Challenge

Reinforcement detailing of Columns from ETABS output

  • REINFORCEMENT DETAILING OF COLUMNS FROM ETABS OUTPOT :
  • QUESTION :
  • The ETABS file for a G+4 building is provided. Run the analysis and design the RCC Moment Resisting Frame. The following challenge deals specifically with two columns at the following grid intersections.
  • 3A
  • 3B
  • Provide details of longitudinal reinforcement for the two columns, from foundation to terrace level. Sketch the column cross sectional & elevation details or draft it using autocad software.
  • Show shear reinforcement & lapping details as per special confining reinforcement provision of clause 8.1 of IS 13920 - 2016.
  • AIM :
  • Reinforcement detailing of columns in Etabs 2018.
  • BUT I HAVE ETABS VERSION 2017 SO I USED THE ETABS 2017
  • PROCEDURE :
  • STEP 1
  • Start the etabs 2017 software
  • then homepage of etabs software is open
  • from that homepage click on New project option
  • then click on File tab
  • click on Import option
  • select the b2k file and open it
  • STEP 2
  • Go to the terrace view
  • select the all story option
  • select the column 3A and 3B
  • then Right click
  • and click on show selected object only
  • Go to the 3D view
  • STEP 3
  • RUN Analysis :
  • STEP 4
  • Calculate longitudinal reinforcement
  • so that click on concrete frame design key
  • wait for some time for results
  • then click on Elevation view
  • select the along grid A and click ok
  • RESULTS :
  • Check the longitudinal reinforcement along grid 3
  • so then click on elevation tab
  • select the grid 3
  • click on APPLY and then ok
  • STEP 5 :
  • Check the shear reinforcement
  • click on concrete frame design option
  • one dialogbox is open
  • from that click on display design information
  • again one new dialogbox is open
  • select the share reinforcing
  • click on apply and then ok
  • STEP : 6
  • we need to draft the column details on an AutoCAD.
  • The reinforcement details for the column 3A is given as
  • Here the maximum longitudinal reinforcement required is 7027mm².
  • Hence, provide 8 no.s of 32mm dia bars and 2 no.s of 20mm dia bars which together contributes an Ast of 7060mm²
  • Now, for shear reinforcement, the maximum reinforcement area required is 720mm2.
  • Hence, provide 10mm dia bars @ 150mm c/c at zone A and a spacing of 100mm c/c at zone B (at splicing location and near the beams) which contributes to an Ast of 1570mm² and 2355mm² respectively.
  • STEP 7
  • The reinforcement details for the column 3B is given as:
  • Here the maximum longitudinal reinforcement required is 5046mm².
  • Hence, provide 4 no.s of 32mm dia bars and 6 no.s of 20mm dia bars which together contributes an Ast of 5100mm²
  • Now, for shear reinforcement, the maximum reinforcement area required is 720mm2.
  • Hence, provide 10mm dia bars @ 150mm c/c at zone A and a spacing of 100mm c/c at zone B (at splicing location and near the beams), which contributes to an Ast of 1570mm² and 2355mm² respectively.
  • RESULTS :
  • The given Etabs model has been analysed after checking the model.
  • Then concrete frame design has also been carried out hence the reinforcement area required has been obtained.
  • The longitudinal reinforcement details obtained from the results have been drafted in AutoCAD software.
  • Similarly the shear reinforcement details also have been drafted.
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.