they automate everything. So, there will be robotic arm or some other new technology will be there to create or like to build some parts of the building. So, there is no need to compromise anything on the quality. Then increase productivity and efficiency. Because the many, as I mentioned, the modular prefabrication automation, because of the, all of all these things, we can increase the productivity and even the efficiency.
And a third point is like, there won't be any rework. So, because of that, we can increase the productivity and efficiency. Help, helps analyze project constructability. Like, we can, we will be able to analyze whether the beam can run through a particular location, whether there will be any clash between the beam and the mechanical duct. So, all those things, we can analyze before the construction itself. Ease of access to information. So, we have a collaborative platform for all the beam projects. Easy to access the information because of this collaborative platform.
And increased predictability of project delivery and reduced risk. So, many AI, VR and AR, everything is involved in this beam process because of the crane movement. And everything is controlled prior to the construction. And, like, even the movement of the trucks and even material import. All these things are done prior to the, like, analyzed prior to the construction. Because of that, risk involved is really less. And the project delivery, like, because we are making a track on everything. Like, we are creating a 4D model. In the 4D model, we can see, like, on December 25th of 2021, how much portion of the building can be constructed.
All these things can be seen very. Prior to the construction. If it's not happening as per the schedule, what people can do is they can give more resources to that particular project. Those things can be managed and controlled very prior to the construction. Enable faster and better planning, design and construction. So, because of these things planned very prior to the construction, there will be, of course, there will be better planning, design and construction. Facilities improve communication between stakeholders because there is a collaborative platform like BIM 360, Autodesk BIM 360 and even other platforms are there.
Then it's easy for different stakeholders to communicate each other. Help in better decision making in all stages. This is because each stage people are communicating each other through different platform like teams and other things are easily available. Because of that, the communication part is really easy. The decision making and all can be done easily at the coordination stage. Reduced base, delays, errors and improved precision. As I mentioned, many things are automated and everything is pre-planned because of these base stages less and delay and errors and chances of errors are also less.
Yes. It's applicable to end their life cycle. Yes. So, BIM execution plan is created prior to the construction. And as I mentioned earlier, the ones we share the aspect model. So, these facility management is happened just before giving to the client. And even this will be there for the end their life cycle of the building because if you want to replace something. So, the facility management team will get notifications like there is some issue with this particular equipment. All those things can be resolved and all those things can be resolved. And because of that, it's tiddling. It's applicable to end their life cycle.
So, like BIM execution plan is created before the construction and even during the construction process. So, we are before the construction, we are creating the model. And even during the construction, if some changes happens because of some uncertain reasons, so that will also taken care. Once the building is completed, so the facility management team come into picture and they will take care of all the facilities in that. And if some replacement or something is there, then the facility management team will be involved in this. So, for the end their life cycle, like the BIM is involved in the end their life cycle of a building.
Okay. Okay. So, next is project delivery method. So, as you can see, like this is the typical organization, you know, project team, like, so these are the owner or the client will be there and they will be an architect, general contractor, engineers and other designers will be there, subcontractors and fabricators and the building product shippers will be there. So, this one represents the normal line represents the typical contract relationship and this relationship needed to build an integrated building model or to use BIM process. So, what is the architect? So, what is the architect? So, what is this mentioning is? So, an architect, so he or she will be directly communicate, will directly communicate with the subcontractors, fabricators and the building product shippers and even the general contractors.
And even the general contractors will be directly in touch with the engineers and other design team. So, there will be a collaborative approach. It's not like, so the architect is just finished his or her work and they give everything to the engineering unit. And so, here in the traditional process, the architect and the general contractor, they are not in touch with each other. So, but here there is a collaborative approach in the case of BIM. So, people can communicate with each other. So, people can communicate with each other and they can share their information with each other in a standard platform. So, it will be really easy to, for the smooth run of a project.
Okay. So, BIM project delivery method. So, here you can see that design, bid and build. So, like different teams are involved. So, this is mentioning the project timeline. So, if it's a design and build, only these are involved. If it's a collaborative approach, then how would it function? Then here the thing is like visibility, then the design, then the design part comes. Once the design part is completed. So, then the construction, the build team is involved and then there comes the pre-construction and construction. And then after that only operational stages coming into picture. But here once these two are work collaboratively. So, these two work collaboratively, then what will happen? We can reduce this project timeline.
Like, so, at this stage only, it will start operating. So, but once there is a, if there is some percentage of collaborative approach is there. So, then the project timeline we can reduce. Okay. So, but if everyone is work collaboratively, so then what will happen? So, the design and the construction team work in a collaborative environment. So, so we can save this much amount of time. So, we can save this much amount of time. So, the one main reason is like, so the design and the construction will happen parallelly. So, all, so here the situation is once the design team need to finalize everything, then only the building like pre-construction team starts his or her work.
So, so it will take more time. So, it will take more time than the collaborative approach. So, it will take more time than the collaborative approach. So, what will happen? Once the design team finalize their 30% CD drawing or like if their percent are 10% like 60% CD drawing, the same time the construction team, the like pre-construction team start his or her work. And so, so they will work collaboratively once they are done with the 100% CD. Then they will share with these people and then the documentation and construction, all these things will work collaboratively.
So, because of that, we can reduce the project timeline and we can hand over the building to the client or the to the owner very prior to the normal project timeline. So, these are the conventional practice, the paper, paper and like pen and paper based workflow, the linear process, centralized or distributed collaboration, people and the process working in silos. So, in this case, in the case, in the case, in the case of BIM shift towards digitalized workflow, cyclic process and centralized common like common data and environment collaboration.
So, I will explain all these points. People, people, people, process, technology, level of development. So, there will be common point with that, different people share all the documents. Okay. So, here one architect will be there, he or she will complete the process, then it will share to other set of people. Like, so here comes a linear process. So, let's start with the first point. So, everything is done with the help of pen and paper. So, all the drawings are created and like all the we need to take a print out and like everything is done with the help of pen and paper and this documentation will be really helpful, really hectic and there won't be enough space to store all the paper.
And there will be chances for missing everything. With the help of BIM or everything is stored in a software. So, the work, the people, the labor who are working at the site, they will, they can picturize everything clearly in just in a one click. So, So, So, Usually what is happening nowadays, what is happening at the site is like, so site engineer will have an iPad, all these pre-created models or the BIM models will share with these people at the site and they can visualize everything at the site.
So it is really difficult for a labor to understand a standard set of drawing, so that 2D drawing and it will be really difficult for him or her to imagine everything, what is we are seeing in a 2D picture. So if we share something 3D, so they can visualize, they can visualize these things really easy and they can do the construction and everything, like they can imagine everything at the, before construction and they can work really fast. Then comes the linear process and the cyclic process, so the, as I mentioned there will be a common data environment, so there all the informations are stored and all the information related to a model is stored in a 1 BIM model, like the structural details, architectural, MEP, all everything is stored in a single building, but in the linear process, but in the linear process is like MEP, once the electrical drawing set are released, so that will be separate and the other set of drawings, all these things will be separate.
So there won't be any cyclic process approach, then the people and the process like, so here in the conventional practice, only people and the process is involved, so no technology is involved. So here in the, in the, in the case of BIM, the technology is involved, because of that, we can reduce time, we can reduce course and we can increase the quality. In the conventional process, like most of the, most of the teams are working as, as silos, so there won't be any collaborative approach. So, so, but in the case of BIM, so many people are working as a, as one unit, and so the detailing and level of development and all is really good, if we go with the BIM approach.
Then, uh, in this traditional approach, like, uh, people are using CAD drawings, only 2D drawings, but here comes the, uh, 3D, uh, drawings are there, then their, uh, accurate representation of the existing condition, the point clouds, and the surface, everything, uh, even the surface finish, and everything we can see prior to the construction. Like, uh, like, uh, what are the texture of this particular, uh, wall, or particular door, or particular window, all these things we can know before the construction. Uh, here, uh, in the traditional approach, the 2D base coordination is happening.
So here, the multidisciplinary model base coordination and the class resolution is happened before the, it will happen before the construction itself. Then, uh, uh, impact, uh, impact on, uh, ability to incorporate changes is high. Like, uh, the thing is, like, many changes will happen, uh, like, uh, um, before the construction, sometimes the, there'll be, uh, difficulties, uh, with running the plumping line, and there'll be some difficulties with the running, uh, electrical or, like, mechanical unit. And those kind of impact is really, will be really less in the case of a BIM model.
So here in the, uh, traditional design method. So line-based drawing documentation. So as I, I think I mentioned in the previous session. So in the traditional approach, most of the things are happened, like, uh, created in a 2D set. And, like, all the drawings are created based on lines. And the documentation is really difficult. So there'll be manual effort. So if I wanted to make something, uh, some changes in, uh, 3D, 2D. And so we, I need to go to each set of drawings. So I need to go to 2D and make the changes.
Then section view, I need to go and make changes. And similarly, I need to go and make changes in the 3D view. So many manual effort is really high. But, uh, in the case of BIM model, we have Dynamo, Revit, and Grasshopper. Because of, with the help of those, we can automate the repetitive task. So I'll be covering the Revit and Dynamo, those things in the upcoming, uh, sessions. So the parametric modeling with the, uh, intelligent object. So this one, I, uh, explained, uh, with the help of a door.
So if I wanted to change something, uh, like, uh, 4000 door, I need to make changes only at one location. And it will automatically reflect, uh, at the, uh, at all the other locations. Object inconsistent with the project. So it's here. So we need to model every, uh, each and everything separately. So there will be chances for inconsistency. And here, uh, in the, uh, uh, design, uh, in the BIM model. So accurate representation of the existing condition. Like, uh, point, cloud, surface, and everything. Prior to the construction itself, we will get to know the climatic condition.
And the wind flow, all these things we can know before the construction. And we can make the model. And we can make the surface. And we can make the, uh, make, uh, make the changes according to the existing condition. So this is all about, uh, conventional practice with the, uh, uh, with versus BIM. So then comes the BIM fundamental dimensions. So there are different dimensions of BIM. So the first is 3D, 4D, 5D, 6D, 7D. So 2D, uh, so first is 2D. 2D is X and Y.
So normally CAD. And the 3D is like X and Y and Z. So we can visualize everything in a 3D picture. And, uh, here, uh, with the help of Revit and all, we can see the 3D image, right, of a door, of a building, or, uh, anything. So then if we add time to that, that is the 4th dimension and of BIM. And if we add course to that, then it is called the 5th dimension of BIM. And if I, if we add life cycle information, that is called the 6th dimension of BIM.
And, uh, finally, 7th dimension. So there are different levels of BIM. Uh, like, just start with level 0. Uh, it's, uh, in 90s and all. So it was level 0, that is CAD. Uh, so everything is, uh, based on a vector line. Then comes the, uh, BIM level 1, 2D and 3D. The smart 3D, uh, in that include the model plus information. And so all the data and everything is shared during, uh, sorry, shared using PDFs and the CAD drawings. Then the, then the next level is level 2.
Their BIM process started implementing BIM process. And the, uh, people started working collaboratively. And so this is now the stages like, uh, uh, shifting from level 1 to level 2 in India. And so in many locations, it started with, uh, uh, like planning to start in, in level 3 stage. So most of, in most of the countries and like, um, in most of the companies. So it's, uh, progressing from level 1 to level 2. And, uh, so in the level 2. So the BIM process, collaborative workflow.
And the model based coordination using cloud platform. So there are different platforms available, uh, for the coordination. So now this works is a one of one such platform. So there the class detection and everything is, uh, doing at that particular, uh, platform. And then the final one is level 3. Lifecycle management BIM platform with a complete integrative process. So this is not, uh, come into picture actually. Like, yeah, it started the life cycle management and all. So not, it's not in a completely implemented stage. So level 2 BIM, uh, process.
The key project complaints factors are like, uh, process and standard to be used. And the BIM protocol included in the project and contract. Document and participants and pre-qualified on BIM capability before appointment and the employer's information requirement given. So these things are like BIM execution plan and the BIM capability assessment and the project implementation plan prepared, the common data environment used. So whenever we implement level two BIM process, we need to, we need to take care of all these factors like the process. So we need to use BIM, like we need to follow the BIM protocol and so there should be a qualified person who can handle the BIM process and like, so before implementing it, like before starting a project, so people should know like the capability of the team who can implement BIM and all the information should be given, employers should be given all the relevant information and there should be a BIM execution plan and all these things should be prepared before the construction and there should be a common platform to share all the information relevant to the project. And to the continuation to that, so digital plan of work that is tasks, deliverables, lists, participants, roles and responsibility, level of detail and level of information stages should be detailed out.
Like who, like who, who is doing this particular task, who is responsible for this particular task, when we will deliver this particular project, like who all are the participants or who all are the subcontractors, who all are the stakeholders, all this information and at what level of detail we will be sharing the model and the level of information at each stage. All these things should be planned before the construction itself, all these things should be planned before the construction itself and the roles and responsibility, what is the responsibility of a BIM engineer, what is the responsibility of a BIM coordinator and what is the responsibility of BIM manager.
All those things should be mentioned prior to the responsibility of a BIM manager, all those things should be mentioned prior to the construction and the responsibility metrics should be created. So task information delivery plans and the master information delivery plan should be prepared. So as I mentioned, like what all are the tasks involved and what all the information required and what are the information that we should supply. So all these things should be prepared early, all the drawings and schedule outputs are delivered from BIM. So no, no zero BIM.
So I, I mentioned what is zero BIM. So zero, I'm just repeat it once again because it most, uh, it's a new thing, right? So there are many companies like, uh, many companies who are, uh, getting information, like, uh, all the drawings and schedules. They use these particular drawings and schedules and then they create BIM model, but this should not happen. Everything should come from a BIM model. There should not be any pseudo BIM and the federated model use model being used for coordination, flash detection, sequencing, programming, I mean, and planning, quantity takeoff, like, uh, curve and course control and the performance analysis.
So all these, so all the models, uh, the different stakeholders will be involved and these people will share the model and these models should only use for the class detection because, uh, these are coming from the different contractors. And so class detection should be made using these particular model and like, if there are any issues, like any clashes, then, uh, BIM coordinator, they, they should invoke, they should inform these particular contractors and they should make, uh, a class free model. Then once the class free model, like, uh, these quantity takeoff and the performance analysis and planning, scheduling, sequencing and programming, everything can be done after that.
Then operational asset information models for facility management, that is the seventh dimension of BIM. So as I mentioned, once the facility is created at the same point of time, these facility management team come into picture and they will, uh, create, uh, create an asset information, like what all the facilities available in this particular building, all these things should be created, uh, before handing, uh, over the, this to the client. But these facility management team will be there, uh, for the entire life cycle, because they will be making changes and they'll be giving their suggestions and all.
Then comes the BIM file exchange format. People use different types of software for each task. So many are, uh, for, uh, example, for steel modeling, some companies might use Tekla. And some companies you, uh, for architectural Revit and like that way. So different companies will be using different BIM softwares. So the, the, the, there is a file format for, uh, sharing the file that is called IFC industry foundation class. IFC format is the base information carrier because with this, like, uh, once the steel structure is completed, the IFC is exported from Tekla and this can be used in Navish.
So there, so there, flash detection and all is done. Then other aid, uh, aids information exchange between different software platform for coordination between different process and stakeholders. And developed by building smart and contains all graphical and metadata of the project, geometry, attributes, location, etc. In this IFC file, we'll have all these informations. Then BIM CD. So this, we, uh, mentioned this, uh, at many locations, common data environment. So, so there'll be a common platform. So there we have contract drawings, uh, construction documents, all the models, schedules, and everything is, uh, shared at the common, uh, platform.
So, all the stakeholders, contractors, and all these people can access all these information from a common environment. The information sharing in BIM level two CD accesses central repository for all project related information. So, as I mentioned, so all these information are available at a common location. CD help in managing and distributing project information for different project teams at a different defined collab, uh, controllable access level. So, uh, uh, this, even this one is also, uh, uh, explained many times. Like there is a common platform there from that platform, all the stakeholders can, uh, uh, take all the information.
And CD platform generally hosted on a cloud sharing platform or the external server accessible to all the stakeholders, holders of the, of a project. So, uh, uh, so mostly, uh, uh, different, um, um, collaborative platforms are there. In that one, one of the most trending and most, uh, useful links, uh, autodesk BIM 360. Then, uh, EIR, employers information requirement. So, in this, the outline of, uh, outlines the project requirement of the employer. So, what are the project requirements, like how many area, how many levels, how many, all these information will be available in this EIR.
Highlights level of modeling detail, management process, and the data exchange format, etc. So, as I mentioned earlier, like modeling details, like, so, like which all details we need to add, like which are level, like LOD level of detailing, the management, how to manage all the documents and how to manage all the workers and how we need to exchange the information, like which are the file format we need to use, whether go for the IFC format, or like .RVT or NWC. So, all these file format, all these information will be available in EIR.
Then comes BIM execution plan. It is a redundancy document signed between parties to meet the requirements. EIR. So as I mentioned here the file format in a BIM execution plan also. So BIM execution plan I'll be covering in the seventh session. So all the parties will meet together and like there will be information like who like roles and responsibilities, how what are the responsibilities of a BIM engineer, BIM coordinator and BIM manager all those things will be there. What are the file format we need to use that will be available and nomenclature. So how we need to share a file, the nomenclature what we need to follow, the delivery time and the quality check.
All this information will be available in the BIM execution plan and this one is created very prior to the BIM implementation stage and it will share with all the stakeholders and even for the contractors and we will get a signature from each and every contractor. Then only we will start implementing this BIM. Highlights, the responsibilities and roles of stakeholders, methods, BIM deliverable format, the process with respect to different milestone. All this information will be available in the BIM execution plan.